CompTIA Project+ Certification (2024) Questions and Answers
During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
Which of the following is a quality assurance tool?
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
A team member identifies a critical issue in production. Which of the following should the project manager apply?
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
Which of the following tools is best to use when conducting project meetings across time zones?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
Which of the following activities should a project manager perform during the closing phase? (Select three).
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:
Average worked hours
Which of the following describes the result?
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
Which of the following statements best describes a content management system?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
• Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
Which of the following best represents the project impact to a company's brand value?
A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?
An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?
A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
A project team member wrote a user guide over the past ten days. Given the following scatter diagram.
Which erf the following can be formally conducted?
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:
Based on the chart, which of the following is the current status of the project?
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
Which of the following is a characteristic that defines a project?
Which of the following items must be protected as Pll? (Select TWO).
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:
Which of the following most likely represents the number of items in the backlog?
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
Which of the following offers administrators more direct control over operating systems?
An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?
A)
B)
C)
D)
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
• Two developers
• High uncertainty about existing systems
• Risk of frequent requirement changes
• Tight deadlines
Which of the following project methodologies would be best to use in this situation?
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?
Given the following network diagram:
Which of the following is the critical path?
Which of the following aspects are true of agile as compared to waterfall? (Select two).
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?
Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?