Planning & Scheduling Professional (PSP) Exam Questions and Answers
What is the remaining work duration of Active D?
Resource planning must take all of the following into account except for:
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
Activity C is a
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
Which of the following is NOT a tool or technique used to perform scope planning?
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
Project delays are best analyzed
Determine the correct formula and date for the late finish for Activity 2001.
Who will receive the most benefit from a master schedule of the Spring Highway project?
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Which of the following will always describe the critical path? The path with
Determine the driving activity for Activity 10001.
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.
PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.
Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
What is the result of a forward pass calculation?
Why does activity 1001 have two successor activities?
Determine the correct formula and date for the late start for the Activity 11001:
What day would Activity C complete if the duration of Activity A was reduced by five days?
The activity with the most total float is:
What is a critical path method schedule?
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
Which of the following is NOT input data to the construction planning process?
A good change management plan___________.
What is the actual duration as of the status date or data date of Activity B?
At the end of month one, did the delay to the parking structure foundation delay the project?
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
Determine the correct formula and date for the late finish for Activity 2002.
Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?
Which of the following parties is NOT a stakeholder of the Spring Highway project?
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
What was the original planned duration for Activity A through Activity G?
What is the cycle time?
How many workdays occur from the start of the Product Testing to the Product Available milestone?
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
Which of the following phases does NOT describe the commonly accepted construction life cycle?
Project schedules help control all of the following EXCEPT for_____________________.