Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dumps65

USGBC LEED-AP-BD+C Dumps

Page: 1 / 30
Total 304 questions

LEED AP Building Design + Construction (LEED AP BD+C) Questions and Answers

Question 1

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

Options:

A.

50,000 ft2 (4 645 m2) office project

B.

80,000 ft2 (7 432 m2) hospital project

C.

110,000 ft2 (10 219 m2) school project

D.

140,000 ft2 (13 006 m2) retail project

Question 2

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

Options:

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

Question 3

A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content. Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?

Options:

A.

$75

B.

$150

C.

$750

D.

$1,500

Question 4

What is the maximum number of points a project pursuing LEED for New Construction can achieve under Location

and Transportation Credit, Access to Quality Transit?

Options:

A.

Two points

B.

Three points

C.

Four points

D.

Five points

Question 5

Which of the following is the location of CO2 sensors in naturally ventilated spaces to comply with the Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Options:

A.

At least 6 ft. (2 m) above the floor

B.

At least 3 ft. (1 m) away from windows

C.

Between 3 ft. and 6 ft. (1 m and 2 m) above the floor

D.

On the ceiling 3 ft. (1 m) away from adjacent walls

Question 6

According to the Integrative Process Credit, Integrative Process, the goal-setting workshop should identify

Options:

A.

potential project sites

B.

targeted LEED credits

C.

expected water demand

D.

expected energy demand

Question 7

A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

Options:

A.

No action is necessary as the PV system is not required to be commissioned

B.

The PV system installer should commission his own installations and share the results with the project owner

C.

The Cx agent for the project must conduct or oversee the Cx of the PV system

D.

The building's mechanical engineer should commission his own installations and share the results with the project owner

Question 8

Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite,

Storage and Collection of Recyclables?

Options:

A.

Take appropriate measures for the safe collection, storage and disposal of batteries

B.

Make a waste stream projection for the entire year based on the six hours of the waste stream study

C.

Make a waste stream projection for the entire week, based on the six hours of the waste stream study

D.

Extend the waste stream study to cover a representative time period of a minimum of 24 hours to identify the top five recyclable waste streams

Question 9

Which of the following are the major factors determining the total irrigation requirement for a particular landscaping design?

Options:

A.

Planting density, soil conditions, irrigation efficiency and rainfall

B.

Relative humidity, site exposure, plant species and planting density

C.

Plant species, rainfall, evapotranspiration rate, site exposure and irrigation efficiency

D.

Plant species, rainwater tank size, evapotranspiration rate, site exposure and irrigation efficiency

Question 10

A construction manager is looking for a project management tool that offers energy management strategies, benchmarking software tools for buildings, and product procurement guidelines. Which of the following is recognized by U.S. Green Building Council to assist them?

Options:

A.

Green Seal

B.

SCAQMD

C.

ENERGY STAR®

D.

SMACNA

Question 11

Which of the following is required to earn Energy and Atmosphere Credit, Renewable Energy Production if using a Solar Photovoltaic System?

Options:

A.

Carbon offsets

B.

Daylighting strategies

C.

Passive solar strategies

D.

Produced electricity consumed on-site

Question 12

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper

Options:

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

Question 13

For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include

Options:

A.

verification that a weighted daily average has been used for each qualifying route

B.

confirmation that functional entries of the project are within 3/4 mi. (1.20 km) of the stop

C.

verification that a weighted building average has been used for each qualifying functional entry

D.

confirmation that each qualifying route features paired route service (service in opposite directions)

Question 14

Building Product Disclosure and Optimization is based on market

Options:

A.

reliability

B.

durability

C.

transparency

D.

consumption

Question 15

What is the best strategy for a LEED AP to suggest in order to quantify the impact of increasing the window-to-wall ratio on a Building Design and Construction project?

Options:

A.

Compare the current project to other similar projects

B.

Monitor the HVAC loads throughout the life of the project

C.

Perform a simple box energy model before the completion of the schematic phase

D.

Review Green Business Certification Inc. (GBCI)'s comments on the energy model submission

Question 16

Location and Transportation Credit, Reduced Parking Footprint calculations must include

Options:

A.

motorbike spaces

B.

on-street parking in public rights-of-way

C.

parking within 1/4 mi. (0.40 km) radius of the project boundary

D.

parking outside the project boundary but used by the project

Question 17

Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?

Options:

A.

Energy and Atmosphere Credit. Demand Response

B.

Energy and Atmosphere Credit. Advanced Energy Metering

C.

Energy and Atmosphere Prerequisite. Minimum Energy Performance

D.

Energy and Atmosphere Prerequisite. Building Level Energy Metering

Question 18

A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for

Options:

A.

natural gas

B.

hot water at the main service point

C.

nothing, because the flat fee is included as part of the lease

D.

nothing, because the energy source is outside of the project's scope

Question 19

Showers are addressed under which prerequisites and/or credits within LEED Building Design and Construction?

Options:

A.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Indoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

B.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Water Efficiency Credit, Water Metering

C.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

D.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Cooling Tower Water Use; and Water Efficiency Credit, Water Metering

Question 20

What is the sequence of the process for LEED certification?

Options:

A.

Submit documentation through LEED Online, Choose Rating System, Review, Register, Certify

B.

Submit documentation through LEED Online, Choose Rating System, Register, Review, Certify

C.

Choose Rating System, Register, Submit documentation through LEED Online, Review, Certify

D.

Choose Rating System, Register, Submit documentation through LEED Online, Certify, Review

Question 21

In Sustainable Sites Credit, Light Pollution Reduction, which factor is included in the lamp lumen uplight calculation?

Options:

A.

Total fixture power

B.

Site area of the project

C.

Quantity of installed luminaires

D.

Total fixture lumens below 90 degrees

Question 22

A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be desirable considering the location of the project?

Options:

A.

Energy and Atmosphere Credit, Optimize Energy Performance, Exemplary Performance

B.

Indoor Environmental Quality Credit, Quality Views, Exemplary Performance

C.

Indoor Environmental Quality Credit, Acoustic Performance, Exemplary Performance

D.

Energy and Atmosphere Credit, Enhanced Commissioning, Exemplary Performance

Question 23

The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve

Options:

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,

Option 2. Leadership Extraction Practices

B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,

Option 1. Raw Material Source and Extraction Reporting

C.

Materials and Resources Credit, Building Product Disclosure and Optimization Environmental Product

Declarations, Option 1. Environmental Product Declarations

D.

Materials and Resources Credit, Construction and Demolition Waste Management, Option 1. Diversion

Question 24

When a project team sustainably develops a project site, the design should

Options:

A.

increase water runoff

B.

maximize construction pollution

C.

remediate sites already in decline

D.

replace natural water flow patterns

Question 25

A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles. What action must the project take to meet the Option 2 requirements?

Options:

A.

Install a preferred drop-off lane for buses meeting the emission requirements

B.

Provide calculations showing that the average fleet bus meets the emission requirements

C.

Inventory the school fleet to develop and create a plan for all buses to meet the emission requirements

D.

Document that all buses serving the project achieve a minimum green score of 30 on the American Council for an Energy Efficient Economy (ACEEE) annual vehicle rating guide

Question 26

A project design team for an elementary school project is attempting to achieve Innovation Credit, Innovation, Option 1. Innovation. Which of the following strategies would qualify?

Options:

A.

Pilot Credit from LEED Pilot Credit Library

B.

Exemplary Performance in Energy and Atmosphere Credit, Optimize Energy Performance

C.

Create educational kiosks and posters around the school with picture of building systems' sustainable features

D.

Implement a building as a learning lab curriculum that has been piloted in three other primary schools in the district

Question 27

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Question 28

For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to

Options:

A.

five bicycle trails

B.

at least eight diverse uses

C.

a restaurant, a grocery shop, a post office and two bus lines

D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary

Question 29

During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?

Options:

A.

Green roof

B.

Site conditions

C.

Massing and orientation

D.

Programmatic and operational parameters

Question 30

Which is a benefit of earning Regional Priority credits?

Options:

A.

The LEED project can achieve more sustainable outcomes by recognizing the issues that are a priority in the project's location

B.

The context of the project's location is not addressed, allowing the project team to focus on the building's priority issues

C.

The project's operations are considered separately from design and construction, allowing the project team to focus on regional issues

D.

The LEED project is able to skip a review phase by considering the issues that are a priority in the project's location

Question 31

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractor substituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

Options:

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner's Project Requirements

D.

Coordination of other contractors

Question 32

To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate

Options:

A.

all luminaires have full cutoff fixtures

B.

all luminaires have a minimum color temperature of 3500 K

C.

all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone

D.

all luminaires are mounted at least three mounting heights from the lighting boundary

Question 33

The LEED AP has identified a pilot credit that is relevant to the project. This would be documented in LEED Online as a(n)

Options:

A.

Exemplary Performance for a related credit

B.

Special Circumstances within a related credit

C.

Regional Priority Credit

D.

Innovation Credit

Question 34

Which approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management?

Options:

A.

Installing bioretention area

B.

Installing on-site renewable power generation facility

C.

Substituting impervious surface area with high-albedo paving materials

D.

Increase artificial turf on the roof

Question 35

For a new project with a $10 million construction cost, the weight of the total recycled content is 0.9 tons (816.5 kilograms) each for post-consumer and pre-consumer recycled content. The value of the total recycled content is one million each for post-consumer and pre-consumer recycled content. What is the percentage of recycled content that contributes toward Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2, Leadership Extraction Practices?

Options:

A.

33%

B.

20%

C.

40%

D.

18%

Question 36

A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the following suggestions should the LEED AP give to the project owner?

Options:

A.

Modify the design to enclose the performance areas

B.

Calculate the return on investment over the 20-year life of the project

C.

Compare the energy consumption against an alternative

D.

Inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction

Question 37

The Solar Reflectance Index (SRI) includes the measure of a material's

Options:

A.

color (shade of gray)

B.

ability to reflect solar radiation

C.

ability to absorb solar radiation

D.

ability to reflect thermal radiation

Question 38

What requirement must be met when creating a Demand Response Program that satisfies Energy and Atmosphere Credit, Demand Response?

Options:

A.

Permanently reduce the energy consumption in the building by 5%

B.

Demonstrate submetering of the two highest electrical end uses

C.

Demonstrate a load shift reduction of 5% in the building

D.

Create a comprehensive plan for meeting a demand response event

Question 39

What reference standard is used to determine compliance with the Energy and Atmosphere Prerequisite, Minimum Energy Performance when the whole building energy modeling option is used?

Options:

A.

ASHRAE 55-2010

B.

ASHRAE 90.1-2007

C.

ASHRAE 90.1-2010

D.

ASHRAE 62.1-2010

Question 40

What is the system boundary that a building life cycle analysis must be defined to account for?

Options:

A.

Cradle-to-gate

B.

Cradle-to-grave

C.

Cradle-to-cradle

D.

Cradle-to-building

Question 41

Which of the following criteria does a project need to implement in order to qualify for Sustainable Sites Credit: Site Development - Protect or Restore Habitat, Option 1?

Options:

A.

Use of natural plants rated for their effect in reducing the heat island effect, while also restoring a minimum of 20% (including the building footprint) of all portions of the site identified as previously disturbed

B.

Use of only native or adapted vegetation, along with not restoring a minimum of 36% (including the building footprint) of all portions of the site identified as previously disturbed

C.

Use of native or adapted vegetation, restoring a minimum of 30% (including the building footprint) of all portions of the site identified as previously disturbed

D.

Use of natural vegetation and not artificial greenery, restoring a minimum of 25% (including the building footprint) of all portions of the site identified as previously disturbed

Question 42

What is the first step to earn the Water Efficiency Credit, Cooling Tower Water Use?

Options:

A.

Select air-conditioner condensate for cooling

B.

Calculate cycles of concentration

C.

Identify the maximum number of cycles for the cooling tower or evaporative condenser

D.

Engage a water treatment professional to perform a chemical analysis

Question 43

Smoking is prohibited inside LEED-certified buildings in order to eliminate the health risks associated with environmental tobacco smoke. Which building type is exempt from this requirement?

Options:

A.

Office projects

B.

Healthcare projects

C.

Warehouse projects

D.

Residential projects

Question 44

Green Infrastructure (GI) and Low-Impact Development (LID) rainwater management strategies improve upon the conventional approach for rainwater management by

Options:

A.

replicating a site's natural hydrology

B.

discharging rainwater at a faster rate

C.

increasing a site's impervious surface

D.

providing a greater volume of rainwater detention

Question 45

What document allows a LEED AP to register a project and sign the Certification Agreement?

Options:

A.

Owner Confirmation of Agent Authority

B.

Architect Code of Professional Conduct

C.

Commissioning (Cx) Agent Construction Permit

D.

LEED AP Standard Form of Agreement Between Owner and Architect

Question 46

According to the Integrative Process Credit, the discovery phase of energy-related systems should identify

Options:

A.

ventilation rates

B.

functional performance tests

C.

thermal comfort ranges

D.

transportation options

Question 47

What is the average flush rate for a dual flush toilet with a high flush rate of 1.6 gpf (6 lpf) and a low flush rate of 1.05 gpf (4 lpf)?

Options:

A.

1.05 gpf (4 lpf)

B.

1.19 gpf (4.5 lpf)

C.

1.23 gpf (4.66 lpf)

D.

1.32 gpf (5 lpf)

Question 48

Which of the following items must have safe collection, storage, and disposal for Materials and Resources Prerequisite, Storage and Collection of Recyclables?

Options:

A.

Food waste

B.

Medical waste

C.

Electronic waste

D.

Landscape waste

Question 49

An office project has the following items in its break room kitchen: a kitchen sink, a residential-style dishwasher, and a coffee machine. How would these items be addressed in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

The kitchen sink is included in fixture calculations, the dishwasher and coffee machine must be ENERGY STAR® or performance equivalent

B.

The kitchen sink is included in fixture calculations, the dishwasher must be ENERGY STAR® or performance equivalent, and the coffee machine is not included in the prerequisite

C.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine is not included in the prerequisite

D.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine should be included in fixture calculations

Question 50

A rectangular office building is located in an extremely humid climate and is shaded by very large adjacent buildings

on all four sides. If the building owner wants to decrease the annual energy cost for operating the building, which of

the following would be the best design approach?

Options:

A.

Install glazing with a higher solar heat gain factor

B.

Install photovoltaic panels on the sides of the building

C.

Increase outdoor air intake quantities during summer months

D.

Recover waste energy through exhaust air energy recovery systems

Question 51

Which strategy can maximize the efficiency of water use in an irrigation system?

Options:

A.

Determine a set rate of irrigation and avoid adjustments

B.

Set the irrigation controllers on a timer

C.

Incorporate precipitation sensors with smart irrigation controllers

D.

Space irrigation sprinkler heads for overlapping coverage

Question 52

A contractor wants to use an adhesive that exceeds the allowed Volatile Organic Compound (VOC) content limit under Indoor Environmental Quality Credit, Low Emitting Materials. This credit can be earned if

Options:

A.

the VOC budget method is applied for VOC content

B.

the adhesive is not included in the LEED documentation

C.

75% of the adhesives used comply with the VOC content limit and emissions requirements

D.

95% of the adhesives used comply with the VOC content limit and emissions requirements

Question 53

Which of the following strategies can be used to reduce the internal load of a building?

Options:

A.

Decreasing lighting power

B.

Oversize the HVAC systems

C.

Install low reflective exterior facade

D.

Increase the insulating value of the glazing and window frame system

Question 54

A project team develops a site plan for a school project with an athletic field and a playground with real grass. In order to qualify for the Water Efficiency Prerequisite, Outdoor Water Use Reduction, the landscape area calculations:

Options:

A.

Must include the athletic field and playground

B.

May include the playground but must exclude the athletic field

C.

Must include the playground but exclude the athletic field

D.

May include or exclude the athletic field and the playground

Question 55

If a commercial building is considered to have 100 peak visitors in a day, what is the minimum number of short-term

bicycle storage spaces that must be provided to earn one point under Location and Transportation Credit, Bicycle

Facilities?

Options:

A.

Three

B.

Four

C.

Five

D.

Ten

Question 56

Which of the following must be included in the Sustainable Sites Credit, Site Assessment?

Options:

A.

A targeted Brownfield remedy plan

B.

Historic preservation plan to include neighboring properties

C.

Proximity of vulnerable populations to major sources of air pollution

D.

The surrounding density within a 1/4 mi. (0.40 km) radius of the project boundary

Question 57

The Required Breathing Zone Outdoor Airflow Vbz for a new banking facility is 0.120 CFM/ft2 (0.6 L/s/m2). If the team decides to attempt Increased Ventilation under Option 2 in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies, what is the minimum Design Zone Outdoor Airflow?

Options:

A.

0.144 CFM/ft2 (0.73 (L/s)/m2)

B.

0.156 CFM/ft2 (0.79 (L/s)/m2)

C.

0.168 CFM/ft2 (0.85 (L/s)/m2)

D.

0.30 CFM/ft2 (1.5 (L/s)/m2)

Question 58

Which of the following actions should be taken to ensure that project team members understand and prioritize the selection of materials compliant with the Materials and Resources Credit: Building Product Disclosure and Optimization?

Options:

A.

Select locally sourced and manufactured materials

B.

Procure materials directly from raw material suppliers

C.

Include all building materials in a whole-building life-cycle analysis

D.

Include the material requirements in the project specifications

Question 59

The Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged Solar Reflectance Index (SRI) values for roofing material because

Options:

A.

SRI generally increases with age

B.

SRI generally decreases with age

C.

SRI generally remains the same with age

D.

SRI generally does not impact the Heat Island Effect

Question 60

A project team reviews office chairs with a Type III environmental product declaration (EPD) for the five different categories of environmental impact reduction. Which of the following must the chairs demonstrate for product optimization?

Options:

A.

A reduction in at least two categories

B.

A reduction below the industry average in at least three categories

C.

A 5% reduction in all categories

D.

A 10% reduction in GHG emissions and a 10% reduction in at least two other categories

Question 61

Which of the following strategies can be used to achieve a point in Innovation Credit, Innovation, Option 1.Innovation?

Options:

A.

Achieve 60% reduction in outdoor water use

B.

Implement an employee engagement and education plan

C.

Use on site renewable energy for 8% of the total energy needs

D.

Purchase green power for 100% of the total project energy use

Question 62

When calculating the reverberation time of a room, which of the following pieces of information is least relevant?

Options:

A.

Height and width of room

B.

Noise reduction coefficient of the ceiling surface

C.

Sound absorption coefficient of the floor surface

D.

Operating sound level of nearest HVAC equipment

Question 63

An existing vacant office building will be completely renovated and new mechanical, electrical and plumbing systems will be installed. 20% of the building's gross floor area will be complete at the time of certification. There will be a data center and some retail stores on the ground floor of the building at a future date. Which rating system is applicable for the building?

Options:

A.

LEED BD+C: Retail

B.

LEED BD+C: Data Centers

C.

LEED BD+C: Core & Shell Development

D.

LEED BD+C: New Construction & Major Renovation

Question 64

Which one of the following represents quality transit service as defined in Location and Transportation Credit, Access to Quality Transit?

Options:

A.

A bus stop served by two bus lines Monday through Friday, located 1/8 mi. (0.20 km) from the project building

B.

A rail station served by one train line Monday through Sunday, located 1/2 mi. (0.80 km) from the project building

C.

A rail station served by two train lines Monday through Sunday, located 1 mi. (1.60 km) from the project building

D.

A private shuttle bus stop providing hourly service Monday through Friday to a rail station two hours away, located across the street from the project building

Question 65

Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?

Options:

A.

Two Level (on, off)

B.

Three Level (on, 25%, off)

C.

Three Level (on, 50%, off)

D.

Three Level (on, 75%, off)

Question 66

A new commercial building is being designed to use small capacity air handling units. To meet the requirements of the Carbon Dioxide Monitoring strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Environmental

Quality Strategies, where would CO2 monitors need to be located?

Options:

A.

In each occupied space

B.

In each densely occupied space

C.

In each occupied space and outdoors

D.

In each occupied space over 500 ft2 (46 m2)

Question 67

A project has a potable water source as well as two alternative water sources. Which of the following statements is applicable for a project using two alternative water sources?

Options:

A.

A project may not use two alternative water sources

B.

Target the uses that require the least treatment first

C.

Match uses by location: indoor sources to indoor uses, outdoor sources to outdoor uses

D.

All alternative water sources should be treated to potable water standards

Question 68

What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

Options:

A.

One

B.

Two

C.

Four

D.

Six

Question 69

Which of the following products must always be included in Materials and Resources credits?

Options:

A.

Faucets

B.

Furniture

C.

Interior Paint

D.

Fire suppression system

Question 70

Under Energy and Atmosphere Credit: Optimize Energy Performance, Option 1: Whole-Building Energy Simulation, how can the energy cost savings be accurately determined?

Options:

Question 71

When working on a renovation project, asbestos containing materials have been found on the perimeter walls. When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be

Options:

A.

included in the calculation

B.

excluded from the calculation

C.

excluded if the total volume is less than 25% of the building being reused

D.

excluded if the total volume is more than 25% of the building being reused

Question 72

Which views would qualify as a quality view for Indoor Environmental Quality Credit, Quality Views?

as

Options:

A.

A, B, C

B.

B, C, D

C.

C, D, E

D.

A, B, D

Question 73

When the project occupancy is not known, which method is recommended?

Options:

A.

Default occupant density from ASHRAE 62.1-2010, Table 6-1

B.

Default occupant density from ASHRAE 90.1-2010, Table G3.1.1A

C.

Weekly average taken into account all the occupants in a typical 24-hour day of operation

D.

Occupancy measured for eight hours, between 8 a.m. and 5 p.m., for all occupancy patterns

Question 74

For an emergency care facility project, which of the following credits can be achieved if the total cost of

permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator?

Options:

A.

Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Material Reuse

& Innovation Credit, Innovation, Exemplary Performance

B.

Materials and Resources Credit, Furniture and Medical Furnishing, Option 3. Multi-Attribute Assessment of

Products & Innovation Credit, Innovation, Exemplary Performance

C.

Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2.

Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance

D.

Materials and Resources Credit, Furniture and Medical Furnishings, Option 3. Multi-Attribute Assessment of

Products & Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization

Question 75

What are the requirements of commercial projects for long-term bicycle storage under Location and

Transportation, Bicycle Facilities - Bicycle Storage and Shower Rooms?

Options:

A.

Provide for at least 5% of all regular building occupants, with no less than four storage spaces per building

B.

Provide for at least 10% of all regular building occupants, with no less than five storage spaces per building

C.

Provide for at least 15% of all regular building occupants, with no less than 10 storage spaces per building

D.

Provide for at least 25% of all regular building occupants, with no less than 10 storage spaces per building

Question 76

In the Indoor Environmental Quality Credit, Low-Emitting Materials, what types of products need to be evaluated for

both Volatile Organic Compound (VOC) content of the material and VOC emissions of the material?

Options:

A.

Flooring

B.

Furniture

C.

Composite wood

D.

Wet applied products

Question 77

In the calculations for Water Efficiency Credit, Outdoor Water Use Reduction, food gardens

Options:

A.

must be calculated using at least 20% from an alternative water source

B.

must be calculated using 100% potable water

C.

may be included or excluded from the calculations

D.

may be calculated using a standard 20% reduction from baseline

Question 78

Which of the following variables must be included in the calculations for Indoor Environmental Quality Credit, Quality Views?

Options:

A.

Ceiling heights

B.

Building furniture

C.

Movable partitions

D.

Permanent interior obstructions

Question 79

A building owner installs a building automation system (BAS) to allow programmable load control. Which of the

following credits can be pursued because of the installation?

Options:

A.

Energy and Atmosphere Credit, Demand Response

B Energy and Atmosphere Credit, Ongoing Commissioning

B.

Energy and Atmosphere Credit, Enhanced Commissioning

C.

Energy and Atmosphere Credit, Enhanced Refrigerant Management

Question 80

Which system is eligible for the Energy and Atmosphere Credit, Renewable Energy Production?

Options:

A.

Ground-source heat pumps

B.

Tidal-based electrical production

C.

Municipal solid waste combustion

D.

Passive solar and daylighting strategies

Page: 1 / 30
Total 304 questions