BICSI Registered Communications Distribution Designer - RCDDv14.1 Questions and Answers
A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?
Which two of the following items MUST be included in a detailed SoW? (Select two options.)
A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component protect requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.
What is a critical component of the Program Schedule Management Process?
A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.
At this stage of the program, what is the first step?
When designing an underground conduit system, a single bend should be NO MORE THAN ________ degrees.
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
For a backbone distribution system serving a usable floor space of ≈ 8,920 m2 (96,000 ft2), the MINIMUM slot area to be used for this back bone is
An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager can be successful in delivering the program's commitments
What should the program manager do to align stakeholders with planning and monitoring the program's progress?
A 3 trade size conduit is sized at
An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?
The program selection committee presents several programs for approval:
Which program was selected based solely on a three-year return on investment?
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not belong in the close-out phase.
Which of the following procedures should you removed?
Exhibit:
In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff
What should the program manager do to ensure communications on the component projects are consistent?
A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters
To ensure the realization of long-term benefits what should the program manager use?
A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations The high-level scope of this transformation encompasses three main areas.
1. The technology area—assessing which technology/tooling should be retained for the target data center
2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services
3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions
You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase
Which document should be present m your business case?
An ICT distribution designer is representing a client during a project execution. What is the designer's role in the Vendor and Contractor Coordination?
The program manager wants to increase the team's commitment to the program objectives. The program manager should do which of the following?
The type of apparatus housed in ERs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)
A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years
What is the expected time of delivery?
What is the MAXIMUM length of continuous conduit allowed before a pull point or pull box needs to be installed?
Smaller buildings with a serving area larger than 1000 ft2 and less than 5000 ft2 may be served by:
Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)
A critical program for a company fails lo delivers its intended benefits. The CEO and program sponsor are both held accountable and. ultimately, their employment is terminated by the board of directors
What should the program manager do before formally closing the program?
For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?
A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete
What should the program manager do to understand the financial environment?
A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation
Which of the following metrics should the PMO capture on a monthly basis?
For the MAXIMUM flexibility of a cabling system in a hierarchical star topology, ALL backbone cables and links to FR's should be terminated at the
In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.
To assure positive performance in the current environment, the program manager should do which of the following?
Exhibit:
What does this international symbol stands for?
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
What is the air change requirement for a tunnel of 610 m (2000 ft) long with a diameter of 3.4 m (11 ft)?
A small regional utility closes a customer rewards program and transitions it to operations The executive sponsor and program manager are concerned about the impact on benefits realization The program manager assures the executive sponsor that any corrective actions will be included in the next phase.
What should the program manager do to ensure a successful transition?
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk
What should the program manager do to monitor and control the supplier?
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?
What actions are taken in the process of developing and maintaining a program risk register?
Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)
Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?
The program manager leads a medical billing system integration program for company A. a health services provider Company A acquires smaller company X. which delivers health services strategically aligned with company A Company X uses a different billing approach than company A. Company A's chief information officer (CIO) seeks counsel on which solution would be the better option moving forward requesting the program manager's assistance.
How should the program manager respond to the ClO's request1?
An ICT distribution designer is providing labeling for a data center room number 2A, located on the second floor having 10 rows of cabinets. Which of the following identifiers/labels would the designer attach to the bonding and grounding conductor between the first cabinet in the 6th row and the data center ground bar?
Conducted coupling may affect electronic devices primarily through which two of the following means'? (Select two options.)
A client hired an ICT distribution designer who is designing some additional capacity for a customer owned aerial outside plant. Which of the following would be a PRIMARY consideration?
The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized
After further analysis of the performance indicators the program manager should do which of the following*?