EXIN EPI Certified Data Centre Specialist Questions and Answers

Question 1

The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?

Options:

A.

Vacuum the whole room using a HEPA/S-Class-based filter.

B.

Install air-scrubbers.

C.

Clean the room and racks with a damp/wet cloth.

D.

Provide more air changes per hour by adding more fresh air to the computer room.

Question 2

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

Options:

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

Question 3

Smoke sensors need to be tested to ensure that they pick up a potential fire in the data center.

What should you recommend?

Options:

A.

Test the sensors by injecting smoke or simulated smoke directly into the sensor

B.

Press the self-test button on each sensor in the data center

C.

Inject smoke at the floor level

D.

Test the sensors according to the vendor specification

Question 4

In which stage of the data center life cycle does commissioning take place?

Options:

A.

Retire

B.

Operate/optimize

C.

Implement

D.

Design

Question 5

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

Options:

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Question 6

You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.

What should you recommend?

Options:

A.

Review the cable lengths of each UPS to the common busbar

B.

Nothing, there is no reason for any concern

C.

Review the common mode noise levels within the computer room

D.

Review the harmonics levels within the computer room

Question 7

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

Options:

A.

PUE does not indicate efficiency

B.

Data center A

C.

Data center B

D.

Data center C

Question 8

Which formula is correct?

Options:

A.

Phase-to-Neutral Voltage = Phase-to-Phase voltage * 1.732

B.

Phase-to-Neutral Voltage = Phase-to-Phase voltage /1.732

C.

Phase-to-Neutral Voltage = Phase-to-Neutral voltage * 1.732

D.

Phase-to-Neutral Voltage = (Phase-to-Phase voltage * 1.732) / Phase-to-Neutral Voltage

Question 9

The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.

What is the most likely root cause?

Options:

A.

The cleaning crew is not doing their work properly

B.

Every computer room has high dust levels due to constant high-speed air movement

C.

Low pressure in the computer room

D.

Floorboards are most likely not fitted correctly

Question 10

What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?

Options:

A.

Cables should be loosely organized to allow for movement and be latched at the connectors.

B.

Cables shall be tightly organized to the rack and trays to avoid movement.

C.

Cables can be organized in any way as it is not important.

D.

Cables should be replaced by busbar trunking.

Question 11

The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

as

Options:

A.

Rating - 4

B.

Rating - 3

C.

Rating - 2

D.

Rating - 1

Question 12

When designing a data center network, your company wants to minimize the number of network switches to manage.

What type of physical cabling layout would be the best choice?

Options:

A.

ToR (Top of Rack) design

B.

EoR (End of Row) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Question 13

What is a potential disadvantage of using water mist as a fire extinguishing system?

Options:

A.

It only uses 10% of the water normally used in a water-based fire suppression, which might not be enough to suppress the fire

B.

It will rapidly increase the humidity level in the data center, which can cause a potential risk for the operation of the equipment

C.

It extracts oxygen from the air creating a potential risk for humans inside the computer room

D.

It has droplets that are too small (100-120 microns) so it can only be used for small fires

Question 14

The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.

What would be the best option?

Options:

A.

Do not use fire-rated glass due to the size limit and replace it with normal glass.

B.

Split the window in two equal parts using an aluminum frame.

C.

Split the window into parts smaller than specified as the maximum exposed area and ensure fire-rated frames are used.

D.

Split the window in two equal parts fitted together with transparent silicon glue.

Question 15

Do you need to consider blast protection when designing a data center?

Options:

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

Question 16

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

Options:

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

Question 17

What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?

Options:

A.

Two feeds coming from two different substations, one power company is not acceptable

B.

Two feeds coming from two different substations, one power company is acceptable

C.

Two feeds entering the data center building from one substation

D.

One feed from one substation split over two separated distribution boards in separate rooms

Question 18

What is the calculation for the desired attenuation factor for shielding material?

Options:

A.

A = 20 log (M / R)

Where

A is Attenuation

M is the maximum acceptable value

R is the real value measured

B.

A = M / R

Where

C.

A is Attenuation

M is the maximum acceptable value

R is the real value measured

D.

A = 20 log (R / M)

Where

A is Attenuation

R is the real value measured

M is the maximum acceptable value

E.

You do not have to calculate the attenuation factor for shielding material as it always has the same attenuation