Professional in Project Management (PPM) Questions and Answers

Question 1

Which of the following items should be considered when choosing the project team?

Options:

A.

Personality

B.

Skills

C.

Area of expertise

D.

All of the above

Question 2

True or False: You shouldn’t start planning for the end of a project until the end is in sight.

Options:

A.

True

B.

False

Question 3

True or False: Copies of the Crisis Management book or binder need to be available to everyone on a password protected server.

Options:

A.

True

B.

False

Question 4

What method can you use to budget for projects?

Options:

A.

Bottom-up

B.

Top-down

C.

Combination of bottom-up and top-down

D.

Any of the above

Question 5

True or False: Precedence is indicated by the sequence of tasks joined with a line and an arrow.

Options:

A.

True

B.

False

Question 6

A good communicator has which of the following traits?

Options:

A.

Credibility

B.

Trustworthiness

C.

Respectfulness

D.

All of the above

Question 7

A ______________________ is an organized form of brainstorming.

Options:

A.

Chessboard

B.

Checkerboard

C.

Game board

D.

Rules board

Question 8

Why are teams such a popular way of getting things done?

Options:

A.

You can complement each other’s efforts

B.

You can do more with less

C.

You can share ideas and brainstorm

D.

All of the above]

Question 9

The _____________________________ will include some important tools, such as a camera, flashlight, and safety tape.

Options:

A.

Spokesperson’s kit

B.

First responder’s kit

C.

Accident investigation kit

D.

First Aid Kit

Question 10

What should you do with e-mails that you won’t refer to in the future?

Options:

A.

Archive them on a CD or some other electronic storage

B.

Delete them

C.

Print them off and file them with your archive files

D.

Mark them as a spam

Question 11

Which of the following skills might a project manager need?

Options:

A.

Writing

B.

Speaking

C.

Persuading

D.

All of the above

Question 12

What are the three ways to end a project? (Choose three)

Options:

A.

Fulfillment

B.

Partial Fulfillment

C.

Premature Termination

D.

Priority Fulfillment

E.

Fulfillment of Scope

F.

Fulfillment of Budget

Question 13

Which of the following is not a schedule compression method?

Options:

A.

Crashing

B.

Fast-Tracking

C.

Descoping

D.

Balancing

Question 14

A review of management processes and the associated documentation is commonly called

Options:

A.

Audit

B.

Inspection

C.

Testing and measuring

D.

Analysis

Question 15

Which of the following is not a level of delegation?

Options:

A.

Sell

B.

Consult

C.

Order

D.

Participate

Question 16

True or False: When dealing with conflict within your organization, sometimes the best solution is to develop several possible solutions.

Options:

A.

True

B.

False

Question 17

True or False: The best way to get the right people on your team is to make non-negotiable demands.

Options:

A.

True

B.

False

Question 18

True or False: Pausing to let the other person speak is not an effective probing method. You always need to ask an open question for more information.

Options:

A.

True

B.

False

Question 19

Emotional intelligence includes our ability to:

Options:

A.

Accurately identify emotions in ourselves

B.

Accurately identify emotions in others

C.

Understand and manage emotions

D.

All of the above

Question 20

True or False: The critical path shows the shortest amount of time needed to complete a project.

Options:

A.

True

B.

False

Question 21

A _____ is a unique venture that has a start and an end and that is conducted by people to meet established goals within parameters of cost, schedule, and quality.

Options:

A.

Task

B.

Work

C.

Project

D.

Business

Question 22

A good office organizes files into Working, Reference, and Archive categories. Which category of files should store research for future projects and past projects associated with the same client?

Options:

A.

Working

B.

Reference

C.

Archive

D.

Backup

Question 23

True or False: Everyone can follow the same approach in order to get organized.

Options:

A.

True

B.

False

Question 24

True or False: Phrases like “uh-huh,” “OK,” yes,” or “Go on” are invitations for someone else keep talking.

Options:

A.

True

B.

False

Question 25

True or False: Change management processes are outdated and unnecessary.

Options:

A.

True

B.

False

Question 26

presentation [What is a quality audit?

Options:

A.

A team meeting dedicated to measuring and examinations.

B.

A quality based inspection of work results.

C.

A structured review of quality management activities.

D.

A meeting with the customer to identify quality requirements.

Question 27

True or False: During a survey of Yale graduates, only 3% of the graduates set goals, but that 3% earned more money and were more successful than the other 97% put together.

Options:

A.

True

B.

False

Question 28

True or False: A consensus is a unanimous vote that represents everyone’s priorities.

Options:

A.

True

B.

False

Question 29

The _____ is the formal project definition document.

Options:

A.

Statement of Work

B.

Charter

C.

Improvement Proposal

D.

Process Control Document

Question 30

In order to master a skill, it is most important to:

Options:

A.

Practice

B.

Watch others

C.

Ask for instructions

D.

Demonstrate your skills]

Question 31

True or False: It’s always a good idea to be an optimist.

Options:

A.

True

B.

False

Question 32

The process framework model investigated how an organization can divest knowledge.

Options:

A.

Process framework

B.

Information framework

C.

Management framework

D.

Time framework]

Question 33

True or False: If the leader of a meeting gets off track, an apology to the group is in order.

Options:

A.

True

B.

False

Question 34

A ___________ can help you identify the biggest priorities in your project.

Options:

A.

Gantt chart

B.

Statement of Work

C.

Target chart

D.

Pie Chart

Question 35

Which of the following methods could be used to identify risks?

Options:

A.

HAZOP analysis

B.

Consulting with experts

C.

Interviewing people in the organization

D.

All of the above

Question 36

__________can be defined as either individuals or groups of people that network in the effort to share, build, create, disseminate, and apply knowledge.

Options:

A.

Knowledge Management

B.

Information Management

C.

Scope Management

D.

Time Management]

Question 37

Which of the following is an example of communication?

Options:

A.

Two colleagues talking about a project

B.

A memo from the supervisor

C.

A barking dog

D.

All of the above

Question 38

Well-organized offices have three file categories. Which category describes files that nobody looks at?

Options:

A.

Working Files

B.

Reference Files

C.

Archive Files

D.

Deleted Files

Question 39

True or False: If the boss asks me how I can reach the benchmarks she has established, she is encouraging me as a self-leader.

Options:

A.

True

B.

False

Question 40

The SPIRIT model for goal setting stands for:

Options:

A.

Specific, positive, interactive, review, inspiring, terminate

B.

Singular, positive, individual, realistic, instigating, tentative

C.

Specific, prizes, individual, review, inspiring, time-bound

D.

Specific, product, initiative, realize, inspiring, time-bound]

Question 41

An _____________ audit is something we would not have done twenty years ago.

Options:

A.

External

B.

Employee

C.

Online]

Question 42

Norma is a very productive team member, but she’s always poking around for information and asking for details, especially in areas of the project that she isn’t involved in. What should you do?

Options:

A.

Tell her to stop being so nosy

B.

Think about why she’s asking questions and try to address the root of the problem

C.

Ignore her and hope it goes away

D.

Tell her to contact a Subject Matter Expert

Question 43

Teams that rarely see each other face-to-face are defined by:

Options:

A.

The Cutting Edge Model

B.

The Cyber Team Model

C.

The Task Force Model

D.

The Core Group Model

Question 44

True or False: If I know what is important to me (things I want to do and places I want to go), I can become better at managing time.

Options:

A.

True

B.

False

Question 45

Trust allows team members to stay ________-focused.

Options:

A.

Synergy

B.

Problem

C.

Team

D.

Budget

Question 46

Which of the following opportunities can projects offer you?

Options:

A.

Network with others

B.

Learn new skills

C.

Demonstrate skills that you don’t use in your everyday job

D.

All of the above

Question 47

Which of the following items should be included in a project status meeting?

Options:

A.

Individual task status reports

B.

Risk inventory review

C.

Project plan review

D.

All of the above

Question 48

True or False: When you are creating your project’s vision, you should be as creative as you can.

Options:

A.

True

B.

False

Question 49

Which of these words means “the combined effort is greater than its parts?”

Options:

A.

Synergy

B.

Interactivity

C.

Interdependence

D.

Stability

Question 50

True or False: Setting a project goal is the same as setting other goals.

Options:

A.

True

B.

False

Question 51

Which acronym describes the key qualities of a risk management program?

Options:

A.

PACED

B.

PESTLE

C.

SMART

D.

SAFE

Question 52

True or False: Doing quick and easy tasks right away is one way to manage time better.

Options:

A.

True

B.

False

Question 53

_______ and _________are two ways to calculate activity estimates.

Options:

A.

PERT

B.

Scientific

C.

CAM

D.

CPM

Question 54

Logical, sequential thinking is defined by the term:

Options:

A.

Horizontal thinking

B.

Vertical Thinking

C.

Lateral Thinking

D.

None of the above

Question 55

True or False: Milestones signify a key accomplishment in your project

Options:

A.

True

B.

False

Question 56

Which of the following is not a requirement for building team trust?

Options:

A.

Honesty

B.

Openness

C.

Consistency

D.

A specific goal

Question 57

When considering risk, we can use a system for analyzing threats that was originally developed by Dr. James Turner and Dr. Michael Gelles. In this system, category one is __________ severe of the five levels.

Options:

A.

Least

B.

Most

C.

Average

D.

All of the above

Question 58

It’s come to your attention that some team members feel that Carlos is a negative influence on the team. You can certainly understand why – he believes that everything is doomed. What should you do?

Options:

A.

Remove Carlos from the team.

B.

Use Carlos as an asset, particularly during risk identification

C.

Ignore him and hope it goes away

D.

Escalate the issue with the higher authorities]

Question 59

What are the four stages of team development?

Options:

A.

Forming, Storming, Norming, Performing

B.

Low, Medium, High

C.

Developing, Shaping, Finishing

D.

Gathering, Building, Developing, Educating]

Question 60

What does the O stand for in the TORI model of team building?

Options:

A.

Options

B.

Organization

C.

Openness

D.

Opportunity

Question 61

True or False: Projects can help you build relationships.

Options:

A.

True

B.

False

Question 62

True or False: A team can be defined as a group of people working towards a common goal.

Options:

A.

True

B.

False

Question 63

Using a risk matrix is a helpful ___________________.

Options:

A.

Distraction

B.

Visual tool

C.

Use of computer software

D.

Command line tool

Question 64

A quantitative risk…

Options:

A.

Is certain to happen

B.

Has a measurable impact

C.

Is the top risk you should address

D.

Is the risk with the worst impact

Question 65

True or False: Training is only necessary for the core members of the crisis management team.

Options:

A.

True

B.

False

Question 66

True or False: Existing systems can be included in your risk management plan.

Options:

A.

True

B.

False