Black Friday Biggest Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

PMI CAPM Dumps

Page: 1 / 114
Total 1135 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 1

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

Options:

A.

The organization

B.

The project

C.

The industry

D.

The product

Question 2

What process is included in Project Schedule Management?

Options:

A.

Estimate Activity Durations

B.

Create Work Breakdown Structure (WBS)

C.

Direct and Manage Project Work

D.

Estimate Activity Resources

Question 3

A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

Options:

A.

Rolling wave planning

B.

Expert Judgement

C.

Decomposition

D.

Data analysis

Question 4

What are the inputs of the Estimate Costs process?

Options:

A.

Project management plan, work performance data, enterprise environmental factors, and organizational process assets

B.

Project management plan, project documents, enterprise environmental factors, and organizational process assets

C.

Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets

D.

Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Question 5

What scenario describes when a project must be created due to market demand?

Options:

A.

A public company authorizes a project to create a new service for electric car sharing to reduce pollution.

B.

A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.

C.

Researchers develop an autonomous car. with several new features to be commercialized in the future.

D.

Stakeholders request that raw matenais be changed due to locally high costs.

Question 6

Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?

Options:

A.

Planning and risk management skills

B.

Communication and time management skills

C.

Business intelligence and leadership skills

D.

Strategic and business management skills

Question 7

Which tools and techniques will a project manager use to develop a project charter?

Options:

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Question 8

The primary purpose of the stakeholder register is to:

Options:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

Question 9

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

Options:

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps

Question 10

A project manager Is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?

Options:

A.

Monitor Stakeholder Engagement

B.

Monitor Communications

C.

Manage Communications

D.

Manage Stakeholder Engagement

Question 11

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

Options:

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Question 12

What tool should a project manager use to efficiently manage project resources?

Options:

A.

List of project resources

B.

Resource breakdown structure

C.

Resources detailed in the project scope

D.

Resource requirements

Question 13

In which type of organization does the project manager have the maximum influence

Options:

A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

Question 14

Recognition and rewards are tools and techniques of which process?

Options:

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Question 15

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

Options:

A.

Life cycle approaches

B.

Resource availability

C.

Project dimensions

D.

Technology support

Question 16

With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

Options:

A.

Suppliers

B.

Customers

C.

Governing bodies

D.

Project team

Question 17

Once the make-or-buy analysis is completed, which document defines the project delivery method?

Options:

A.

Procurement statement of work (SOW)

B.

Procurement strategy

C.

Terms of reference

D.

Change request

Question 18

To which knowledge area does the Collect Requirements process belong?

Options:

A.

Quality Management

B.

Scope Management

C.

Cost Management

D.

Integration Management

Question 19

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

Options:

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Question 20

Which of the following describes the similarities of the process groups and project life cycle?

Options:

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

Question 21

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

Options:

A.

Involvement is needed only during project initiation.

B.

Minimal involvement of stakeholders is sufficient.

C.

They should be continuously engaged.

D.

They should be involved only during phase or deliverable reviews.

Question 22

What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?

Options:

A.

Tornado diagrams and influence diagrams

B.

Detectability bubble charts and probability and impact matrix

C.

Hierarchical charts and burndown charts

D.

Flow charts and responsible, accountable, consult, and inform (RACI) charts

Question 23

Which role does the project manager resemble best?

Options:

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Question 24

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

Options:

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Question 25

In an agile or adaptive environment. when should risk be monitored and prioritized?

Options:

A.

Only during the initiation and Closing phases

B.

During the initiation and Planning phases

C.

During each iteration as the project progresses

D.

Throughout the Planning process group and retrospective meeting

Question 26

What is a tool or technique used in the Control Quality process?

Options:

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Question 27

What is the role of project management in terms of organizational strategy?

Options:

A.

Project management aligns initiatives, prioritizes work, and provides resources.

B.

Project management provides the strategic vision (or an organization lo achieve its goals.

C.

Project management enables the achievement of organizational goals and objectives.

D.

Project management harmonizes components and controls interdependencies to realize specific benefits.

Question 28

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Options:

A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

Question 29

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?

Options:

A.

Take control of all decisions and product planning.

B.

Build a team that can respond to changes within a collaborative, decision-making environment.

C.

Promote a team with a narrow specialization within a hierarchical environment.

D.

Delegate project decisions to the product owner and sponsor.

Question 30

Which is an example of analogous estimating?

Options:

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Question 31

Which set of competencies should a project manager have?

Options:

A.

Leadership, strategic and business management, and technical project management

B.

Expertise in the Industry, leadership and business management, and bilingual skills

C.

Technical project management, expertise in every role, and PMP certification

D.

Expertise in every detail on project activities. PMP certification, and leadership

Question 32

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Options:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

Question 33

Which statement is related to the project manager's sphere of influence at the organizational level?

Options:

A.

A project manager interacts with other project managers to detect common interests and impacts between their projects.

B.

A project manager facilitates communication between the suppliers and contractors on the project.

C.

A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.

D.

A project manager may inform other professionals about the value of project management.

Question 34

Which of the following tasks focuses on decomposing work packages?

Options:

A.

Adjust duration estimates

B.

Define activities

C.

Complete rolling wave planning

D.

Develop milestone list

Question 35

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Options:

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

Question 36

Which is the order of steps in the Procurement Management process?

Options:

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements

B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements

C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors

D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements

Question 37

Which is the correct hierarchy in a project environment, from most to least Inclusive?

Options:

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Question 38

Which are the main objectives of Project Risk Management?

Options:

A.

Increase the probability of positive risks and decrease the probability of negative risks

B.

Avoid all kind of risks

C.

Increase the probability of positive risks and eliminate all negative risks

D.

Identify positive and negative risks

Question 39

Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?

Options:

A.

Influence and challenge

B.

Innovation and administration

C.

Leadership and management

D.

Engagement and guidance

Question 40

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

Options:

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

Question 41

What organizational asset can influence the Plan Risk Management process?

Options:

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

Question 42

What is an output of the plan resource management process

Options:

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Question 43

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

Question 44

A project manager held a meeting and listed all team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

Options:

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Question 45

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

Options:

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Question 46

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options:

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Question 47

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

Options:

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Question 48

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager's key responsibility during this phase?

Options:

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Question 49

Match each dimension of the communications management plan to its corresponding focus.

as

Options:

Question 50

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Question 51

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Question 52

In a weak matrix, the project managers role is:

Options:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Question 53

Labor, materials, equipment, and supplies are examples of:

Options:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Question 54

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Question 55

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

Options:

A.

Three weeks

B.

Four weeks

C.

Five weeks

D.

Six weeks

Question 56

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Question 57

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Question 58

One of the tools and techniques of the Manage Project Team process is:

Options:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Question 59

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Question 60

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Question 61

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Question 62

Which of the following is an example of the simplest fixed-price contract?

Options:

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Question 63

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1

B.

0.4

C.

0.5

D.

0.8

Question 64

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Question 65

In which Project Management Process Group is the project charter developed?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Question 66

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

Options:

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

Question 67

Which type of risk diagram is useful for showing time ordering of events?

Options:

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

Question 68

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Question 69

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Question 70

Which of the following is a tool or technique of the Define Activities process?

Options:

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Question 71

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Question 72

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

Question 73

Which of the following is an output of the Distribute Information process?

Options:

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Question 74

Quality metrics are an output of which process?

Options:

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Question 75

A tool or technique in Perform Quality Control that a project manager would use is:

Options:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

Question 76

What is a tool to improve team performance?

Options:

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Question 77

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Question 78

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Question 79

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Question 80

Monte Carlo is which type of risk analysis technique?

Options:

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Question 81

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Question 82

How many Project Management Process Groups are there?

Options:

A.

3

B.

4

C.

5

D.

6

Question 83

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio

B.

Process

C.

Project

D.

Program

Question 84

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Question 85

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Question 86

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Question 87

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

Options:

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Question 88

Which of the following is an input to the Perform Qualitative Risk Analysis process?

Options:

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Question 89

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Question 90

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Question 91

Which activity involves ensuring that the composition of a projects configuration items is correct?

Options:

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Question 92

The progressive detailing of the project management plan is called:

Options:

A.

expert judgment.

B.

rolling wave planning.

C.

work performance information.

D.

specification.

Question 93

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Question 94

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit

B.

Share

C.

Enhance

D.

Transfer

Question 95

Which process determines the risks that might affect the project?

Options:

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Question 96

Testing falls into which of the following categories of cost of quality?

Options:

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Question 97

Which provides the basic framework for managing a project?

Options:

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Question 98

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Question 99

What is the primary benefit of the Manage Quality process?

Options:

A.

Increases the probability of meeting quality objectives

B.

Enhances the performance of the product berg created

C.

Defines quality roles and responsibilities

D.

Ensures that the project is completed as originally planned

Question 100

Project governance refers to framework.......which of the following is a portfolio?

Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?

Options:

A.

A portfolio is a group of projects, programs, subsidiary portfolios and operations managed together to achieve strategic objectives.

B.

A portfolio is the mam project of the company, supervised directly by the CEO.

C.

A portfolio is a group of projects managed by the same project manager.

D.

A portfolio is a group of related proiecls, programs, subsidary portfolios, and operation*, thai provides similar products or services.

Question 101

What risk response strategy involves removing high- risk scope elements from a project?

Options:

A.

Transfer

B.

Avoid

C.

Exploit

D.

Accept

Question 102

Match the praxes manager's sphere of influence with the associated primary role:

as

Options:

Question 103

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Question 104

Which are the competing constrains that project manager should address when tailoring a project?

Options:

A.

Cost, scope, schedule

B.

Sponsorship, risk, quality

C.

Schedule, sponsorship, scope

D.

Resources, Quality, Communication

Question 105

During a project's execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?

Options:

A.

Legal requirements

B.

Politics and power structures

C.

Internal information needs

D.

Sensitivity and confidentiality of the information

Question 106

Which organizational process asset can make an impact on the outcome of a project?

Options:

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

Question 107

The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?

Options:

A.

10 days

B.

15 days

C.

12.5 days

D.

5 days

Question 108

What process is performed periodically throughout the project as needed?

Options:

A.

Plan Risk Management

B.

Plan Communications Management

C.

Plan Resource Management

D.

Plan Cost Management

Question 109

Match the life cycle type to when its requirements are defined.

as

Options:

Question 110

If a project manager effectively manages project knowledge, a key benefits is that:

Options:

A.

all stakeholders have access to the same information.

B.

the project team is able to understand the project status.

C.

project stakeholders have a clear picture of the project.

D.

new knowledge is added to organizational process assets.

Question 111

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

Options:

A.

Detailed estimation

B.

Lightweight estimation

C.

Parametric estimation

D.

A mix of them

Question 112

How can you describe the role of the project.... of influence concept?

Options:

A.

The proiect manager proactivnly interacfS with other project managers creating a positive influence Km fulfilling project needs, working with other managers and sponsor to address internal political and strategic issues and ensunng that the project managemenl plan aligns with the portfolio or program plan

B.

The project manager leads the team, performs communication roles between stakeholders, and uses interpersonal sills to balance conflicting goals

C.

The proiect manager stays informed about current technology developments lakes into account new quality management standards, and uses relevant technical support tools

D.

The proiect manager participates in project management trainings, contributes to the organization professional community sharing knowledge, and maintains subied matter expertise

Question 113

What is the main purpose of Project Quality Management?

Options:

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Question 114

What should a project manager consider to address the full delivery life cycle for large projects?

Options:

A.

A range of techniques utilizing a plan driven approach, adaptive approach or a hybrid ot both

B.

Only techniques of an agile/adaptive approach in large organizations

C.

Change the role of the project manager to managing pro|ci I in adaptive nuviionin-

D.

Splitting larger projects into two or more smaller project is which can be addressed in an adaptive method

Question 115

Select three processes that are associated with Project Schedule Management.

Options:

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

Question 116

How is program success measured?

Options:

A.

By delivering the benefit of managing the program's projects in a coordinated manner

B.

By the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Question 117

Agile release planning provides a high-level summary timeline of the release schedule based on.

Options:

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Question 118

What type of stakeholder is part of a project manager 's sphere of influence on a project?

Options:

A.

Customers

B.

Sponsors

C.

Directors

D.

Resource managers

Question 119

What is a key benefit of using virtual project teams?

Options:

A.

Ensures appropriate behavior, security, and the protection of proprietary information

B.

Reduces the risk of conflict due to interpersonal communications and other interactions

C.

Assures that all team members have a clear and common understanding of the project

D.

Reduces project cost by use of modern technologies allowing seamless team collaboration

Question 120

Which three techniques can be estimate costs?

Options:

A.

Financing, bottom-up estimating, and expert judgment

B.

Cost aggregation, analogous estimating, and financing

C.

Expert judgment, financing, and cost aggregation

D.

Expert judgment, analogous estimating, and bottom-up estimating

Question 121

Which statement describes the various purposes of project scheduling?

Options:

A.

Define the policies, rules, and techniques to run a schedule; serve as a tool to manage stakeholder expectations; and serve as a base for backlog management

B.

Define how and when deliverables will be completed, serve as communication tool, and serve as a base for performance reporting

C.

Define the life cycle, traditional or agile approach, and tools to control schedule; serve as a reference for scope management; and serve as a base for risk management

D.

Define activities, sequences, duration, and dependencies, serve as a reference for resource allocation, serve as a base for earned value analysis.

Question 122

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

Options:

A.

Iterative

B.

On-demand

C.

Interactive

D.

Quality

Question 123

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

Options:

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Question 124

Which statement describes the relationship between Manage Quality process and Control process?

Options:

A.

Manage Quality is all about following planned processes and provedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.

B.

Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.

C.

Manage Quality and Control Quality are the same

D.

Manage Quality is part of Quality Management and Control is a subset of the Stakeholder Management Process group

Question 125

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders'?

Options:

A.

Prioritization

B.

Directions of influence

C.

Salience model

D.

Power/influence grid

Question 126

How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

Options:

A.

It details product or service failures experienced by the customer

B.

It clarifies the costs associated with assessing the quality of the product or service

C.

It accounts for costs used to avoid poor quality in the product or service

D.

It communicates product or service failures discovered by the project team

Question 127

What CPI > 1 and SPI < 1 mean?

Options:

A.

Under budget ahead of schedule

B.

Over budget, behind schedule

C.

Under budget, behind schedule

D.

Over budget, ahead of schedule

Question 128

What is a tailoring consideration for Project Scope Management'?

Options:

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Question 129

A product owner wants to ensure that the project's requirements, including product requirements, are met and validated. To do this project manager wants.

Match each process to its definition.

as

Options:

Question 130

What is main purpose of Project Quantity Management?

Options:

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Question 131

Which of the following lists represents trends and emerging practices in Project Risk Management?

Options:

A.

Integrated risk management, non-event risks, and project resilience

B.

Representation of uncertainty, strategies for opportunities, and strategies for overall project risk

C.

Dormancy, proximity, and propinquity

D.

Simulation, sensitivity analysis, and decision tree analysis

Question 132

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment ol Iheir power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Question 133

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

Options:

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

Question 134

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Options:

A.

Project Cost Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Schedule Management

Question 135

Which is an example of an internal enterprise environmental factor?

Options:

A.

Market Share brand recognition

B.

Factory location

C.

Local government regulation

D.

Industry research

Question 136

What estimating technique is used when there is limited information?

Options:

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Question 137

What are the project management processes associated with project quantity management?

Options:

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Question 138

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

Options:

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

Question 139

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

Options:

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

Question 140

Due to organizational changes, a new product owner joins a project The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

Options:

A.

Acquire Resources

B.

Plan Resource Management

C.

Estimate Activity Resources

D.

Control Resources

Question 141

Which of these statements is true of subsidiary management plans?

Options:

A.

Subsidiary management plans are mandatory for any project

B.

Subsidiary management plans use the project charier as input

C.

Subsidiary management plans can be independently managed

D.

Subsidiary management plans do not need regular updates

Question 142

What can a project1 manager review to understand the status of project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Question 143

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier

B.

Conduct quality audits

C.

Validate Scope

D.

Validate quality requirements

Question 144

Which is an aspect of the requirements management plan?

Options:

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Question 145

In which of the risk management processes is the processes is the project charter used as an input?

Options:

A.

Palm Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

Question 146

Which actions should a project manager follow to manage stakeholders?

Options:

A.

Identify the key stakeholders and keep them informed at all times.

B.

Identify the stakeholders, planning, managing and monitoring their engagement

C.

Meet and keep informed any person related to the project, at all times

D.

Identify the stakeholders and monitor their level of satisfaction

Question 147

Project managers plan a key role performing integration on the project what are the three different levels of integration?

Options:

A.

Process, cognitive

B.

Complexity, understand and change

C.

Interact, insight and leadership

D.

Communication, knowledge and value

Question 148

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Question 149

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Question 150

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Question 151

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Question 152

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

Options:

A.

Project

B.

Scope

C.

Contract

D.

Program

Question 153

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Question 154

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Question 155

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Question 156

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Question 157

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Question 158

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Question 159

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question 160

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Question 161

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Question 162

Which characteristics do effective project managers possess?

Options:

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Question 163

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Question 164

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Question 165

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Question 166

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Question 167

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Question 168

Which of the following is an output of Close Procurements?

Options:

A.

Accepted deliverables

B.

Organizational process assets updates

C.

Managing stakeholder expectations

D.

Performance reports

Question 169

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

Options:

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (T&M)

D.

Cost Plus Incentive Fee Contract (CPIF)

Question 170

Which of the following can be used as an input for Define Scope?

Options:

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Question 171

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Question 172

Which of the following is an output of the Conduct Procurements process?

Options:

A.

Project statement of work

B.

Selected sellers

C.

Risk register updates

D.

Teaming agreements

Question 173

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Question 174

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Question 175

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Question 176

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Question 177

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Question 178

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Question 179

At the end of the project, what will be the value of SV?

Options:

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Question 180

The diagram below is an example of a:

as

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Question 181

One of the objectives of a quality audit is to:

Options:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Question 182

Projects are separated into phases or subprojects; these phases include:

Options:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Question 183

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Question 184

Which activity may occur at project or phase closure?

Options:

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking

Question 185

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Question 186

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Question 187

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Question 188

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Question 189

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Question 190

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Question 191

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two

B.

Four

C.

Five

D.

Twelve

Question 192

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Question 193

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Question 194

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Question 195

Exhibit A is an example of which of the following types of Sequence Activities?

as

Options:

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Question 196

Administer Procurements is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Question 197

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Question 198

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

Options:

A.

To the project management plan.

B.

To the risk register.

C.

In the scope verification processes.

D.

And their impact to the project in terms of time, cost, and risk.

Question 199

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Question 200

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Question 201

What is an objective of the Develop Project Team process?

Options:

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Question 202

An input to the Create WBS process is a:

Options:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

Question 203

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Question 204

Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Question 205

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Question 206

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Question 207

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Question 208

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Question 209

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Question 210

Which is an example of Administer Procurements?

Options:

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Question 211

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Question 212

Which tools or techniques will a project manager use for Develop Project Team?

Options:

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Question 213

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

Options:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Question 214

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Question 215

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Question 216

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

Options:

A.

plan

B.

process

C.

program

D.

portfolio

Question 217

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

Options:

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Question 218

Which illustrates the connection between work that needs to be done and its project team members?

Options:

A.

Work breakdown structure (WBS)

B.

Network diagrams

C.

Staffing management plan

D.

Responsibility assignment matrix (RAM)

Question 219

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Question 220

The Human Resource Management processes are:

Options:

A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.

B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.

C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.

D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Question 221

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Question 222

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Options:

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

Question 223

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Question 224

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Question 225

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

Options:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Question 226

Which process is included in the Project Integration Management Knowledge Area?

Options:

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Question 227

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Question 228

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

Options:

A.

Program

B.

Functional

C.

Project

D.

Portfolio

Question 229

The stakeholder register is an output of:

Options:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Question 230

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Question 231

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

Options:

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Question 232

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Options:

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

Question 233

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Question 234

Which of the following investigates the likelihood that each specific risk will occur?

Options:

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Question 235

The process of formalizing acceptance of the completed project deliverables is known as:

Options:

A.

Validate Scope.

B.

Close Project or Phase.

C.

Control Quality.

D.

Verify Scope.

Question 236

Which enterprise environmental factors are considered during Estimate Costs?

Options:

A.

Market conditions and published commercial information

B.

Company structure and market conditions

C.

Commercial information and company structure

D.

Existing human resources and market conditions

Question 237

Which action should a project manager take to ensure that the project management plan is effective and current?

Options:

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Question 238

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Question 239

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders' tolerances.

Question 240

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Question 241

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Question 242

What is the name of a graphic display of project team members and their reporting relationships?

Options:

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Question 243

The product scope description is used to:

Options:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Question 244

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Question 245

The integrative nature of project management requires which Process Group to interact with the other Process Groups?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Project Management

Question 246

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

Options:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Question 247

Which process involves developing an approximation of the monetary resources needed to complete project activities?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Question 248

When does the project team determine which dependencies are discretionary?

Options:

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

Question 249

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Question 250

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Question 251

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

Options:

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Question 252

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Question 253

An input to the Plan Cost Management process is:

Options:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Question 254

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Options:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Question 255

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

Options:

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Question 256

An output of the Validate Scope process is:

Options:

A.

A requirements traceability matrix.

B.

The scope management plan.

C.

Work performance reports.

D.

Change requests.

Question 257

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Question 258

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Question 259

Which process determines the risks that may affect the project and documents their characteristics?

Options:

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Question 260

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Question 261

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Question 262

Which cost is associated with nonconformance?

Options:

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Question 263

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

Options:

A.

Develop Project Team.

B.

Manage Project Team.

C.

Acquire Project Team.

D.

Plan Human Resource Management.

Question 264

Which Knowledge Areas include processes from the Closing Process Group?

Options:

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Question 265

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Options:

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Question 266

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Question 267

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Question 268

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Question 269

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Options:

A.

Organizational process updates

B.

Quality metrics

C.

Change requests

D.

Quality control measurements

Question 270

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Question 271

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Question 272

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Question 273

An example of a group decision-ma king technique is:

Options:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Question 274

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Question 275

Which tool or technique is used to manage change requests and the resulting decisions?

Options:

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Question 276

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Question 277

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Question 278

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Question 279

Which tool or technique is effective in a project in which the deliverable is not a service or result?

Options:

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Question 280

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Question 281

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Options:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

Question 282

An input to the Identify Stakeholders process is:

Options:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Question 283

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Question 284

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Question 285

An element of the project scope statement is:

Options:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Question 286

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Question 287

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Question 288

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Question 289

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

Question 290

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

Options:

A.

Develop Schedule

B.

Create VVBS

C.

Estimate Activity Resources

D.

Define Scope

Question 291

Sensitivity analysis is typically displayed as a/an:

Options:

A.

Decision tree diagram.

B.

Tornado diagram.

C.

Pareto diagram.

D.

Ishikawa diagram.

Question 292

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Question 293

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

Options:

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Question 294

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (T&M)

Question 295

High-level project risks are included in which document?

Options:

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Question 296

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Question 297

A tool and technique used in the Develop Project Charter process is:

Options:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Question 298

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100

B.

120

C.

1,000

D.

1,200

Question 299

Analytical techniques are a tool and technique of which process in Project Procurement Management?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Conduct Procurements

D.

Close Procurements

Question 300

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Question 301

Requirements documentation will typically contain at least:

Options:

A.

Stakeholder requirements, staffing requirements, and transition requirements.

B.

Business requirements, the stakeholder register, and functional requirements.

C.

Stakeholder impact, budget requirements, and communications requirements.

D.

Business objectives, stakeholder impact, and functional requirements.

Question 302

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Question 303

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Question 304

The process of defining how the project scope will be validated and controlled is known as:

Options:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Question 305

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Question 306

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Question 307

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Question 308

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Question 309

The following chart contains information about the tasks in a project.

as

Based on the chart, what is the schedulevariance (SV) for Task 8?

Options:

A.

-2,000

B.

-1,000

C.

1,000

D.

2,000

Question 310

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

Options:

A.

lead

B.

lag

C.

mandatory dependency

D.

internal dependency

Question 311

In a typical project, project managers spend most of their time:

Options:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

Question 312

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

Options:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Question 313

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Question 314

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Question 315

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Question 316

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Options:

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Question 317

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Question 318

The scope management plan and scope baseline are contained in:

Options:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

Question 319

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Question 320

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Question 321

Specification of both the deliverables and the processes is the focus of:

Options:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Question 322

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Question 323

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Options:

A.

Define Activities

B.

Direct and Manage Project Work

C.

Develop Project Management Plan

D.

Develop Project Charter

Question 324

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Question 325

An input to the Control Quality process is:

Options:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Question 326

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Question 327

A project manager who communicates to the project team though email is using which type of communication?

Options:

A.

Formal

B.

Informal r

C.

Horizontal

D.

Unofficial

Question 328

In project management, a temporary project can be:

Options:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Question 329

The chart below is an example of a:

as

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Question 330

An issue log is an input to which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Question 331

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Options:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Question 332

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

Options:

A.

management

B.

response

C.

tolerance

D.

appetite

Question 333

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

Options:

A.

Level of control.

B.

Communication channels.

C.

Scope.

D.

Strategic alignment.

Question 334

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Question 335

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Question 336

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Question 337

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Question 338

Every project creates a unique product, service, or result that may be:

Options:

A.

tangible

B.

targeted

C.

organized

D.

variable

Question 339

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Question 340

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Options:

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Page: 1 / 114
Total 1135 questions