Black Friday Biggest Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

PMI PMI-PBA Dumps

Page: 1 / 20
Total 200 questions

PMI Professional in Business Analysis Questions and Answers

Question 1

In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.

Which technique could have prevented this problem from occurring?

Options:

A.

Prototyping

B.

Diagrams

C.

Use cases

D.

Document analysis

Question 2

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

Options:

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.

Question 3

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

Options:

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Question 4

When eliciting requirements, a good time to consider using the interviewing method is when:

Options:

A.

attempting to obtain sign-off on requirements from stakeholders.

B.

there is not enough time to gather requirements from many different sources.

C.

there are communication challenges among stakeholders.

D.

assembling a requirements traceability matrix.

Question 5

A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

Options:

A.

verify that the test case is incorrect.

B.

let the users decide if the test result 1s acceptable.

C.

change the requirement according to the test result.

D.

ask the tester to perform the test again.

Question 6

Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

Options:

A.

PEST analysis

B.

B. Force-field analysis

C.

Feasibility analysis

D.

Gap analysis

Question 7

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

Options:

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Question 8

What is a standardized, effective, and efficient way to manage changes to project documentation?

Options:

A.

A configuration verification and audit system

B.

A requirements traceability matrix

C.

A configuration management system

D.

A change control board

Question 9

What can a business analyst use to track requirements documentation?

Options:

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Question 10

When determining the value of a business case, which tool or technique should be used?

Options:

A.

Variance analysis

B.

Cost-benefit analysis

C.

SWOT analysis

D.

Feasibility analysis

Question 11

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

Options:

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Question 12

An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.

What analysis should the business analyst conduct to facilitate a successful migration?

Options:

A.

Document

B.

User interface

C.

Interface

D.

Systems

Question 13

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Options:

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Question 14

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

Options:

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Question 15

A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.

Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

Options:

A.

Data dictionary

B.

Configuration management system

C.

Sequence diagram

D.

D. Process model

Question 16

A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.

How could the business analyst address the end user's concerns about the new interface?

Options:

A.

Consult the stakeholder register to evaluate if the user has authority to influence the project.

B.

Develop a prototype to gather functional requirements.

C.

Develop a use case package to support the user interface.

D.

Document the business data objects using an entity relationship diagram.

Question 17

The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.

What could have caused this issue?

Options:

A.

The test engineer has not properly communicated requirements to the team.

B.

Not all stakeholders were involved during requirements elicitation.

C.

Acceptance criteria for the requirements were not measurable.

D.

Requirements were not adequately reviewed with the project sponsor.

Question 18

The best way to ensure the integrity of requirements is to:

Options:

A.

implement version control, maintain a history of requirements changes, and track the status of each requirement.

B.

use a requirements management tool, measure requirements volatility, and maintain a history of requirements changes.

C.

establish a change control board, track the status of each requirement, and use a requirements management tool.

D.

establish a requirements baseline, establish a change control board, and label each requirement uniquely.

Question 19

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

Options:

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Question 20

A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?

Options:

A.

Cost-benefit analysis

B.

Benchmarking

C.

Brainstorming

D.

Document analysis

Question 21

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

Options:

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Question 22

After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?

Options:

A.

Context diagram

B.

Use cases

C.

Process flow

D.

Tracing requirements

Question 23

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

Options:

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Question 24

The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

Options:

A.

communicate changes to requirements only when they are completely defined.

B.

spend the time required to provide, clarify, and elaborate requirements.

C.

challenge assessments of the cost and feasibility of requirements.

D.

perform an alternatives analysis for requirements implementation.

Question 25

The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

Options:

A.

Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.

B.

Plan regular meetings with stakeholders to review the requirements baseline update and to discuss changes.

C.

Establish a risk traceability matrix and designate someone to manage each risk with the appropriate response.

D.

Record all the requirements in a matrix, review it regularly, and get approval from stakeholders.

Question 26

A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?

Options:

A.

The industry is unregulated.

B.

The project impact is contained within a small department of the company.

C.

Errors in the product could result in financial solvency.

D.

The organization follows an iterative project life cycle.

Question 27

An insurance company embarks on a project to replace its current enrollment and billing software application, which will no longer be supported by the end of the calendar year. The new enrollment and billing application must be implemented before the current vendor contract ends. The business analyst gathers the initial requirements for the new enrollment and billing application. Based on the large

volume of requirements, the business analyst realizes that the requirements will need to be prioritized.

Which requirements prioritization method should the business analyst use for this project?

Options:

A.

Time-boxing

B.

Weighted ranking

C.

MoSCoW

D.

Risk analysis

Question 28

A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.

Which approach will better cope with the requirements’ volatility?

Options:

A.

Storyboarding

B.

Multivoting

C.

Phased baselining

D.

Comparative analysis

Question 29

Which tool provides combined functionality for business analysis and quality assurance activities?

Options:

A.

Functional specification tool

B.

Requirements traceability tool

C.

System use case modeling tool

D.

Solution quality assurance tool

Question 30

The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?

Options:

A.

Requirements traceability matrix

B.

Requirements baseline document

C.

Requirements management plan

D.

Requirements impact analysis

Question 31

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Question 32

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?

Options:

A.

Risks identified in the risk management plan were not addressed properly.

B.

There is no issue since the product exceeded the customer expectations.

C.

The sponsor approved the release of the product without reviewing the budget.

D.

Requirements were not properly traced and monitored.

Question 33

What should a business analyst do after discovering that two solution requirements conflict?

Options:

A.

Consult the sponsor(s) and log the constraint.

B.

Perform an impact analysis and propose a lower-cost alternative.

C.

Update the requirements baseline and upload it to the project repository.

D.

Communicate the conflict to stakeholders and facilitate a resolution.

Question 34

The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?

Options:

A.

Which stakeholders have the most influence?

B.

Which functional areas are impacted?

C.

How is the organizational chart structured?

D.

What is the business need?

Question 35

A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.

What should the business analyst do next?

Options:

A.

Bring the subsequent project to the change control board (CCB).

B.

Ask the stakeholders to review the requirement before any other action is taken.

C.

Communicate that the status of this requirement has changed.

D.

Mark the requirement as complete so that it is not forgotten.

Question 36

The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.

This situation could have been averted if:

Options:

A.

quality attributes were captured and tested.

B.

critical business requirements were accommodated and tested.

C.

nonfunctional requirements were identified and tested.

D.

essential product requirements were captured and tested.

Question 37

A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.

Which of the following types of surveys would be most appropriate to create and why?

Options:

A.

A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct

B.

A closed-ended survey using the Likert scale to rank specific areas of the current business process

C.

An open-ended survey to allow users the opportunity to explain their opinions on the current business process

D.

An open-ended survey to collect different opinions on the current business process

Question 38

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

Options:

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP's choice, as it is most likely to be adopted.

Question 39

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Question 40

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

Options:

A.

prepare a test procedure for the product to discuss at the requirements review.

B.

start designing the product to impress the customer with the amount of progress achieved early in the project.

C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.

D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.

Question 41

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

Options:

A.

vote on the product's highest-value business needs.

B.

negotiate to best meet each department's objectives.

C.

collaborate on a product scope that aligns with the company’s objectives.

D.

delegate the decision to be made by the product sponsor.

Question 42

A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.

The customer is having difficulty determining if the product is meeting the requirements during the test event because the:

Options:

A.

customer did not adequately review the test procedure before the test.

B.

test engineer is not communicating effectively with the customer.

C.

requirements in the technical specification are unclear and ambiguous.

D.

customer cannot make this determination until the entire test is complete.

Question 43

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Question 44

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

Options:

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Question 45

A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.

Which model should the team employ to ensure the most effective representation of analysis boundary?

Options:

A.

Data flow diagram

B.

Context diagram

C.

State diagram

D.

Entity relationship diagram

Question 46

The following requirement was included in a business requirements document: “An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized.” What should be done with this business requirement?

Options:

A.

It should remain because it specifies the reason why the business requirement is needed.

B.

It should be removed because it does not state how often the data should be synchronized.

C.

It should be revised because it states a solution to the problem rather than the business need.

D.

It should remain because it specifies the type of data and the source system.

Question 47

After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased. Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

Options:

A.

Questionnaires and surveys

B.

Document analysis

C.

Observation

D.

Traceability matrix

Question 48

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

Options:

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Question 49

Which of the following best describes the function of the requirements baseline?

Options:

A.

Controls the product development and evolution.

B.

Provides the basis for the development scope.

C.

Tracks the progress of requirements documentation.

D.

Defines how the project will be scheduled.

Question 50

Which technique or tool is used to obtain acceptance of the delivered product?

Options:

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Question 51

A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?

Options:

A.

MoSCoW

B.

SMART goals

C.

RACI models

D.

Storyboarding

Question 52

During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

Options:

A.

Business activity model

B.

RAC! matrix

C.

Power/interest grid

D.

Organization modeling

Question 53

A new project's goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?

Options:

A.

A Cost-benefit analysis of the existing system

B.

Technical readiness of the development team

C.

New solution design specification

D.

Customer metrics on the existing system

Question 54

Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

What could the business analyst have established to help manage this situation?

Options:

A.

Change control process

B.

Configuration management system

C.

Communication plan

D.

Sponsor signoff

Question 55

Which function involves auditing both the quality requirements to resolve discrepancies and the results of quality control measurements to ensure that appropriate quality standards and operational definitions are being used?

Options:

A.

Quality control

B.

Quality assessment

C.

Quality management

D.

Quality assurance

Question 56

Which of the following actions will contribute most to the success of the initial stage of the project?

Options:

A.

Interview stakeholders to clearly define the problem.

B.

Document the requirements and obtain sign-off.

C.

Establish the change control process of the project.

D.

Define the acceptance criteria required during the acceptance phase.

Question 57

The business analyst is conducting a feasibility study to understand how well a potential solution fits into the organization. What kind of feasibility assessment is the business analyst undertaking?

Options:

A.

Operational

B.

Technical

C.

Cost-effectiveness

D.

Time

Question 58

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

Options:

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Question 59

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)

versioning?

Options:

A.

Statement of work

B.

Project plan

C.

Problem or opportunity statement

D.

Traceability matrix

Question 60

Once the requirements are compared to internal and external quality standards, what should the business analyst do next?

Options:

A.

Set the priority of the requirements.

B.

Communicate the requirements to stakeholders.

C.

Ensure that the requirements are validated.

D.

Baseline the requirements.

Page: 1 / 20
Total 200 questions