Pre-Summer Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

PMI PMP Dumps

Page: 1 / 219
Total 2191 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 1

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

Options:

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

Question 2

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

as

Options:

Question 3

Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?

Options:

A.

Remove one of the team members

B.

Identify the issues between the team members and guide them toward a resolution

C.

Warn the team members about their behavior

D.

Train the team members on communication techniques and interpersonal behavior

Question 4

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

Question 5

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

Options:

A.

Ensure that the whole team is appropriately recognized and organize a project farewellparty to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and savethem in the organization's project management information system (PMIS).

C.

Archive all the project documents following the organization's accepted practices sothe documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult toundertake because the current project is not yet complete.

Question 6

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

Options:

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members' supervisors

D.

Modify the communications management plan and resend it to the team

Question 7

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

Options:

A.

Perform an impact analysis with subject matter experts (SMEs).

B.

Inform the government representative about the impact of the separate project.

C.

Implement a change request to increase the budget and schedule.

D.

Consult and update the risk register with the project stakeholders.

Question 8

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

Options:

A.

Contract negotiation

B.

Team assessment

C.

Mentoring and coaching

D.

On-the-job training

Question 9

A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.

Why did this action occur?

Options:

A.

Inadequate funds for the automation project

B.

Inadequate engagement of the political stakeholders

C.

Lack of competence to manage the automation project

D.

Lack of a proper legal framework in place

Question 10

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

Options:

A.

Issue log

B.

Lessons learned register

C.

Stakeholder engagement plan

D.

Risk register

Question 11

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Question 12

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

Options:

A.

Ask an external technical leader to provide input and plan the sprint.

B.

Remove the items from the product backlog since the size couldn't be estimated.

C.

Make the decision about the backlog items based on what makes more sense.

D.

Facilitate the discussion so that the team members can reach a consensus.

Question 13

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

Options:

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Question 14

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

Options:

A.

Evaluate the project exit criteria in the project charter.

B.

Reach out to the senior executive sponsor for the project.

C.

Understand the project success criteria and objectives.

D.

Review the project status reporting for the latest information.

Question 15

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

Options:

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

Question 16

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

Options:

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project managerdirectly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to beinvolved.

Question 17

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

Options:

A.

Perform collaborative work that is coordinated by the project manager.

B.

Rely on the expert judgment of the product owner.

C.

Use a market-based strategy.

D.

Engage the project sponsor.

Question 18

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback'?

Options:

A.

Assessed and analyzed personality indicators from the project team

B.

Sent the activity details to everyone involved prior to the session

C.

Communicated the decision to conduct this activity to the key team stakeholders

D.

Selected a vendor for the activity according to the procurement management plan

Question 19

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Question 20

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

as

Options:

Question 21

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

Options:

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.

Question 22

During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?

Options:

A.

Update the issue log and document the change

B.

Review the product specification requirements.

C.

Perform a root cause analysis

D.

Submit a change request for corrective action.

Question 23

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

Options:

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Question 24

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

as

Options:

Question 25

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

Options:

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

Question 26

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

Options:

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Question 27

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Question 28

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

Question 29

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

Options:

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

Question 30

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

Options:

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Collaborate/problem solve

D.

Force/direct

Question 31

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.

B.

Commit each team member's time and deliverables and aim for overall projectcompletion.

C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Question 32

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Question 33

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

Options:

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Question 34

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Question 35

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Question 36

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

Options:

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

Question 37

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

Options:

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

Question 38

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

Options:

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office's (PMO)assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.

Question 39

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

as

Options:

Question 40

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

Options:

A.

An agreed-upon work method and tools that should fit the business need and project constraints

B.

A detailed mitigation plan on the risks for each work method and the tools used

C.

A consensus that everything will run as anticipated once the tools and work methods are identified

D.

A technology roadmap for creating similar deliverables in the future with the same tools

Question 41

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.

Meet with each stakeholder individually to gather input to the product backlog andbegin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learnedand complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for theproduct backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Question 42

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

Options:

A.

Allow project B's leader to continue building relationships.

B.

Talk with project B's leader to discuss possible impacts to both projects.

C.

Tell project A's team member to ignore project B's leader.

D.

Ensure project A's team member can finish the work committed to project A.

Question 43

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

Options:

A.

Negotiate the payments with the supplier and remind them of their long-term association

B.

Penalize the supplier according to the contract's service level agreement (SLA)

C.

Hire another information security supplier and incentivize them for speedy delivery

D.

inform the relevant stakeholders of this challenge and seek their support

Question 44

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

Options:

A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration

B.

Requested the product owner's approval to add an external expert to define theacceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject

D.

Increased the communications between the team member and the product owner

Question 45

When a project manager is trying to determine a leadership style to use on a project what should they consider?

Options:

A.

Number of tasks on the protect

B.

Culture of the organization

C.

Project timeline

D.

Experience of the project manager

Question 46

An international client contacted a software development company to build out a

software product, and an agile project manager was assigned. At one of the review meetings,

the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?

Options:

A.

Include the mentioned feature in the prioritized requirements list.

B.

Assign a team member to immediately start working on that feature.

C.

Review the original project documentation to confirm.

D.

Treat it as a change request and assess the effect on the project's goals.

Question 47

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Question 48

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

Options:

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Question 49

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.

Engage the project team In implementing and Improving key aspects of the standup meetings.

B.

Ask the product owner to remove team members who do not comply with standup meeting rules.

C.

Send a daily retrospective report to all team members instead of holding standup meetings.

D.

Include a daily brainstorming session In the standup meetings to resolve pending Issues.

Question 50

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?

Options:

A.

Inform the project steering committee of this constraint.

B.

Inform the project team and create a spike for the next Iteration.

C.

Inform the legal department that the project scope will be updated.

D.

Inform the product owner that the project will continue as planned.

Question 51

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Question 52

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.

Notify all team members that all steps in the process must be completed.

B.

Escalate the issue to the other executive leadership members.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

Question 53

A project team has been together for a long time and has been led by three different

project managers. Lately, the performance of one of the team members has been declining

and has affected the project delivery.

What should the current project manager do to ensure that team performance is improved and

sustained?

Options:

A.

Liaise with the functional managers to replace the team member.

B.

Engage with the team member and draw up a development plan.

C.

Organize quarterly team-building events.

D.

Request that a new team member be added to the team

Question 54

An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.

What should the agile leader do?

Options:

A.

Reassign the task to another team member and require the team member to complete training

B.

Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint

C.

Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.

D.

Speak directly with the team member about improvements and commit to an agreed-upon time frame.

Question 55

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

Options:

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Question 56

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

Options:

A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.

Develop a communications management plan for each category in the stakeholder register.

C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Question 57

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Options:

A.

Functional managers, team members, and external consultants with experience in the field

B.

Team members, engineers, and weather experts

C.

Team members, consultants from outside the project with experience in the field, and the customer

D.

Weather experts, functional managers, and team members

Question 58

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Question 59

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

Options:

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior

B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately

C.

Request a meeting with the disruptive team member and help to resolve the issue

D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly

Question 60

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Question 61

A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?

Options:

A.

Escalate the change request to the sponsor

B.

Validate the work completed

C.

Inform the stakeholders of the change

D.

Facilitate the update of the product backlog

Question 62

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

Options:

A.

Project charter

B.

Stakeholder register

C.

Team charter

D.

Project organization charts

Question 63

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

Options:

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Question 64

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.

Send an email update to existing team members about the addition of the new teammembers.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Question 65

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

Options:

A.

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.

B.

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.

C.

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.

D.

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.

Question 66

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

Options:

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

Question 67

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

Options:

A.

Request a change in the contract to include the shipment in the project managementplan.

B.

Find the root cause of the issue and discuss the customer's current engagement.

C.

Inform the customer that subsequent packages cannot be manufactured.

D.

Request a delivery date extension from the customer

Question 68

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Question 69

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

Options:

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

Question 70

A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

Options:

A.

Request stakeholders who understand the technology.

B.

Recommend a change in technology to senior management.

C.

Plan to conduct informal sessions with the stakeholders.

D.

Include the issue in the Issue log and escalate to senior management.

Question 71

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

Options:

A.

Reinforce the value of documenting and approving all change requests and ask thecustomer to issue these through the agreed channels.

B.

Organize a meeting to mediate the relationship between the customer and the teammember to ensure no feelings are hurt.

C.

Ask the customer to email all requests directly to you and you will ensure they areactioned by the correct team member.

D.

Explain to the customer that the team member was just trying to help and the changescan be reverted if necessary.

Question 72

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

Options:

A.

Design a set of metrics including velocity, which is a good measure of value delivered.

B.

Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)

C.

Promote a productive environment where everybody can work without interruptions from the rest of the team members

D.

Create a reward system recognizing group contributions to get people motivated and improve performance

Question 73

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

Options:

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Question 74

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Question 75

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

Options:

A.

Company's historical organizational project artifacts

B.

Company's project responsibility assignment matrix (RAM)

C.

Company's resource management plan

D.

Company's resource calendars

Question 76

A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met

How should the project manager approach the stakeholder?

Options:

A.

Analyze the stakeholder's expectations and emphasize the topics of interest that may influence the project's success

B.

Post regular updates to the project teams board and email the stakeholder when they are posted so the stakeholder can review at their convenience

C.

Schedule regular review sessions with the stakeholder and the project team so the stakeholder can understand the status and engage with team members

D.

Continue to send status reports by email and schedule one-on-one sessions with the stakeholder so they are regularly debriefed on the project status

Question 77

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for theproject.

Question 78

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

Options:

A.

Reprimand the team members who did not fill out the status reports.

B.

Justify the team members' behavior to the project sponsor.

C.

Quickly put together a report that will satisfy the project sponsor.

D.

Discuss the issue with the team members at fault.

Question 79

A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?

Options:

A.

Deliver to the receiving manager on time, who can then make a knowledge transfer totheir team.

B.

Inform the project sponsor of the two-week delay and replan activities to minimizedelays.

C.

Request that the receiving manager issue a change request to prolong the project bytwo weeks.

D.

Issue an internal change request to secure the resources for an additional two weeks.

Question 80

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

Options:

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Question 81

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurityrequirements.

Question 82

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Question 83

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Question 84

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

Options:

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Question 85

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

Options:

A.

Check the change management plan

B.

Document the issue in the scope management plan.

C.

Conduct a team brainstorming session to resolve the issue

D.

Check the quality management plan

Question 86

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Question 87

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

Question 88

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

Options:

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

Question 89

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

Options:

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Question 90

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Question 91

A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation

What should the project manager do?

Options:

A.

Communicate the ground rules, principles and reporting methods to the project stakeholders

B.

Penalize the project team lead for not updating the project documentation properly.

C.

Review this issue with the team lead for possible ways to resolve this situation

D.

Issue guidance to the team member about reporting directly to the project manager

Question 92

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

Options:

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan

B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis

C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge

D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Question 93

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

Options:

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Question 94

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

Options:

A.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

B.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,

D.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

Question 95

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

Options:

A.

Postpone the required work on the project until school holidays begin

B.

Advise the school to close (or the duration of the project work

C.

Continue the work as planned and inform the school when the project team arrives on-site

D.

Liaise with the school to include nonworking project hours during school start and finish times

Question 96

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Question 97

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute toprojects.

B.

Assign employees to agile projects so they can quickly adjust to the new approach.

C.

Train all employees in agile approaches.

D.

Shift the way the company views, reviews, and assesses employees.

Question 98

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

Question 99

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

Question 100

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

Options:

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

Question 101

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Question 102

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Question 103

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Question 104

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodologyfor consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Question 105

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Question 106

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to supportdevelopment.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Question 107

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

Options:

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Question 108

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

Options:

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Question 109

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

Options:

A.

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.

B.

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.

C.

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

D.

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.

Question 110

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

Options:

A.

Discuss the issue with the team to resolve the disagreement.

B.

Ensure that there is consensus among the project stakeholders.

C.

Discuss the issue during the next sprint planning meeting.

D.

Support the outcome of the architects’ agreement.

Question 111

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

as

Options:

Question 112

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

Options:

A.

Request help from human resources to keep the key team members on the project.

B.

Work with the project sponsor to determine an appropriate response.

C.

Ask to meet privately with the senior-level executive to discuss the matter further.

D.

Discuss the incident with the key project team members.

Question 113

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

Options:

A.

Accept the change request from country A and reschedule the deployment project for country A.

B.

Take the request into account and ask the sponsor to inform countries B and C about the change

C.

Ask country A to submit a change request that will be analyzed along with countries B and C

D.

Refuse country As request as there is no time for the change as deployment has already begun

Question 114

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Question 115

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project's quality management

D.

Determined a budget reserve for this project

Question 116

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Question 117

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

Options:

A.

Assign an experienced resource to support the team member

B.

Escalate the team member's performance to the project sponsor

C.

Ask the team member to learn the new system as on-the-job training

D.

Issue a change request to extend the project schedule

Question 118

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

Options:

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Question 119

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.

Determine what methods the team has been trained on and utilize those methods for the project.

Question 120

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

Options:

A.

Allow the sponsor to determine how long the planning phase should last.

B.

Allow the client ta determine how long the planning phase should last.

C.

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.

Explain that more features can be planned in upcoming Iterations and begin building the product.

Question 121

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

Options:

A.

Tell the owner that a rough order of magnitude will be provided.

B.

Contact a subject matter expert (SME) for advice and consultation.

C.

Call a meeting with the project team to identify the most appropriate approach.

D.

Tell the owner that the task requires more time and expertise

Question 122

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

as

Options:

Question 123

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

Options:

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

Question 124

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Question 125

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Question 126

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Question 127

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

Options:

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Question 128

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

Options:

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Question 129

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

Question 130

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Question 131

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Question 132

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Question 133

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

as

Options:

Question 134

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan.

B.

Review the communications management plan.

C.

Send the CEO one executive summary per week instead of five reports per week.

D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.

Question 135

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Question 136

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Question 137

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

Options:

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

Question 138

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Question 139

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone

B.

Delay sending a formal communication until the project team catches up

C.

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.

Forego the formal communication and have a conversation with the supervisor

Question 140

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

Options:

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Question 141

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

Question 142

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

as

Options:

Question 143

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Question 144

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

Options:

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Question 145

What should an agile lead do lo ensure their team is set up for success?

Options:

A.

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.

Schedule sprint meetings and coaching sessions to discuss project-related information

C.

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.

Document team tasks and challenges in order to understand when to step in and help a member of the team

Question 146

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

Options:

A.

Assess and evaluate the team member's skills to ensure alignment to the particular requirement and solution

B.

Reassign the requirement to another team member who may have ideas on how to meet the requirement

C.

Assist by connecting the product owner with the team member to discuss what problem is to be solved

D.

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity

Question 147

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

Options:

A.

The functionality is delivered early; therefore, more value is delivered.

B.

The team productivity is higher; therefore, more value is delivered,

C.

The cost is reduced: therefore, the total value delivered is higher.

D.

The risk is significantly reduced; therefore, more value Is delivered.

Question 148

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Question 149

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Options:

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

Question 150

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Question 151

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

Options:

A.

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

Question 152

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.

Instruct the team members involved to resolve the issue among themselves

B.

Discuss the issue with the steering committee to determine the proper course of action.

C.

Coordinate a video conference with the offending team member to resolve the issue

D.

Reassign the offending team member to a different project

Question 153

A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment

What should the project manager do?

Options:

A.

Escalate the issue with an impediment to the project sponsor

B.

Use the contingency budget to implement schedule compression

C.

Implement the mitigation plans listed in the organizational process assets (OPAs)

D.

Reassess the issue as part of monitoring and controlling

Question 154

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact tothe project value.

Question 155

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Question 156

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

Options:

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Question 157

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Question 158

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Question 159

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

Options:

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Question 160

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Question 161

A government approved the construction of a river dam to enable year-round farming in a community. At the project kickoff meeting, a key stakeholder in the community disagrees with the location of the dam.

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan to confirm that all key stakeholders were consulted.

B.

Explain to the key stakeholder that final approval has already been obtained.

C.

Meet with the key stakeholder to review the stakeholder engagement plan.

D.

Schedule a meeting with all stakeholders to discuss the view of this key stakeholder.

Question 162

During a requirements review session with a customer, a team member gets upset when questioned by the customer and responds angrily.

What should the project manager do next?

Options:

A.

Discuss with the whole team the root cause of this issue

B.

Meet with the team member to reset expectations

C.

Provide the team member with space to manage their emotions

D.

Follow up with the whole team to find the best approach

Question 163

A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.

What should the project manager do to ensure effective communication?

Options:

A.

Plan to implement a united communication platform, where all information about the project will be shared and updated regularly.

B.

Ensure all the information about the project implementation is provided to all of the different stakeholders in a unified communication format.

C.

Define communication target groups and provide information, messages, channels, and the frequency of communication for each group.

D.

Arrange an information session for all of the stakeholders about the plans for handling their various communication needs.

Question 164

A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.

What should the project manager do?

Options:

A.

Conduct a round table and ask the team to share their opinions one by one.

B.

Propose new team ground rules and communicate them to all.

C.

Ask the silent team members to share their opinions via email.

D.

Perform focus group interviews based on the new team ground rules.

Question 165

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

Options:

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Question 166

An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.

What should the project manager do first?

Options:

A.

Document the direction and control framework into the project charter.

B.

Develop an engagement plan to achieve consensus.

C.

Identify and interview all of the relevant stakeholders.

D.

Get direction and control framework requirements from stakeholders.

Question 167

The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.

Which three actions should the project manager take? (Choose three)

Options:

A.

Conduct a root cause analysis (RCA) and identify a solution.

B.

Elaborate on the plan to implement a solution and execute it.

C.

Increase the working time to recover the lost time.

D.

Negotiate with the teams involved to manage team dependencies.

E.

Evaluate the effectiveness of the proposed solution.

Question 168

A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.

Options:

A.

Update the issue log and escalate it to the project sponsor.

B.

Remove the deliverables from the iteration backlog.

C.

Meet with the stakeholders and request a solution.

D.

Ask the team to work on the unblocked deliverables.

Question 169

An email arrives shortly after the beginning of a sprint. It is from a key project stakeholder who is unfamiliar with agile approaches and has a serious complaint about future work that has been scheduled. The stakeholder is insisting that a future work package be removed from the backlog entirely, claiming that it is unnecessary.

What should the project manager do?

Options:

A.

Address the stakeholder's request at the daily standup and ask for the team's opinion.

B.

Discuss the stakeholder's request at the next retrospective meeting.

C.

Invite the stakeholder to the backlog refinement meeting to discuss their request.

D.

Alter the backlog to accommodate the stakeholder's request.

Question 170

Due to their different ideas regarding the execution of a project, a conflict has occurred between two stakeholders.

What should the project manager do to resolve the conflict?

Options:

A.

Arrange a group meeting with the stakeholders to generate creative alternatives.

B.

Address the conflict in a planned meeting with all stakeholders and project team members.

C.

Assess the conflict based upon the stakeholders' past disagreements.

D.

Focus on the personal issues between the stakeholders.

Question 171

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

Options:

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Question 172

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

Options:

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Question 173

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

Options:

A.

Add more items to the sprint backlog that will add value.

B.

Complete the sprint and seek a waiver from the regulator.

C.

Complete the sprint, but do not release the deliverable.

D.

Perform a sprint risk assessment and analyze challenges.

Question 174

A project's planning process is finished, and all resources were budgeted for and approved by senior management. Just before the kickoff meeting, a member of the production department realizes that the plan does not meet the requirements for their area.

What should the project manager have done during the planning process?

Options:

A.

Monitored the budget variations during the planning process

B.

Developed a good resource estimation in the planning process

C.

Included all functional managers in the planning process

D.

Distributed the resource estimates to all areas during the planning process

Question 175

Project stakeholders have provided a team with requirements that will take at least one year to complete. The project sponsor advised that they need to see some return on investment (ROI) soon.

What should the project manager do?

Options:

A.

Request additional funding from the project sponsor to accelerate delivery.

B.

Discuss reducing the requirements with the project sponsor in order to release the product earlier.

C.

Prioritize the work into incremental features that can be delivered iteratively.

D.

Acknowledge that the benefits cannot be realized any sooner due to the nature of the requirements.

Question 176

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

Options:

A.

Time and materials (T&M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Question 177

In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.

Which action should the project manager avoid?

Options:

A.

Escalating a conflict within the project

B.

Creating a new communication channel

C.

Giving special attention to this stakeholder

D.

Dismissing the stakeholder's opinions

Question 178

A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.

Which two actions should the project manager take first? (Choose 2)

Options:

A.

Review the conformity management plan to ensure the requirements are clearly defined.

B.

Reference the quality management plans from old projects to determine if they apply to these deliverables.

C.

Add a conformity team member to inspect each deliverable upon receipt from the supplier.

D.

Evaluate industry standards of similar products to determine which apply to this project.

E.

Ask the suppliers to create a statement of conformity when the product is delivered.

Question 179

A new offshore call center project is vital for a company's branch offices. The project is at the end of the planning phase when the project manager is informed by the sponsor that the project will be delayed due to reprioritization.

What should the project manager do?

Options:

A.

Create a messaging group chat with the branch office stakeholders to inform them about the project delay.

B.

Schedule a video conference to inform the branch office stakeholders about the project delay.

C.

Send an official project memo to inform the branch office stakeholders about the project delay.

D.

Include the project delay in the monthly progress report for the branch office stakeholders.

Question 180

A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.

What should the project manager do to manage such a situation for upcoming phases?

Options:

A.

Revise the project schedule to accommodate fixing discovered issues.

B.

Ensure customer validation occurs more frequently during the life cycle of the project.

C.

Review the customer validation team's test plan early in the life cycle.

D.

Ask the project team to increase unit testing of the deliverables.

Question 181

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

Options:

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

Question 182

An organization has successfully delivered many projects using only predictive approaches. The organization has now decided to add some agile development processes into their standard deployment framework.

What should the project manager take into account first when building the schedule for this new project?

Options:

A.

The benchmarked velocities of the previously completed projects

B.

The benchmarked baselines of the previously completed projects

C.

The compliance needs and categories of the new project

D.

The compliance measurement criteria of the new project

Question 183

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

Options:

A.

Analyze the communication needs of the stakeholders.

B.

Communicate the project details to the stakeholders.

C.

Communicate progress more frequently to the stakeholders.

D.

Introduce a separate stakeholder engagement meeting.

Question 184

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

Options:

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.

Question 185

A project manager is leading the development and delivery of a strategic product that must be delivered on time. The project is facing technical issues that could significantly impact the budget and ability to deliver some of the product features.

What should the project manager do first to resolve the issue?

Options:

A.

Record the situation in the risk register and communicate it to stakeholders.

B.

Assess the impact of the feature on the project and ask for a contingency.

C.

Schedule a meeting with the team and management to discuss options.

D.

Develop a quality management plan to clearly identify how features should be classified.

Question 186

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

Options:

A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.

Question 187

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.

Request that all team members receive the newest quality standards training and review one another's work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Question 188

A project is starting its first iteration out of eight. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

Options:

A.

Assign a resource from the core team to handle the acquisition.

B.

Register a risk and escalate it to the project sponsor.

C.

Update the status report with information about this dependency.

D.

Register a risk and monitor its exposure variation.

Question 189

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Question 190

A project team wants to change a delivery approach for a project. Team members explain the need for a review of the information-sharing approach to ensure efficient information exchange during the project.

What should the project manager do?

Options:

A.

Ask the project sponsor to decide on the best communication strategy.

B.

Review the stakeholder engagement plan with the project team.

C.

Ask the project sponsor to approve funding for a collaboration tool.

D.

Review the communications management plan with the project team.

Question 191

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

Options:

A.

Accept the client's observations and pay the penalties as per the project contract details.

B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.

Inform the project director of the change and complete the project so as to not incur any penalties.

D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

Question 192

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?

Options:

A.

US$100,000

B.

US$150,000

C.

US$300,000

D.

US$250,000

Question 193

A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.

What should the project manager do first to manage the team's workload effectively?

Options:

A.

Add additional temporary resources to the project to achieve the next milestone.

B.

Encourage open communication and involve the team in task distribution decisions.

C.

Assign additional tasks to high-performing team members to decrease the burden on others.

D.

Renegotiate the scope of the next milestone with the stakeholders to align with the team's capacity.

Question 194

A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.

What should the project lead do?

Options:

A.

Use Pareto techniques to identify the knowledge required by the majority of the team.

B.

Recommend putting the project temporarily on hold and focus on onboarding and training.

C.

Develop a training curriculum and schedule training delivery throughout the project.

D.

Document the processes and organize a week-long, off-site meeting with the project team.

Question 195

A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.

Which action should the project manager take?

Options:

A.

Ask the team if they can do the work until there is an available supplier.

B.

Train the supplier in agile approaches to help them understand the contract.

C.

Issue a request for proposal (RFP) to find new suppliers with agile experience.

D.

Change contract terms and conditions to avoid losing the supplier.

Question 196

During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.

What should the project manager do?

Options:

A.

Review and update the project management plan to accommodate the delays.

B.

Speak with the project sponsors about changing the project management plan.

C.

Create a change request to increase the cost of resources.

D.

Delay the project until additional resources can be identified.

Question 197

A project manager has just been assigned a major, ongoing project. The project team is not working in harmony and their performance is decreasing. Some team members are autocratic in their approach whereas others are in avoidance mode.

How should the project manager proceed?

Options:

A.

Emphasize their autonomy as project manager, implying that they will not allow team disunity.

B.

Appeal for cooperation from all of the team members, emphasizing the benefit of the project outcome to the company.

C.

Assess the various team behaviors through the use of personality indicators to appropriately deal with each personality type.

D.

Request for removal of the autocratic members who obviously are not interested in the project.

Question 198

During a business review meeting, a key stakeholder raised a concern on the quality of deliverables and has now escalated the concern.

What should the project manager do first?

Options:

A.

Schedule a meeting with all team members to clarify and plan next steps.

B.

Discuss with the stakeholder and share a report on the deliverables.

C.

Discuss with the team and check all reports on the deliverables.

D.

Schedule a meeting with the stakeholder to clarify and plan next steps.

Question 199

A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.

What should the project manager do?

Options:

A.

Demonstrate that risky projects are subject to change so adding reserves to the budget is a necessity.

B.

Explain to the project sponsor and key stakeholders the need to add the reserve and get their buy-in.

C.

Seek key stakeholders' approval and finalize the budget with the reserve.

D.

Agree with the project sponsor and finalize the budget without the reserve.

Question 200

A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.

What should the project manager do?

Options:

A.

Remove the development team's rejected feature from the backlog.

B.

Reassure all team members that the development team will fix the issue.

C.

Initiate an improvement plan for the development team to follow.

D.

Evaluate the context for the conflict with the development team.

Question 201

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?

Options:

A.

Relocate the project to another country that is not shutting down.

B.

Evaluate the possibility of having another country complete the task.

C.

Identify additional team members who are able to complete the task.

D.

Determine if the project has built-in slack to remain on schedule.

Question 202

A project manager has been assigned to a new project. The project sponsor has requested a detailed timeline, but the project includes some deliverables that are not yet clearly defined.

Which project management approach should the project manager advise using?

Options:

A.

As the project includes elements that are not yet clearly defined, an agile approach is the best option.

B.

As the project sponsor has requested a detailed timeline up front, an agile approach is the best option.

C.

As the project appears to have both agile and predictive elements, a hybrid approach is the best option.

D.

As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

Question 203

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.

Align the project goals with the team member.

B.

Reassign the team member to another project.

C.

Nominate the team member to receive agile training.

D.

Allocate another resource to support the team member.

Question 204

A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?

Options:

A.

Schedule meetings every 2 days at the same time with all team members.

B.

Organize a daily meeting for all team members and extend it, if required.

C.

Schedule meetings every 2 days that align with team members' time zones.

D.

Organize a standard meeting time to engage all of the team members.

Question 205

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor's concerns?

Options:

A.

Document the team member's mistake in the lessons learned.

B.

Train the team member to improve their performance to avoid future mistakes.

C.

Talk with the team member to identify the reason for the mistake.

D.

Relocate the team member to another project due to the mistake.

Question 206

A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.

What should the project manager do?

Options:

A.

Review the proposed change with the team and consult the project sponsor for approval.

B.

Evaluate the product owner's proposed change alone and consult the project sponsor for approval.

C.

Submit the proposed change to the change control board (CCB) to evaluate and approve.

D.

Accept the product owner's suggested change and notify the project sponsor of the acceptance.

Question 207

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

Options:

A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

Question 208

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.

What should the project manager do in this situation?

Options:

A.

Review the risk register for this unforeseen circumstance.

B.

Utilize virtual teams for meetings and deliverables.

C.

Use the contingency reserve and subcontract the work.

D.

Ask for an extension of time on the project deliverables.

Question 209

An agile project has completed several iterations. The project manager has been asked to participate in a meeting with the executive functional manager, who is a company leader and the product owner's supervisor. The executive functional manager wants to know about the project deliverables.

What should the project manager focus on for the required meeting?

Options:

A.

Demonstrating the actual working product

B.

Analyzing the project performance of the sprints

C.

Reviewing the team's performance metrics

D.

Reviewing the burndown chart and backlog

Question 210

A project lead has asked a project team to update a 200-page project report and send it to the project sponsor. The team mentioned that nobody reads the report and it takes time away from higher priority work. The project lead responded that they have to show all the work that they performed in every iteration.

What should the project lead do first?

Options:

A.

Summarize the project report so it can be more efficient to read and send it to the project sponsor.

B.

Ensure the communications methods, channels, frequency, and level of detail for the stakeholders are what is needed.

C.

Reinforce the need to document and provide updated information to make the process transparent.

D.

Include a task in every iteration to allocate time for the project team to complete the documentation updates.

Question 211

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

Options:

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Question 212

The project sponsor wants to obtain quick feedback from end users for a product under development. The roadmap is extensive and will not be completed for quite some time.

What should the project manager do?

Options:

A.

Advise the stakeholders that they will need to wait until development is completed in order to get actual end-user feedback.

B.

Hire additional resources to accelerate the schedule and deliver the product faster in order to get actual end-user feedback.

C.

Advise the stakeholders to share images of the finished product in order to obtain valuable feedback from end users.

D.

Work with the stakeholders to determine the minimum requirements needed to get valuable end-user feedback and revise the project schedule.

Question 213

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

Options:

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager's knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

Question 214

During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager's influence, the project team is concerned about the overall impact to the project.

What should the project manager have done?

Options:

A.

Obtained a list of the critical stakeholders from the project sponsor

B.

Consulted with the project sponsor on stakeholder roles and responsibilities

C.

Identified and consulted stakeholders during requirements gathering

D.

Requested stakeholders to participate in project initiation and planning phases

Question 215

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

Options:

A.

11 days

B.

12.5 days

C.

12 days

D.

11.5 days

Question 216

A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.

What should the project manager do?

Options:

A.

Communicate the risks and propose hiring members with leadership experience before continuing with the request.

B.

Decline the scope expansion until the team members get appropriate leadership opportunities within the project.

C.

Implement the scope expansion and suggest the team members get a mentor due to their lack of leadership experience.

D.

Recognize each team member for their contributions and recommend them to the leadership development program.

Question 217

A project sponsor indicates that the time frame for a project needs to be shortened. The project network diagram cannot be modified, but there are extra resources available in the company.

What action should the project manager take?

Options:

A.

Crash the project schedule.

B.

Conduct earned value management (EVM) analysis.

C.

Fast track the project.

D.

Perform Monte Carlo analysis.

Question 218

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

Options:

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Question 219

A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?

Options:

A.

Give some advice to the team member to reduce their stress and anxiety.

B.

Review team participation in the next retrospective meeting with all team members.

C.

Reach out to the team member to discuss and address their concerns as soon as possible.

D.

Evaluate upcoming project deadlines and reorganize team member assignments.

Question 220

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

Options:

A.

Investigate alternatives for team member needs.

B.

Evaluate the engagement needs for stakeholders.

C.

Identify the root cause of the team member's misunderstanding.

D.

Build trust and influence stakeholders.

Question 221

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.

Ask the other project manager to change the delivery methodology.

B.

Request that the other project manager develop a work breakdown structure (WBS).

C.

Participate in the other project's daily standup meetings.

D.

Align with the other project manager's high-level project time lines.

Question 222

A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.

What should the project lead advise?

Options:

A.

During the sprint review, ensure that the completed items deliver business benefits.

B.

Present in detail the business benefits delivered in the sprint during the sprint retrospective.

C.

During the daily standup, ensure that each item meets the definition of done (DoD) before accepting it.

D.

Review in detail the criteria for the definition of done (DoD) for each item during the sprint planning.

Question 223

A project was recently flagged as being noncompliant during an inspection. Several options were suggested on how to address the noncompliance, but each may have different impacts on the budget, schedule, and quality.

How should the project manager proceed?

Options:

A.

Review the risk register.

B.

Perform a cost-benefit analysis.

C.

Determine the cost of change.

D.

Conduct a root cause analysis (RCA).

Question 224

A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.

What should the project manager do next?

Options:

A.

Ask the project sponsor to help with engagement of the key stakeholders.

B.

Communicate project outcomes and results with the key stakeholders.

C.

Define a high-level project scope and share it with the key stakeholders.

D.

Conduct a workshop on project goals and deliverables with the key stakeholders.

Question 225

A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.

What should the project manager do to demonstrate the capabilities of a servant leader?

Options:

A.

Encourage all team members to develop the perfect plan to achieve the desired results.

B.

Create an environment where all team members compete to achieve the desired results.

C.

Assess the business case and define the project priorities to motivate all team members.

D.

Define the project's objectives and create an environment where all team members can succeed in achieving them.

Question 226

A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).

Which two steps should the project lead take to define the MVP? (Choose 2)

Options:

A.

Hold a team meeting to generate a work breakdown structure (WBS).

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a project management plan, including subtasks, to meet the requirements.

D.

Conduct an information gathering session to determine the project value.

E.

Refer to the stakeholder register to determine who should be consulted.

Question 227

A project manager is new to an organization that typically follows a hybrid approach but is shifting to incorporate more agile. A dedicated project team has been provisionally assigned. The new project manager needs to review the internal environment in order to build a high-performing team.

To build a high-performing team, which three factors should the project manager evaluate? (Choose 3)

Options:

A.

Review the team's capability to determine if they have the skill set needed to proceed forward.

B.

Evaluate the infrastructure to determine if the team has the appropriate equipment and communication channels.

C.

Perform a benchmark analysis across similar sectors to determine if the structure can be followed.

D.

Review the customer governance documents so that they align with the set expectations.

E.

Assess the organizational culture to determine if more needs to be done to foster psychological safety.

Question 228

A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.

What should the project manager do?

Options:

A.

Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.

B.

Initiate planning for the project with the modified scope as laid out in the client's purchase order.

C.

Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.

D.

Consult the project sponsor to understand if the change must be processed for project execution.

Question 229

A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.

Which action should the project manager take?

Options:

A.

Apply the new list of approval procedures.

B.

Escalate the issue to the project sponsor.

C.

Ask the project team if the scope can be changed.

D.

Inform the customer that the project will be late.

Question 230

During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?

Options:

A.

Reinforce the initial rules of the negotiations.

B.

Engage a facilitator to support the negotiations.

C.

Concentrate on meeting the customer's requests.

D.

Set clear expectations among the participants.

Question 231

During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.

What should the project manager do first?

Options:

A.

Put the current project work on hold and revisit the scope based on the impacts.

B.

Perform a root cause analysis to assess which deliverables can be reused by the team.

C.

Discuss with the team and implement the revisions that were requested by the sponsor.

D.

Update the business case and seek sponsor approval on the modified project scope.

Question 232

After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?

Options:

A.

Log the issue and see if improvements show in the second iteration.

B.

Log the issue and ask a senior member to coach these team members.

C.

Hire new team members to implement the correct way of testing.

D.

Check lessons learned and use the testing process from previous projects.

Question 233

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Make changes to reprioritize the backlog because of the obstacle.

C.

Reject the obstacle and present the partial solution to the customer.

D.

Focus on generating business value despite the obstacle.

Question 234

An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?

Options:

A.

Incentivize the team with prizes for increased performance and engagement in order to persuade the team member to resume previous performance.

B.

Ask the direct manager to reach out and try to identify the problem, then provide that information back to the project manager.

C.

Inform the team member that a change in performance and engagement is noticed and work together to develop a solution for improvement.

D.

Meet with human resources (HR) to determine the problem and develop a recommendation based on the results.

Question 235

A company is building a minimum viable product (MVP). How should the project manager help to ensure the company builds a high-quality product?

Options:

A.

Ask the product manager to spend more time improving quality.

B.

Determine the quality metrics for the product and recommend options for improvements.

C.

Partner with a qualified third-party vendor to develop a product that meets the requirements.

D.

Hire a quality engineering leader to drive the strategy.

Question 236

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

Options:

A.

Create a communications management plan.

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a kanban board.

D.

Send a copy of the project charter to all project stakeholders.

Question 237

A railroad construction project is in the planning stage. During a monthly progress meeting, an external project manager from the sponsoring organization mentioned there is a potential delay in the design completion date. The external project manager wants to know the impact of this delay on the overall project completion date in the next monthly meeting.

Which three actions should the internal project manager take next? (Choose 3)

Options:

A.

Perform variance analysis.

B.

Validate the critical path method (CPM).

C.

Establish what-if scenario analysis.

D.

Determine the schedule performance index (SPI).

E.

Execute a Monte Carlo simulation.

Question 238

During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.

What should the project manager do first to resolve this issue?

Options:

A.

Register the issue as a risk in the risk register.

B.

Report to the sponsor that there is a new challenge in the project.

C.

Engage an external expert to provide the estimation.

D.

Refer to the organization's lessons learned from past projects.

Question 239

A project team is struggling to meet the project deadline due to a recurring conflict between two team members. What should the project manager do?

Options:

A.

Hold the team collectively responsible for their actions.

B.

Explore the possibility of reshuffling the team.

C.

Introduce training sessions to improve the team's performance.

D.

Schedule team-building activities as required.

Question 240

The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)

Options:

A.

Leverage the project governance system to track and manage the project artifacts.

B.

Create a central repository system to assess the effectiveness of the project artifacts.

C.

Review the execution roadmap and ask the legal team to manage the artifacts.

D.

Ensure the project artifacts are kept up to date and accessible to all stakeholders.

E.

Work with the team to determine the process to manage the project artifacts.

Question 241

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

Options:

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

Question 242

The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?

Options:

A.

A release burndown chart

B.

Analysis of the business requirements document

C.

Story points for the remaining user stories

D.

Surrogate measurements

Question 243

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.

What should the project manager do?

Options:

A.

Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority

B.

Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities share this with all stakeholders, and ask the team to complete their tasks as scheduled

C.

Conduct a general meeting with all stakeholders and review and address a list of activities for each of them

D.

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities

Question 244

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

as

Options:

Question 245

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee

B.

Functional managers

C.

Board of directors

D.

Advisory team panel

E.

Chief executive officer

Question 246

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experienceto build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Question 247

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

Options:

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Question 248

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

Options:

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

Question 249

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) -> stops working and crashes the system

1.500 rpm (rate-per-minute) -> warns of max rate allowed

1.400pm (rate-per-minute) -> reduces the power and brakes the engine

Which of the following statements is correct?

Options:

A.

0 1,600 rpm is a project risk,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.1,500 rpm is a project issue and 1,400 rpm is a project risk.

Question 250

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

as

Options:

Question 251

An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right

as

Options:

Question 252

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

Options:

A.

Select a predictive development life cycle based on the team's experience

B.

Determine the most appropriate life cycle approach for the project

C.

Register all requirements into a backlog for further detailed analysis.

D.

Split the requirements, put them into two separate projects, and apply different approaches

Question 253

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

Options:

A.

Organize regular meetings with all of the deployment teams to share issues and solutions

B.

Propose that some of the teams delay deployments in their countries

C.

Ask the project sponsor to appoint new managers for the deployment teams

D.

Ask each deployment team to provide a very detailed schedule and action plan

Question 254

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Options:

A.

Share the project documents and invite the key stakeholder to discuss any concerns

B.

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

C.

Proceed with a working session for teams that do not belong to that key stakeholder

D.

Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy

Question 255

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Question 256

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

Options:

A.

Five whys

B.

Communications management plan

C.

Ishikawa diagrams

D.

Issue log

E.

Open-space meetings

Question 257

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

Question 258

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Question 259

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

Options:

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Question 260

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

Question 261

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two)

Options:

A.

Issue log

B.

Risk register

C.

Stakeholder register

D.

Change log

E.

Backlog register

Question 262

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

Options:

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Question 263

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

Options:

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B.

Review the contract requirements and ask for the applicable evidence for quality assurance

C.

Have the vendor issue the quality documentation prior to the next delivery.

D.

Call the vendor and have them verbally guarantee the quality of the next site delivery

Question 264

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Question 265

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

Options:

A.

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.

Estimate the financial impact of the impediments and request additional funding

C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.

Capture the impediments and inform management that their assistance is neededin resolving the impediments

Question 266

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

Options:

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Question 267

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

Options:

A.

Consult the project scope document to make sure the addition is in scope.

B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.

Engage the stakeholder to solicit more information before responding to the request

Question 268

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

Options:

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Question 269

A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

as

Options:

Question 270

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences

B.

Hire a coach to help all project teams to improve their abilities to solve problems ontheir own.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity

D.

Recommend to the project team members that they should improve their planningand make their stones smaller

Question 271

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

Options:

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Question 272

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

Options:

A.

Allocate and use part of the project's contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community

Question 273

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

Options:

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder's understanding during the kick-off meeting

Question 274

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

Options:

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Question 275

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.

B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly

C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties

D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer

Question 276

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

as

Options:

Question 277

Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished

What should the project manager have done differently?

Options:

A.

Formed a separate quality assurance team to test all items coming from each team at the end of each sprint

B.

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments

C.

Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

D.

Arranged an online session on the integration concept and suggested tools to the teams

Question 278

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

Options:

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Question 279

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Question 280

The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members

What two actions should project manager take? (Choose two)

Options:

A.

Ask the team members to work it out themselves

B.

Discuss this situation with other project managers and ask for advice

C.

Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules.

D.

Address the behavioral issue with each team member

E.

Discuss the behavior directly with their managers and request them to correct the behavior.

Question 281

The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?

Options:

A.

Ask the vendor to identify the stakeholders affected, create an action plan and determine an implementation date

B.

Draft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable

C.

Identify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.

D.

Contact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation

Question 282

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

Options:

A.

Determine which agile software tools will be required to support agile delivery within the organization

B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project

C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted

D.

Determine how to transform the organization using agile techniques, including organizational training and communications

Question 283

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

Options:

A.

Prepare a change request and seek approval from the steering committee regarding the new project framework

B.

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan

C.

Bring in a third party company to develop and implement a hybrid framework for this specific project.

D.

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects

Question 284

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people tocompensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Question 285

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

Options:

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Question 286

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?

Options:

A.

Involved the key stakeholders in the decision-making process

B.

Customized stakeholder communications based on the stakeholders’ needs

C.

Analyzed the changes in stakeholder attributes

D.

Documented the project vision and objectives

Question 287

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

Options:

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Question 288

A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company

What should the project manager do first?

Options:

A.

Organize individual sessions with the stakeholders to build awareness and trust in the new framework

B.

Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.

C.

Send documentation to the senior manager about the advantages of the new framework

D.

Escalate the senior manager's concern to the project sponsor and distribute the status to the team

Question 289

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

Options:

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

Question 290

In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.

What should the project manager do?

Options:

A.

Let the developers focus on the refactoring work and discuss it in the retrospective

B.

Restate to the developers the importance of focusing and meeting the sprint goal.

C.

Praise the developers for their proactivity and focus on quality.

D.

Escalate the issue to the developers’ functional managers

Question 291

A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects

What should the project manager do?

Options:

A.

Schedule a steering committee meeting and obtain their approval on the request

B.

Support the decisions of the team and transfer the decision making responsibility to them.

C.

Inform the team that although this is a hybrid environment, the project managermust still be responsible for making decisions

D.

Consult the product owner about letting the resources make decisions

Question 292

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

Question 293

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project

What should the project manager do?

Options:

A.

Use the management reserves to fund some team-building activities

B.

Inflate project estimates to provide a financial buffer for team activities.

C.

Find another method to increase the team's performance

D.

Implement a reward system aimed to keep the team engaged and motivated

Question 294

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

Options:

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

Question 295

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

Options:

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Question 296

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

Options:

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

Question 297

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.

Have the team inform senior management of the situation and ask for recommendations.

D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Question 298

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

Options:

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

Question 299

The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance

C.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

D.

Restrict the project scope only to basic critical features and run the project with the current staffing level until all of the budget is consumed

Question 300

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)

Options:

A.

A team member talking about a user story that is not on the Scrum board

B.

A team member talking about a user story that is on the Scrum board

C.

A technology that blocks agile capabilities

D.

A lack of team empowerment and an inability to self-organize

E.

A review of the backlog at daily standup meetings

Question 301

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Question 302

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.

Raise the issues in the retrospective and propose solutions

B.

Inform management that commitments will not be met.

C.

Involve management to help resolve the conflicts

D.

Coach the team both as a whole and individually

Question 303

A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information

How should the project manager handle this situation?

Options:

A.

Apply lean manufacturing to limit the team’s work

B.

Increase retrospectives to deliver results fast

C.

Make work visible using kanban boards.

D.

Incorporate small batches of work into the project

Question 304

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Question 305

A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members

What is the cause for this communication gap?

Options:

A.

The project sprint board has not been updated

B.

Daily standup meetings were not held or enforced

C.

The project status dashboard has not been updated

D.

The communications management plan has not been developed

Question 306

During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated How should the project manager have handled documentation for the project?

Options:

A.

Updated the project management plan regularly and had it securely shared with all stakeholders

B.

Assigned a project team member to ensure all project documentation was updated

C.

Reviewed the risk register to identify a response plan for the audit

D.

Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders

Question 307

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)

Options:

A.

Conduct a stakeholder analysis.

B.

Reinforce team communication.

C.

Update the project management plan with the new timeline

D.

Adopt an incremental approach

E.

Leverage work between team members

Question 308

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification

B.

Promote the team member to product owner to leverage the new knowledge with the clients

C.

Provide an incentive to team members who begin using the new tool on this project.

D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Question 309

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

Options:

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Question 310

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Question 311

A project manager has received an updated earned value analysis report The following are the key findings from the report

•Budget at completion = USS1 million

•Earned value = US$0 7 million

•Actual cost = US$0 75 million

•Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance'?

Options:

A.

The project will be completed exactly as planned

B.

The project will be easier to complete than planned

C.

The project will be difficult to complete as planned.

D.

The project will not be completed as planned

Question 312

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Question 313

Drag the communication event on the left to the mam subject discussed during the event on the right.

as

Options:

Question 314

The following table shows the business value created and the development effort required to implement various features in a product

as

Which feature should the team prioritize first? Enter the feature name in the box below

as

Options:

Question 315

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

Options:

A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.

Update the communications management plan and implement the change

C.

Meet with the project sponsor to discuss how to address the situation.

D.

Meet with the stakeholder prior to the meeting to obtain their opinion

Question 316

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

Options:

A.

Schedule a meeting for the project team to review the communications management plan.

B.

Tell the rest of the project team to continue discussions with the new team member

C.

Send an email to the project team outlining the communications strategy.

D.

Mentor the new team member on the methodology the project team is using

Question 317

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

Options:

A.

Contingency control in the project and rebaseline

B.

Mitigation control in the project

C.

Benefits management control in the project

D.

Integrated change control in the project

E.

Currency exchange rate

Question 318

A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.

What should the project manager do next?

Options:

A.

Make a change request regarding the project's scope to ensure compliance.

B.

Include an assessment to verfy compliance in the next iteration

C.

Conduct an iteration review to address the new regulation

D.

Start the tests over, adapting the trials to the new regulation

Question 319

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.

Use soft skills to convince the project sponsor to approve the new budget estimate

Question 320

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

Options:

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked

Question 321

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

Options:

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Question 322

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?

Options:

A.

Contact the functional managers to request substitutes for the conflicting team members.

B.

Send a warning to both team members indicating that if the issue continues, both will be removed from the project.

C.

Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.

D.

Escalate both team members to their respective functional managers and let them take the appropriate actions

Question 323

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone's schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Question 324

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

Options:

A.

Assure the senior manager that these features will be queued up in the next sprint.

B.

Meet with the team to understand why the senior manager’s features were not included.

C.

Invite the senior manager to the next planning meeting.

D.

Send the product roadmap to the senior manager.

Question 325

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Question 326

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Question 327

A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?

Options:

A.

Send communications for clarification so there is a full understanding about the situation.

B.

Demonstrate the performance indexes and recommend corrective actions to the stakeholders

C.

Schedule a kick-off session to explain the problems of the project and gain approval and support

D.

Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders

Question 328

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

Question 329

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

Options:

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Question 330

A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?

Options:

A.

Express trust in the team's ability to fulfill the necessary deliverables.

B.

Assert judgment over the team.

C.

Use a plan-driven approach in order to demonstrate control over the project.

D.

Increase the amount of subject matter experts (SMEs) to get better results.

Question 331

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Question 332

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

Options:

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Question 333

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Question 334

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

Options:

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

Question 335

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

Options:

A.

Enforce the project manager's authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project's implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Question 336

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Question 337

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

Options:

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.

Conducted routine meetings and identified team members who are under performing

Question 338

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

Options:

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

Question 339

A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.

How should the project manager handle this situation?

Options:

A.

Discuss the company culture with the supervisor to clarify expectations.

B.

Review the overall organizational culture of the company again.

C.

Request that the new supervisor be assigned to another project.

D.

Explain to the workers that they need to listen to the supervisor.

Question 340

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Options:

A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.

Update the stakeholder register and risk management plan.

C.

Update the stakeholder register and revise the stakeholder engagement plan.

D.

Explain to the community members why they were not included as stakeholders for the project.

Question 341

A supplier was supposed to mobilize a government-issued, licensed piece of

equipment two days ago, but did not. The procurement manager was informed that the

supplier failed to check the validity of the license, which expired last week. The supplier had

already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.

Which action should the project manager take?

Options:

A.

Update the project team on the delay so that resources can be utilized elsewhere.

B.

Analyze the schedule and look for fast tracking and crashing alternatives.

C.

Review the terms of the contract in order to determine next steps.

D.

Update the lessons learned register to serve as an input for future material transactions.

Question 342

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Question 343

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

Question 344

An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?

Options:

A.

Have the team consult with the compliance officer to update the definition of done(DoD) for the user stories in the past sprint.

B.

Have the product owner consult with the change control board (CCB) to have thenecessary compliance requirements implemented.

C.

Have the scrum master organize a weekly meeting with the compliance officer, theproduct owner, and the project team.

D.

Have the product owner review the user stories in the product backlog with thecompliance officer on a regular basis to identify any gaps.

Question 345

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?

Options:

A.

Create a parallel sprint to deliver the additional items.

B.

Guide the agile team to add the new scope to the product backlog.

C.

Pause the sprint to allow time to include the new items.

D.

Moderate the expectations for sprint quality.

Question 346

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

Options:

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Question 347

Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.

What should the project manager have done earlier to change the product owner's behavior''

Options:

A.

Worked on a fixed-price contract to switch the product owner's attention to value instead of money

B.

Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies

C.

Worked on different approaches of estimating to give confidence of the cost spent in each product increment.

D.

Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies

Question 348

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

Options:

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

Question 349

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Question 350

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Question 351

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

Options:

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.

Question 352

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

Options:

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

Question 353

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

Options:

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

Question 354

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

Options:

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Question 355

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Question 356

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''

Options:

A.

The project is on budget and on schedule.

B.

The project is over budget and behind schedule

C.

The project is under budget and behind schedule.

D.

The project is under budget and on schedule.

Question 357

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Consult with the project management office (PMO) for guidance on project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference.

D.

Document the project sponsor's instructions as the archived project artifacts.

Question 358

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

Options:

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

Question 359

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Question 360

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

Options:

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

Question 361

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

Options:

A.

Attach a note to the project management plan about the team member

B.

Hold a project team meeting about the team member's contribution and take minutes

C.

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.

Send a communication to management recognizing the team member's contributions

Question 362

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Question 363

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Question 364

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

Options:

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

Question 365

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

Options:

A.

Ask the project sponsor to replace the contractor since they do not have agile experience

B.

Issue a formal notice to the contractor to obtain an agile certification

C.

Consult the project team to understand the extent of the training needs for the contractor

D.

Instruct the contractor to receive agile training since the project has already started

Question 366

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

Options:

A.

Reducing cost for the customer

B.

Delivering value to the customer

C.

Working together as a team

D.

Finishing the project on schedule

Question 367

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

Options:

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Question 368

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

Options:

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

Question 369

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

Options:

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

Question 370

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.

B.

Organize frequent team building sessions and update the risk register.

C.

Meet with the project sponsor and propose a corrective action for the project.

D.

Encourage participation in decision making and empower the team.

Question 371

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Question 372

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Question 373

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Question 374

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

Options:

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team's agile maturity.

D.

Support the team members' growth and development.

Question 375

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

Options:

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Question 376

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Question 377

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

Question 378

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

Options:

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Question 379

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

Options:

A.

Escalate the issues to the project sponsor.

B.

Review the issues log to ensure the issues are captured.

C.

Check the risk management plan to ensure there is a strategy to address the issues.

D.

Ask the key stakeholders to discuss the issues with the project team.

Question 380

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

Options:

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

Question 381

A product owner has an idea for a new product but is struggling to define the

features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?

Options:

A.

Assess the product roadmap to see if there is another product that is more suitable for the build.

B.

Develop a minimum viable product (MVP) for assessment from a select customer group.

C.

Commission a business analyst to research similar competitor products.

D.

Complete a work breakdown structure (WBS) to assess the cost of each feature

Question 382

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Document the project sponsor's instructions as the archived project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference

D.

Consult with the project management office (PMO) for guidance on project artifacts.

Question 383

A project manager is assigned to oversee the deployment of a new product that

will be used by the entire organization. A key success factor for the project is the timely

and successful adoption of the new solution by all entities.

What should the project manager do to ensure the success of this critical project?

Options:

A.

Considering the project scope and the multiple entities impacted by the solution,communicate with the stakeholders and ask them to adhere to the date.

B.

Ask the project sponsor to issue a directive requesting all business entities toaccept the date set for the new solution launch.

C.

Given the size of the organization and the multiple parties involved, discuss thelaunch date with the CEO and then communicate it to all entities.

D.

Engage in creative and iterative negotiations with the leaders of each entity toagree on the launch date.

Question 384

Drag the technical practices on the left to the scenario on the right.

as

Options:

Question 385

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

Question 386

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Question 387

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.

Assess the impact of the new requirements and initiate the change request process.

B.

Work with the product manager and the rest of the team to update the project backlog.

C.

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.

Follow the change management plan to update the risk register so It accounts for the added scope.

Question 388

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

Options:

A.

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.

B.

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.

C.

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.

D.

Secure some additional funding to recruit more resources to the project team to enable faster delivery.

Question 389

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

Options:

A.

Review the base model with the team leaders in each country to establish anindependent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of differentcultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Question 390

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

Options:

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

Question 391

A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?

Options:

A.

Ask the team member to complete as much as they can now.

B.

Ask the team member to work with their peers to knowledge share

C.

Ask the team member to identify their specialist tasks

D.

Ask the team member to host a special team meeting.

Question 392

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

Options:

A.

Refer to the requirements traceability matrix.

B.

Revise the project scope baseline.

C.

Escalate the change request to the project sponsor.

D.

Review the approved project charter.

Question 393

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Question 394

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

Options:

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Question 395

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Question 396

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

Options:

A.

Request the team member to move to another team.

B.

Delegate other team members to complete this team member's tasks.

C.

Mentor the team member and provide the necessary training.

D.

Include this team member in an improvement program through a human resources request.

Question 397

The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

Options:

A.

Meet with the project sponsor as soon as possible to discuss the matter further

B.

Update the issue log to make the project team aware and to develop a strategy

C.

Create a stakeholder engagement plan to help the team formulate a response

D.

Provide the specifications to the project sponsor with some information removed

Question 398

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Question 399

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.

Question 400

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

Options:

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Question 401

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Question 402

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

Options:

A.

File a change request to make the customer billable for all extra costs incurred for the project.

B.

Ask the accounting department to forward all project expenses to the project manager's email.

C.

Monitor the budget for the project continually and anticipate any issues if possible.

D.

Ask the project resources to finish their assignments in less time than originally planned.

Question 403

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

Question 404

During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.

How should the project manager help guide the lead developer?

Options:

A.

Advise the lead developer and team to consult with the project architect and for their development team leader.

B.

Reassign this work package to another area given the lead developer's concerns,

C.

Direct the lead developer to conduct a weighted evaluation of all products and solutions.

D.

Listen to the concerns and suggest that the lead developer and the team be empowered to recommend the best approach.

Question 405

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Options:

A.

Escalate the issue to the engineer's functional manager.

B.

Discuss the issue with the engineer and determine how to prevent another problem.

C.

Document the task on the kanban board and make it the highest priority.

D.

Assign another engineer to the task due to the urgency.

Question 406

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

Options:

A.

Included lessons learned from past projects

B.

Used bottom-up estimating

C.

Utilized three-point estimates

D.

Validated the schedule performance index (SPI) to evaluate deviation

Question 407

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.

Question 408

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.

Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.

B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.

C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.

D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders' approvals.

Question 409

A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.

What should the agile project manager do to engage the stakeholder in the project?

Options:

A.

Present the project management plan to the stakeholder and reassure them that they will receive regular project updates.

B.

Introduce the stakeholder to the project team and invite them to the next iteration review meeting with the IT team.

C.

Build trust with the stakeholder by keeping project commitments and use demo sessions to gather feedback and realign goals.

D.

Use stakeholder mapping to document the level of influence and interest for the next iteration planning meeting.

Question 410

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Question 411

A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

Options:

A.

Analyse the team members' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

Question 412

After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

Options:

A.

On schedule

B.

Ahead of schedule

C.

Stopped

D.

Behind schedule

Question 413

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Question 414

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Study and determine the appropriate leadership style suitable for the team.

B.

Hire a project team leader who can influence the project team members.

C.

Schedule a meeting and communicate the performance concern to the team.

D.

Apply an agile approach to help improve team performance.

Question 415

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

Options:

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Question 416

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

Options:

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements

Question 417

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?

Options:

A.

Sprint plan and product roadmap

B.

Product roadmap and sprint backlog

C.

Product backlog and scrum board

D.

Sprint backlog and scrum board

Question 418

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

Options:

A.

Request approval from the company director to conduct training for the team.

B.

Ask the senior developer to rewrite all the stories.

C.

Engage with the customer and rewrite all the stories.

D.

Rewrite the stories to include the technical vision of the product.

Question 419

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

Options:

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

Question 420

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Question 421

A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

Options:

A.

Monitor all stakeholders.

B.

Keep all stakeholders informed.

C.

Analyze the stakeholders.

D.

Engage the stakeholders.

Question 422

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Question 423

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Question 424

A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even

though reports have been sent on a weekly basis.

What should the project manager do to ensure all stakeholders are receiving proper information about the project?

Options:

A.

Hold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.

B.

Create daily progress reports and send them to all stakeholders.

C.

Include stakeholders in the weekly status meetings with the team.

D.

Assess all of the project stakeholders and document their preferred communication method and frequency.

Question 425

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

Options:

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

Question 426

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

Options:

A.

Plan the project to deliver value incrementally with regular releases.

B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime

C.

Identify tasks that can run in parallel to deliver the project faster.

D.

Ask the project sponsor to provide additional resources to fast track the project.

Question 427

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to

water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Question 428

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

Options:

A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.

B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.

C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.

D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.

Question 429

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the

documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

Options:

A.

Create a specific sprint to deliver the project documentation.

B.

Assign a dedicated resource to work on the documentation during the project.

C.

Make documentation a standard part of the definition of done (DoD).

D.

Focus on the documentation after the features are delivered.

Question 430

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

D.

In the initiation process, as it happens concurrently with the project contract and project charter creation

Question 431

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

Options:

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Question 432

A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide

any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.

What should the project manager do to ease the situation?

Options:

A.

Talk to the customer and project team member separately to assess the issue and decide on the next steps.

B.

Remove the project team member immediately and assign the pending activities to other team members.

C.

Tell the customer that they do not have the authority to remove project team members.

D.

Ask the project team member to call the customer to apologize for their behavior.

Question 433

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

Options:

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previousways of working.

D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

Question 434

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

Options:

A.

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.

Work with the local government to build the profiles of employees that will be working in the store.

C.

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

Question 435

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

Options:

A.

Create better plans to test the functionality in more detail.

B.

Review the definition of done (DoD) with the product owner.

C.

Include previous sprint defects and close them in the actual sprint.

D.

Get approval from the product owner on the user stories.

Question 436

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Question 437

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

Options:

A.

Organize a meeting with the team and update the work breakdown structure (WBS).

B.

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.

Start the organization's change control process via a change request.

D.

Communicate with an officer in the environmental protection department to check if it is necessary.

Question 438

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Question 439

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to complianceregulations.

B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Question 440

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

Options:

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Question 441

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Question 442

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Ignore the obstacle and present the partial solution to the customer

C.

Focus on generating business value despite the obstacle

D.

Make changes to reprioritize the backlog because of the obstacle.

Question 443

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Question 444

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Question 445

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?

Options:

A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Question 446

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)

Options:

A.

Keep the team engaged and focused on the project's direction.

B.

Encourage the team to do a brainstorming session and provide a mitigation plan.

C.

Focus on the resource management plan and track project progress,

D.

Set a clear vision for the project and ensure it is visible to all stakeholders.

E.

Organize a team-bonding activity and invite an external manager to speak to the team.

Question 447

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.

Inform the functional manager that self-organization includes task allocation.

B.

Confirm with the team members that the functional manager is responsible for the delivery.

C.

Ask the product owner to clarify the roles and responsibilities of the project team.

D.

Inform the functional manager that task allocation is the responsibility of the product owner.

Question 448

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

Options:

A.

Review the issue with project sponsor and submit a change request

B.

Report the issue to the product manager and business segments

C.

Analyze the business benefits criteria and assumptions

D.

Discuss the issue with the operations team to assess expense overruns

E.

Schedule a project review meeting to analyze the root cause

Question 449

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

Options:

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

Question 450

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

Options:

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Question 451

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

Options:

A.

Review the project time line and find opportunities to reduce the project schedule.

B.

Review the budget with the project sponsor and ask for an increase to the budget

C.

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.

Review the resource management plan and find opportunities to reduce project costs.

Question 452

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

Options:

A.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert's availability within the organization on an as-needed basis.

C.

Develop the team member's capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

Question 453

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

Options:

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Question 454

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings,

the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.

How should the project manager ensure that project risks are reported accurately in the risk register?

Options:

A.

Review the risks throughout project execution.

B.

Plan to update the risks at project closure.

C.

Update the risks in the risk management plan.

D.

List the project risks identified in the kick-off meeting.

Question 455

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Question 456

A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools.

What should the project manager do to ensure team members are committed to project success?

Options:

A.

Control and follow the project's mam goals, budget, and schedule

B.

Plan regular virtual meetings to motivate and support the team.

C.

Meet in small groups and share information by email with the rest of the team

D.

Create a monthly report so everyone will be informed of the current status.

Question 457

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

Options:

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

Question 458

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

Options:

A.

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

Question 459

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

Options:

A.

Understand the customer's perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

Question 460

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Motivate the team member to stay by providing them with incentives.

D.

Ask human resources (HR) to counsel the team member to balance the workload.

Question 461

A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to

reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project

manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide

upon the most effective way to communicate progress.

What should the project manager do?

Options:

A.

Send weekly emails to each stakeholder providing them with the project's progress.

B.

Ask the project sponsor to disseminate project progress across the organization's stakeholders.

C.

Set up an intranet site and allow stakeholders to access the relevant project information.

D.

Divide up the organization among the project team to provide direct project updates.

Question 462

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Question 463

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

Options:

A.

Increase the frequency of updates given to this stakeholder.

B.

Inform the team member to stop sending any further updates to the stakeholder.

C.

Raise this issue to the project sponsor in the next project status review meeting.

D.

Review this stakeholder's communication requirements.

Question 464

In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have

most likely caused this communication breakdown?

Options:

A.

The sprint review meetings were not held regularly.

B.

The daily standup meetings were not consistently attended.

C.

The project manager failed to develop a communications management plan.

D.

The weekly project status reports were not published regularly.

Question 465

A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?

Options:

A.

Escalate the issue to the project sponsor and seek their immediate intervention.

B.

Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

C.

Assign the unallocated tasks to the project management office (PMO) manager and reallocate when the resources are available.

D.

Ignore the unallocated tasks for now and reallocate when the resources are available.

Question 466

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

Options:

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

Question 467

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

Options:

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Question 468

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Question 469

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Question 470

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

Options:

A.

Seek help from experts to support the team member in fixing the problem.

B.

Facilitate a session to reach an agreement with the team as a whole.

C.

Negotiate with the customer a delay in the project delivery.

D.

Accept the team's request to reassign the team member.

Question 471

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

Options:

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.

Escalate the issue to the functional manager and ask for support.

C.

Involve all stakeholders in the project by distributing status reports.

D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.

Engage all stakeholders in the project including the unsupportive stakeholders.

Question 472

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

Question 473

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress

What should the project manager do first?

Options:

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

Question 474

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

Question 475

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

Options:

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Question 476

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Options:

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Question 477

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Question 478

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

Options:

A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Question 479

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Question 480

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

B.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

C.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Question 481

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

Options:

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Question 482

A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.

What should the project manager do?

Options:

A.

Allow the team to proceed as they attempt to meet the timeline.

B.

Add a subject matter expert (SME) to the project team.

C.

Invite stakeholders to discuss a mitigation plan to finish on time.

D.

Fill the skill gap personally to execute the project.

Question 483

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product

owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer

features or low quality.

What should the project leader have done to ensure success?

Options:

A.

Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery

B.

Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints

C.

Asked the team to create an impediment log and keep it updated for use in the next sprint planning

D.

Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

Question 484

A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.

What should the project manager do in this situation?

Options:

A.

Schedule a meeting with the reluctant project stakeholder to obtain their feedback.

B.

Meet with all seven of the project stakeholders and request all of their feedback.

C.

Explain to the sponsor why the reluctant stakeholder needs to provide feedback.

D.

Host a meeting with the reluctant stakeholder and project team to resolve any conflict.

Question 485

A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise.

Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)

Options:

A.

Arrange a daily learning session for project team members during lunch to facilitate knowledge transfer.

B.

Allow each team member time in the retrospective sessions to share a little bit about their role and areas of knowledge.

C.

Assess the gaps and assign an expert resource for respective areas of knowledge.

D.

Identify external subject matter experts (SMEs) and plan training sessions to conduct knowledge transfer.

E.

Schedule shadowing sessions among team members to facilitate team learning.

Question 486

A project manager is assigned to a multiyear project. During project execution, the customer delegates a new representative who contacts the project manager directly with a concern about their participation in status meetings. The representative wants to contact team members directly.

What should the project manager do next?

Options:

A.

Send the new representative the approved project management and communications management plans.

B.

Reach out to the customer directly for assistance in incorporating the new representative into the project management plan.

C.

Meet with the project sponsor to discuss how to incorporate the new representative in the project.

D.

Meet with the new representative to determine their understanding of the project and address their concerns.

Question 487

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?

Options:

A.

Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.

B.

Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.

C.

Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.

D.

Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.

Question 488

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV)

to actual cost (AC) for the project and has found the calculated result to be 0.9024.

What does this value mean for the project?

Options:

A.

The project has started exceeding the planned cost.

B.

The project is earning less value an was planned.

C.

The project has earned more value than planned.

D.

The project is close to exceeding the planned cost.

Question 489

A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress

(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.

What should the project manager have done to avoid this situation?

Options:

A.

Stored project documentation in a shared folder.

B.

Organized monthly meetings with the external stakeholders.

C.

Invited all of the stakeholders to daily standup meetings.

D.

Sent weekly status update reports to all of the stakeholders.

Question 490

A senior project manager has included a junior project manager as part of the project team. During a coaching session, the junior project manager

asks the senior project manager how to be efficient and reduce rework.

How should the senior project manager respond?

Options:

A.

Use a work breakdown structure (WBS) to create a project schedule based on the project and resource requirements.

B.

Monitor resource allocation to ensure that team members work 8 hours per day.

C.

Assign project tasks to the team regardless of their skills to accomplish the project schedule.

D.

Schedule daily meetings with key stakeholders to assess the effectiveness of the project management plan.

Question 491

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?

Options:

A.

Set up a meeting with the product owner to discuss the stakeholder's concern.

B.

Discuss this with the team and review the project requirements documentation.

C.

Set up a meeting with the sponsor to discuss the details of the deliverable.

D.

Discuss this with the team and put the stakeholder's concern in the issue log.

Question 492

A project manager is managing a project that requires specialized architecture services. This project was identified as a high risk for the

organization. The project manager works with an external architect who is highly specialized. However, the architect will soon resign because they

accepted an offer from another firm.

What should the project manager do next?

Options:

A.

Discuss this with the project team, assess the impact, and decide on the appropriate actions to follow.

B.

Ask the architect for the contact details for their new employer and call their account manager.

C.

Call the account manager and ask them to retain the expert by offering them an incentive.

D.

Escalate the issue to the procurement department and ask them to discuss this with the vendor firm.

Question 493

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Options:

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

Question 494

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

Options:

A.

A predictive execution strategy

B.

A hybrid execution strategy

C.

An iterative execution strategy

D.

An agile execution strategy

Question 495

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.

Assign the task to someone else on the team.

B.

Discuss it with the team member in confidence.

C.

Discuss this matter during the project meeting.

D.

Include this item in the risk register.

Question 496

Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.

How should the project manager impartially prioritize the requirements to be integrated?

Options:

A.

Retain only requirements that result in profitable revenue growth.

B.

Ensure the CEO selects the requirements from all department leaders.

C.

Give each department a fixed budget that will cover ten requirements.

D.

Rank the requirements with the highest benefit-cost ratio as more important.

Question 497

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

Options:

A.

Log the technical design delay as a risk in the project risk log.

B.

Set up a steering committee session to review the project delay.

C.

Continue with the approved design so that the project is not delayed.

D.

Ask the steering committee to approve a new technical design.

Question 498

At the beginning of a project, a project manager is asked to provide human resources (HR) with an evaluation of every team member's performance. This evaluation will be delivered at the end of the project.

How should the project manager approach this request?

Options:

A.

Establish a set of objective and measurable performance indicators for evaluating team members and share it with the team.

B.

Ask the project team how they would prefer to be evaluated and use those criteria to share results with HR.

C.

Evaluate the project team members' performance based on whether the completed project fulfills its intended objectives.

D.

Meet with HR at the end of the project and provide a confidential evaluation of every team member's performance.

Question 499

A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?

Options:

A.

Discuss this issue with the affected team members and support them during the transition.

B.

Start looking for replacements as soon as possible to help prevent any schedule slippage.

C.

Engage with the project sponsor to ensure that this change does not affect the project execution.

D.

Determine the impact to the project and implement mitigations per the project management plan.

Question 500

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.

Ask the Scrum team members to share retrospectives.

B.

Ask the scrum master to attend the workshops.

C.

Invite the Scrum team members as optional participants.

D.

Invite the Scrum team members as mandatory participants.

Question 501

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated

by other team members.

Which three actions should the project manager take? (Choose three)

Options:

A.

Arrange and conduct team-building sessions to improve team effectiveness.

B.

Allow team members to resolve personal issues without involving the project manager.

C.

Get feedback from other team members to understand what led to this situation.

D.

Identify the isolated team member as a risk and document the situation in the risk register.

E.

Obtain feedback from the isolated team member to understand the situation.

Question 502

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

Options:

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

Question 503

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the protect manager do?

Options:

A.

Perform quality control analysis.

B.

Perform root cause analysis (RCA).

C.

Perform trend analysis.

D.

Perform schedule analysis.

Question 504

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the

importance of this document to the project manager?

Options:

A.

Needed to close the work breakdown structure (WBS).

B.

Needed to share it with the stakeholders.

C.

Needed to close out the project or a phase.

D.

Needed to release the team at the end of the project.

Question 505

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.

What should the project manager do?

Options:

A.

Reschedule on-site training to online sessions.

B.

Create a risk and assign remediation actions.

C.

Cancel all of the on-site training sessions.

D.

Document the project issue and provide options.

Question 506

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has

too many items to allow on-time delivery.

What should the project manager do first?

Options:

A.

Update the risk register and present a contingency plan to meet the deadline.

B.

Suggest to the customer to reduce the backlog to meet the date.

C.

Increase the capacity of the team to finish the project on time.

D.

Ask the team to propose a minimum viable product (MVP) to meet the date.

Question 507

A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with their project tasks.

What should the project manager do first?

Options:

A.

Issue a formal complaint to the project sponsor claiming a lack of proper tools.

B.

Meet with the IT team to evaluate how fast the software license can be renewed.

C.

Ask the team to fast-track the project and perform tasks that do not require calculations.

D.

Ask the team members to find an alternative way to perform calculations.

Question 508

A healthcare company is in the process of deploying an innovative healthcare solution globally. The project team has completed a limited release.

The stakeholders have raised concerns about global healthcare guidelines and risks.

What should the project manager do next?

Options:

A.

Evaluate lessons learned from similar projects prior to deployment.

B.

Perform a qualitative risk analysis on the identified project risks.

C.

Review compliance and regulatory requirements with stakeholders.

D.

Conduct a feasibility analysis of deploying the solution globally.

Question 509

A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.

How should the project manager address this situation?

Options:

A.

Distribute the release plan among the team members.

B.

Ask the team members to focus only on their assignments.

C.

Ask the product owner to clarify the project's vision with the team.

D.

Meet with the product owner to validate the backlog prioritization.

Question 510

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

Options:

A.

Inform the human resource (HR) department about the issue.

B.

Allow the project team to discuss the problem with this team member.

C.

Discuss the issue with the team member's functional manager.

D.

Speak to the team member regarding the need to improve performance.

Question 511

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

Options:

A.

Project requirements, target benefits, issue log, metrics

B.

Target benefits, strategic alignment, time frame for realizing benefits

C.

Strategic alignment, benefits owner, risk register

D.

Target benefits, benefits owner, lessons learned

Question 512

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.

What should the project manager do to keep the stakeholders engaged?

Options:

A.

Use email as a communication channel.

B.

Use feedback and decision-making tools.

C.

Use meetings as a communication channel.

D.

Use a shared collaboration platform.

Question 513

A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.

How should the project manager address the issue?

Options:

A.

Create a self-paced learning plan with the team member during working hours, with checkpoints on learning progress.

B.

Review which tasks the team member would feel more motivated to work on, then assign those tasks to the team member.

C.

Replace the team member with a resource from another team who already has the requisite training and skills needed.

D.

Discuss growth and development needs with the team member and provide learning opportunities accordingly.

Question 514

A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members.

What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor and advise that the project will probably be delayed.

B.

Advise the new team that the schedule cannot be changed and encourage them to complete the project.

C.

Set up a team alignment session to discuss the remaining work and contract with the team.

D.

Ask the team to analyze the impact and develop a new schedule for a project change request.

Question 515

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

Options:

A.

Explain to the team that open discussions are needed but remind the team to follow the ground rules.

B.

Ask this member to only discuss the current topic to achieve team efficiency.

C.

Ask the team to accept the input from this particular member as their input may be useful.

D.

Allow the self-organized team to discuss the situation among themselves and come to a resolution.

Question 516

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

Options:

A.

Organize an online distribution channel from another country.

B.

Ask the sponsor to authorize the launch and then wait for approval.

C.

Ask the board to use their influence and speed up the approval.

D.

Work with the team to find ways to bypass the regulations.

Question 517

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Increase the team capacity to finish the project on time.

B.

Register an issue and escalate it to the project sponsor.

C.

Invite the stakeholders to discuss a new prioritization.

D.

Estimate the impact and consult with the product owner.

Question 518

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.

How should the project manager handle this issue?

Options:

A.

Support the project sponsor so the decision is made top-down and the team follows the provided direction.

B.

Support a voting exercise so all team members can express their opinion and the reason behind their vote.

C.

Support the product owner so only items with high business value are included in the next sprint.

D.

Support the project team so technical debt and infrastructure dependencies are included in the next sprint.

Question 519

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?

Options:

A.

Ask the technical team to revise the requirements, even if it requires extra budget.

B.

Arrange a meeting with the client to request additional time to find a new supplier.

C.

Review the existing service contracts to find an option to help procure the vehicles.

D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.

Question 520

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?

Options:

A.

Guide the team to determine alternatives.

B.

Move the dependent task to the next iteration.

C.

Escalate the issue to the company's IT manager.

D.

Escalate the issue to the project sponsor.

Question 521

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

Options:

A.

Suggest that the team member contact the IT department.

B.

Facilitate a priority resolution of the issue with the IT department.

C.

Update the issue log and escalate the problem to the product owner.

D.

Ask the other team members to step in and do the work.

Question 522

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

Options:

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Question 523

A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the

requirements. The project manager is concerned about scope creep.

Which action should the project manager take to control the scope?

Options:

A.

Ensure that all key stakeholders agree to the project deliverables and there will be no need for changes.

B.

Accept only those changes to requirements that provide additional value to the project.

C.

Reject all changes that will increase the budget or increase the time line of the project.

D.

Accept only those changes that are approved by the change control board (CCB) prior to being implemented.

Question 524

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

Options:

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Question 525

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

Options:

A.

Follow the requirements management process.

B.

Follow the stakeholder engagement process.

C.

Follow the risk management process.

D.

Follow the change management process.

Question 526

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The

project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

Options:

A.

Requirements traceability matrix

B.

Stakeholder register

C.

Stakeholder engagement assessment matrix

D.

Issue log

Question 527

A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,

Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?

Options:

A.

Perform a cost-benefit analysis to evaluate using the Point B option.

B.

Add the issue to the change log and request additional budget through the change control board (CCB).

C.

Seek a decision from the construction team after explaining the project budget and schedule constraint.

D.

Use the Point B option because it will save the project cost and time.

Question 528

A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.

What should the project manager do first?

Options:

A.

Review the project schedule and ask for the contingency reserve to crash the project.

B.

Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.

C.

Review the lessons learned register with the former project manager in a private meeting.

D.

Meet the project team to assert authority and reassign the project tasks for a timely delivery.

Question 529

A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?

Options:

A.

Determine potential threats regarding compliance with the regulations.

B.

Ask human resources (HR) to assign a compliance specialist to the team.

C.

Validate that the software is compliant with standards and regulations.

D.

Measure the extent to which the project complies with the regulations.

Question 530

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

Options:

A.

Counsel both team members and caution them with a final warning.

B.

Escalate the issue to the human resources (HR) manager before a larger problem develops.

C.

Help cultivate self-awareness between the two team members through emotional intelligence (El).

D.

Relocate the two project team members into different project teams.

Question 531

An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.

What should the team lead do next?

Options:

A.

Create all of the stories just for the next sprint and skip the epics until the next sprint.

B.

Create the epics at a high level for the requirements and begin grooming sessions.

C.

Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.

D.

Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.

Question 532

While reviewing a project with high-level executives, the project manager realizes that the conversation always deviates to other topics instead of the project itself.

What two actions should the project manager take? (Choose 2)

Options:

A.

Review with the team all of the topics that came up during the meeting.

B.

Extend the meeting time to review additional topics.

C.

Redirect the conversation to the project updates.

D.

Restrict offline reviews to critical points related to the project.

E.

Schedule effective communications training for the stakeholders.

Question 533

In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.

Which two actions should the project manager take? (Choose 2)

Options:

A.

Request the CEO to assign some of the functional team members to work on the presentation.

B.

Ask the team to work overtime to make up the time lost by supporting the technology summit.

C.

Determine a new target completion date for the project based on the redirection of the team.

D.

Divide the team to continue working on both the presentation and the project work.

E.

Attempt to complete the presentation work alone so that the timeline is not negatively impacted.

Question 534

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

Options:

A.

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.

Schedule meetings with all of the stakeholders to make business decisions when needed.

Question 535

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project

manager do to ensure business value is delivered early?

Options:

A.

Create a detailed project plan and escalate delays to the functional managers.

B.

Fast track the project and monitor tasks closely to ensure timely delivery.

C.

Create robust incentives to the team members to encourage speedy delivery.

D.

Break down the deliverables into sprints and deliver value incrementally.

Question 536

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).

What should the project manager do now?

Options:

A.

Notify the project team about the change request's approval.

B.

Include the new branch of the bridge in the design.

C.

Communicate the decision to the stakeholder who requested the change.

D.

Evaluate the adjustments to the project management plan.

Question 537

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Options:

A.

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Question 538

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

Options:

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Question 539

During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project

kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.

What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

Options:

A.

Develop a stakeholder-by-stakeholder engagement assessment matrix.

B.

Send a letter to the stakeholders to inform them about the project scope and start date.

C.

Schedule meetings with key stakeholders in advance to gather feedback on the project scope.

D.

Identify stakeholder rejection as a risk in the project risk register.

Question 540

During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.

What should the project manager do?

Options:

A.

Ensure team B prioritizes the dependent activity in iteration three.

B.

Include the dependent activity in the current iteration for team B.

C.

Assign the two critical activities to team B in iteration two.

D.

Cancel the current iteration and reschedule it with the dependent activity.

Question 541

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

Options:

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Question 542

A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.

This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of

their time to projects regardless of their complexity.

What should the project manager do as a servant leader to help achieve this transformation?

Options:

A.

Review the organizational process assets (OPAs) to evaluate mitigation plans for similar risks.

B.

Create a risk entry regarding the project manager's capacity and develop a mitigation plan.

C.

Empower the team to develop the necessary skills to move the project forward independently.

D.

Issue a change request to hire additional project managers based on the increased workload.

Question 543

A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.

What should the project manager have done to prevent this?

Options:

A.

Incorporated sufficient schedule reserves based on similar delays in past projects.

B.

Appointed a senior environmental compliance officer to report directly to the project manager.

C.

Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.

D.

Approached the regulator for a partial waiver in light of the environmental importance of the project.

Question 544

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government

official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include

aspects that the previous project sponsor did not support.

What should the project manager do next?

Options:

A.

Meet with the new project sponsor to review the current project scope and the requested changes.

B.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.

C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.

D.

Inform the new project sponsor that the new aspects will not be included in this project.

Question 545

A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.

What should the internal project manager do first?

Options:

A.

Distribute the project plan to all of the interested parties.

B.

Host an alignment session with stakeholders to formalize the project requirements.

C.

Communicate to the supplier that customer testing is required.

D.

Develop a user acceptance testing plan to ensure the quality of the deliverables.

Question 546

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

Options:

A.

Inform team B of the dependency and ensure that the deliverable is planned.

B.

Make team Aa part of team B and ensure that the deliverable is ready.

C.

Request team B to immediately start this activity and deliver to team A.

D.

Ask team B to focus on their backlog and deliver based on their priority,

Question 547

The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,

which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.

What should the project manager do first to address this situation?

Options:

A.

Evaluate the communication needs to discover the gaps and adjust the original plan if needed.

B.

Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).

C.

Review the resource breakdown structure (RBS) to request the main stakeholder's manager to replace the stakeholder.

D.

Provide evidence to the project sponsor that the project is on track and the communications have been sent.

Question 548

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?

Options:

A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.

B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.

C.

Invite the PMO manager to the daily standup with the project team and product owner.

D.

Send weekly reports to all stakeholders, including the project team and the product owner.

Question 549

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

Options:

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

Question 550

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

Options:

A.

Submit a change request and allocate the budget and resources needed for execution.

B.

Confirm that the budget and resources are available to execute the work request.

C.

Check the alternative resources available in the organization for the request.

D.

Evaluate the nature of the request and plan communication accordingly.

Question 551

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.

Delegate most authorities and control the authority by withholding important information.

B.

Delegate certain authorities and control the authority by withholding important information.

C.

Delegate certain authorities and share information to allow fair decision-making.

D.

Delegate most authorities and share information to allow fair decision-making.

Question 552

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

Options:

A.

Facilitate a supportive level of engagement for this stakeholder.

B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C.

Perform a qualitative risk analysis using a probability and impact matrix.

D.

Ensure the key information is accurate and monitor the situation as the project progresses.

Question 553

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.

Ask the team to raise blockers or impediments in daily meetings.

B.

Prioritize deliverables based on business value and define frequent releases.

C.

Ask the team to challenge the project estimations for a faster delivery.

D.

Prioritize the tasks with high risks to reduce the number of iterations required.

Question 554

A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial

department that is being delayed for a later iteration.

What should the project manager do to clarify the situation?

Options:

A.

Create an executive board to review the product backlog and replan the next iterations.

B.

Clarify with the CFO that the prioritization process is based on business value.

C.

Request support from the CEO on how to deal with the situation.

D.

Increase the size of the team in order to match any prior expectations of the CFO.

Question 555

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

Options:

A.

Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

B.

Instruct the team to make only a graphical representation of all the data for the report.

C.

Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

D.

Instruct the team to analyze and interpret the data before including it in the report.

Question 556

A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?

Options:

A.

Update the issue log and escalate the problem to the project sponsor.

B.

Ask for a project extension to deliver the committed scope.

C.

Review the options and possible solutions with the project team.

D.

Ask for help to increase the team capacity to deliver on time.

Question 557

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Question 558

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

Options:

A.

Detail the reason for the project delay in the status report.

B.

Invite the stakeholders to discuss a mitigation plan.

C.

Take on some of the necessary work to minimize the impact.

D.

Register an issue and escalate it to the project sponsor.

Question 559

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

Options:

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

Question 560

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

Options:

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Question 561

During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?

Options:

A.

Work with the product owner to ensure the product backlog is prioritized

B.

Review the project backlog during the team’s coordination meeting

C.

Encourage team members to prioritize the product backlog

D.

Ensure team members are working according to the project management plan

Question 562

A project manager is struggling to provide timely updates to the project team due to team members being spread across multiple time zones. Which communications method should the project manager utilize in this situation?

Options:

A.

Interactive communication

B.

Public communication

C.

Pull communication

D.

Push communication

Question 563

Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?

Options:

A.

Inform the product owner of the issue and request that they reprioritize the delayed task.

B.

Suggest the team member get more technical training in the next quarter.

C.

Update the risk register to reflect the possible risk of a schedule delay.

D.

Raise this issue during the daily meeting to determine a possible solution with the team.

Question 564

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

Options:

A.

Work with the product owner to assess the impact and reprioritize the product backlog.

B.

Schedule a meeting with the project sponsor to identify and allocate additional resources.

C.

Submit a formal change request and obtain approval from the change control board (CCB).

D.

Meet with the Scrum Master to determine if the development cycle can be reduced.

Question 565

A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?

Options:

A.

Improve the configuration management process

B.

Register an issue for the missing documents

C.

Ensure the lessons learned register is up to date

D.

Review the quality assurance (QA) processes

Question 566

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when project deliverables are considered complete. How should the project manager respond?

Options:

A.

At the end of each sprint, the outcome is considered ready for production

B.

The scrum master will approve the user stories that are complete

C.

Backlog items are considered complete when the product owner approves the demo

D.

Items are considered complete when they satisfy the definition of done (DoD)

Question 567

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?

Options:

A.

Assign a business analyst to build detailed requirements so the project manager can estimate the project duration

B.

Explain that the team will build a production prototype model to help the customer visualize how the features should work

C.

Add extra time and resources to the estimating phase to accommodate the lack of requirements

D.

Raise a risk that scoping and estimating will be delayed if the customer cannot approve requirements

Question 568

A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?

Options:

A.

Schedule a meeting with stakeholders and explain the situation.

B.

Discuss the situation with the sponsor and seek their guidance.

C.

Arrange a time to meet with the team to understand the parameters.

D.

Meet with the team to understand the areas of concern.

Question 569

One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?

Options:

A.

Create a change request to replace the provider with a more responsible one from the provider list

B.

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue

C.

Discuss with the sponsor and seek guidance to impose the penalty stipulated in the agreement

D.

Schedule a meeting with the provider to review impacts to the project timeline and deliverables

Question 570

A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?

Options:

A.

The interdependencies between the deliverables

B.

The business continuity plan of the deliverables

C.

The stakeholder engagement plan

D.

The user stories and story points

Question 571

During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?

Options:

A.

Use a network diagram to show that the delayed tasks are not on the critical path.

B.

Use a network diagram to show the task duration and dependencies among tasks.

C.

Use a Gantt chart to compare the actual schedule with the planned project schedule.

D.

Use a resource histogram to show that the resources are adequate to complete all tasks on time.

Question 572

A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?

Options:

A.

Report the behavior to the project sponsor and find a replacement.

B.

Note the stakeholder’s attitude as a risk and continue development according to the plan to deliver value.

C.

Consider using a predictive project management framework and report the results to the project sponsor.

D.

Address the stakeholder’s behavior directly and provide feedback.

Question 573

A project is in its fourth iteration out of eight with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable not visible in the status report. What should the project manager do?

Options:

A.

Include the deliverable in the status report and resend it to the stakeholder

B.

Invite the stakeholder to the next iteration review

C.

Invite the stakeholder to the next daily meeting

D.

Schedule a meeting with the stakeholder to review the status report

Question 574

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

Options:

A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

Question 575

Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?

Options:

A.

Crash the project with two additional contract resources for the newly identified tasks.

B.

Meet with the project stakeholders and inform them that the project is going to be delayed.

C.

Manage the schedule’s critical path, as this was an approved scheduling change.

D.

Review the project schedule and find ways to fast-track the overall project schedule.

Question 576

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

Options:

A.

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.

Use historical information to help guide the estimates that were proposed by the SMEs.

D.

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.

Question 577

In a fixed time and budget project, the customer wants development of a core component to be based on agile practices because the final scope has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact project profitability. Which two controls should the project manager incorporate into the contract to address development of the core component? (Choose 2)

Options:

A.

Establish a governance committee to review contract delivery

B.

Require that only internal resources be utilized for this project

C.

Provide alternatives to scope change at specific project phases within the contract

D.

Tier the contract for fixed and agile components

E.

Limit the number of iterations for development in the contract

Question 578

Shipping problems are impacting the supply chain worldwide, and the project's primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?

Options:

A.

Note the information but refrain from recording it as an issue because the project has not yet placed the order.

B.

Request the procurement team to find another vendor that has available stock of this equipment.

C.

Update the risk and continue to monitor developments by keeping in touch with the vendor.

D.

Request the vendor to provide specific information about the delivery delays before taking any action.

Question 579

A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?

Options:

A.

Conduct a retrospective meeting to identify what went well and what went wrong.

B.

Review the email marketing standards of that country with the stakeholders.

C.

Schedule a meeting with project team members to identify the root cause.

D.

Schedule additional country-specific user testing to reduce email opt out.

Question 580

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

Options:

A.

Assess the opportunities to deliver project value incrementally

B.

Gather all the requirements’ details and schedule a refinement meeting

C.

Prepare a project management plan for the full scope using an agile approach

D.

Approve a change request to change the project approach to agile

Question 581

A team identifies a critical set of tasks that have not been included in the Kanban board, and there is not enough budget for the work hours needed to complete the activities. What solution should the agile project manager implement?

Options:

A.

Review alternatives with the product owner and agile team.

B.

Involve stakeholders and ask them to descope some features.

C.

Ask the sponsor for additional resources to hold the schedule.

D.

Increase productivity and modify the schedule as needed.

Question 582

A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?

Options:

A.

Schedule a conference call with the project team.

B.

Schedule meetings with individual members.

C.

Send email communications to all members.

D.

Distribute the progress report and risk register.

Question 583

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

Options:

A.

Undefined change control process

B.

Unidentified project risks

C.

Improper work breakdown structure (WBS)

D.

Incomplete requirements

Question 584

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

Options:

A.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.

Escalate the issue to the sponsor and register the new risk response in the project documents

C.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.

Submit a change request to perform a different issue response than what is registered in the risk management plan

Question 585

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?

Options:

A.

Revise the project schedule with the customer

B.

Schedule a meeting with the project team to address timelines

C.

Negotiate revised timelines with the project sponsor

D.

Discuss the situation with the project team member

Question 586

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

Options:

A.

Register the risk and provide appropriate response options.

B.

Register the risk and prioritize the implementation strategy.

C.

Register the risk and escalate it to the procurement team.

D.

Register the risk and escalate it to the project sponsor.

Question 587

A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?

Options:

A.

Commit to completing the deliverables associated with only the engaged parties.

B.

Submit a change request to extend the time needed to engage all of the parties.

C.

Request that the product owner define which parties should be engaged first.

D.

Prioritize the engagement of parties who are most impacted to minimize project risk.

Question 588

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?

Options:

A.

Perform a make-or-buy analysis

B.

Review the statement of work (SOW)

C.

Leverage the enterprise environmental factors (EEFs)

D.

Refer to the organizational process assets (OPAs)

Question 589

A project to develop an enterprise resource planning (ERP) system for a university is ongoing. The system should improve business processes through digitalization and elimination of human errors, and also provide end users with simplified and easily accessible services. What should the project manager do to ensure achievement of the intended business value?

Options:

A.

Evaluate each change request and review the business case each time

B.

Evaluate deliverables against the business case continuously

C.

Evaluate deliverables against the business case at the end of the life cycle

D.

Evaluate customer feedback and review the business case each time

Question 590

Two project managers are competing to assign a key subject matter expert (SME) to their concurrently scheduled projects. Work requiring constant physical presence means the SME can serve on only one project at a time. What should the project managers do first to facilitate allocation of the resource?

Options:

A.

Calculate the schedule performance index (SPI) based on the SME assignment

B.

Assess both projects to determine the business benefits based on the SME assignment

C.

Evaluate the associated budget and schedule based on the SME assignment

D.

Determine the cost performance index (CPI) based on the SME assignment

Question 591

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?

Options:

A.

Obtained external training in QA for the new team member

B.

Delegated QA tasks to the team lead

C.

Made sure the new team member understood all requirements

D.

Ensured the new team member had access to the quality management plan

Question 592

There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?

Options:

A.

Discuss the concerns with the project sponsor

B.

Organize a team meeting to review the project status

C.

Review and update the communications management plan

D.

Escalate the concerns to the project steering committee

Question 593

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

Options:

A.

Invite all stakeholders to status meetings.

B.

Identify and categorize the stakeholders.

C.

Interact individually with the stakeholders.

D.

Recognize the diversity of the stakeholders.

Question 594

A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

Options:

A.

Plan the risk responses and assign risk response owners.

B.

Start monitoring and controlling the identified risks.

C.

Proceed with executing the risk management plan.

D.

Spend the contingency budget on the identified risks.

Question 595

A project manager is leading a complex project with stakeholders from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?

Options:

A.

Assign team members to deliverables according to their cultures and languages

B.

Ask the PMO to assign a cultural manager to oversee relations between diverse groups

C.

Perform an analysis to better understand the communication needs and preferences of each group

D.

Establish one language as the main language for communications and one official time zone for the project

Question 596

A project manager is leading a complex project. The team is being challenged with frequent, incremental, and uncontrolled changes to the project. What should the project manager do?

Options:

A.

Establish a detailed quality management plan.

B.

Establish a detailed risk management plan.

C.

Establish a detailed scope management plan.

D.

Establish a detailed schedule management plan.

Question 597

An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?

Options:

A.

Review the evidence of the quality assurance (QA) activities performed.

B.

Perform an analysis of the impact caused by the required rework.

C.

Include time in the next increment for quality assurance (QA) inspections.

D.

Confirm with the customer the expected quality in the next increment.

Question 598

A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?

Options:

A.

A decrease in the project cost

B.

An increase in the project risk

C.

Additional project scope

D.

Additional resources

Question 599

A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?

Options:

A.

Evaluate the sprint backlog

B.

Evaluate the product backlog

C.

Evaluate the sprint increment

D.

Evaluate the product development cycle

Question 600

Throughout the project, the project manager consistently checks the work performance data and finds that two stakeholders are not engaged in the project as expected. In addition, another stakeholder always complains that they are often involved in irrelevant meetings. What should the project manager do first?

Options:

A.

Communicate regularly with stakeholders and address issues.

B.

Perform a root cause analysis using the Ishikawa method.

C.

Review and update the stakeholder engagement plan.

D.

Remove those stakeholders from unwanted meetings.

Question 601

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

Options:

A.

Find another vendor to deliver the required supplies on time

B.

Ask the procurement manager to resolve the issue with the vendor

C.

Document this as a risk and define a risk response plan

D.

Treat the risk as an issue and launch the risk response plan

Question 602

A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?

Options:

A.

Discuss the issue with the product owner

B.

Discuss this with the project team in the next sprint retrospective meeting

C.

Discuss this with the project team in the next sprint planning meeting

D.

Discuss this with the PMO manager

Question 603

An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?

Options:

A.

Execute the next iteration planning considering the quality issues.

B.

Schedule quality reviews to obtain stakeholder approvals and feedback.

C.

Confirm the right quality tests are applied before moving to the next iteration.

D.

Include all the quality problems found in the technical debt backlog.

Question 604

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

Options:

A.

Escalate this issue to the project sponsor.

B.

Communicate the full details of the project activities to the stakeholder and solicit input.

C.

Analyze this stakeholder’s interest and impact.

D.

Share the summary of the project activities with the stakeholder and conclude the project.

Question 605

An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and gives regular status reports. What should the project lead do to satisfy the customer?

Options:

A.

Reduce frequent communication and improve the status report format to include team progress

B.

Schedule a meeting with the customer and explain the team is new to agile and the situation will improve

C.

Review the situation with the customer and make the required adjustments with the team

D.

Review project progress with the customer and modify the frequency of sprint review

Question 606

A project manager is leading a software development project with agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply-chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?

Options:

A.

Hired more Scrum Masters so every Scrum Master manages one supplier.

B.

Escalated the issue to the product owner to seek possible solutions.

C.

Engaged the suppliers by category and validated the strategy with stakeholders.

D.

Created user stories for the suppliers and saved their qualification records to the backlog.

Question 607

An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?

Options:

A.

Reduce the projects’ scope to meet the upcoming target dates.

B.

Crash the schedule from the delayed projects to meet upcoming target dates.

C.

Fast-track the delayed projects so they can meet upcoming target dates.

D.

Ask for project sponsor approval to revise the upcoming target dates.

Question 608

The project team has reviewed the requirements and identified some concerns. The project sponsor has asked the team how they will handle each concern. What should the project manager do next?

Options:

A.

Work with the project team to assess the severity of each risk.

B.

Collaborate with the stakeholders on the communications management plan.

C.

Consult with team members to produce a Monte Carlo simulation diagram.

D.

Develop a mitigation strategy for each risk and update the risk register.

Question 609

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?

Options:

A.

Plan the project in phases, starting with the informal sector, to deliver business value quickly

B.

Divide the project team into groups to execute as small parallel projects, including the informal sector

C.

Gather requirements and convert them into backlog items to quickly deliver value

D.

Execute the projects simultaneously following the project schedule and the communications management plan

Question 610

A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfers on this project?

Options:

A.

Require stakeholders to fully document all domain knowledge before starting

B.

Mentor the team and stakeholders to ensure domain knowledge is exchanged during sprints

C.

Ask the team to set up initial sprints for knowledge transfer before focusing on deliverables

D.

Work with QA to ensure domain knowledge is transferred properly among stakeholders

Question 611

A project manager is working on a multinational project with stakeholders from different regions. What should the project manager do first to ensure there is effective stakeholder collaboration?

Options:

A.

Review the stakeholder engagement plan with all of the stakeholders.

B.

Schedule regular virtual coordination meetings and invite all stakeholders.

C.

Request budget to invite all stakeholders to in-person team meetings.

D.

Analyze stakeholder interest levels to develop an engagement strategy.

Question 612

The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?

Options:

A.

Project milestone chart

B.

Project schedule management plan

C.

Project statement of work (SOW)

D.

Project program evaluation review technique (PERT)

Question 613

After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?

Options:

A.

Request the sponsor ask the key stakeholder to be attentive during the project review meeting

B.

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback

C.

Email the status report to all stakeholders and ask them to review and provide feedback

D.

Present the status report in a chart and assume everyone understands the report

Question 614

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed and impacts the project schedule. What should the project manager do?

Options:

A.

Work with the project team to find a compromise solution that suits both departments

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments

C.

Arrange a meeting with the two departments to understand their differences and address their needs

D.

Assess the risk of postponing this specific solution and advise both departments of the delay

Question 615

A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?

Options:

A.

Negotiate with operations to absorb the cost while the product is launched and remediate the issue.

B.

Engage with the sales team to increase the sales price since it is a breakthrough product.

C.

Evaluate the most cost-effective containment action and use their influence to implement it.

D.

Assess what corrective action is appropriate and use their influence to implement it.

Question 616

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

Options:

A.

Create a list of the tasks and send it to the project sponsor for review and approval.

B.

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.

Prepare a resource management plan that details all the resources needed to complete the tasks.

Question 617

A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?

Options:

A.

Host a team meeting and ask the team to fix any quality issues immediately since the stakeholders’ needs are the main focus.

B.

Request a subject matter expert (SME) from the project sponsor to identify and address the quality issues with the team.

C.

Facilitate a discussion and come to an agreement about what quality means for both the team and the stakeholders.

D.

Schedule a quality retrospective and discuss the challenges that resulted in poor initial quality with the team.

Question 618

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

Options:

A.

Ask the sponsor for additional financial resources

B.

Introduce a change request

C.

Use management reserves

D.

Update baselines to accommodate the delay

Question 619

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?

Options:

A.

Request the vendor to provide the servers on time as penalties may be applied

B.

Wait until the project deadline is reached in order to use contingency funds

C.

Reach out to the vendor to determine a plan to get the project back on track

D.

Review lessons learned from previous projects and take action accordingly

Question 620

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?

Options:

A.

Validate completeness of the tasks delivered in the current sprint

B.

Increase team velocity to execute tasks for the next sprints

C.

Reassign the team member to other tasks in the current sprint

D.

Encourage the team member to execute the next sprint tasks

Question 621

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

Options:

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

Question 622

During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope. How should the project manager share this information?

Options:

A.

Distribute the safety requirements during the project execution phase

B.

Modify the project charter by including the safety requirements

C.

Send an email to the team with the details of the safety requirements

D.

Meet with the team and present the scope of the safety requirements

Question 623

During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?

Options:

A.

Timebox the team members’ debate to ensure the activity is completed on time.

B.

Review expectations with all team members who are working on this activity.

C.

Discuss the issue with the team members who are delaying the activity.

D.

Ask team members to document all points that will need to be refined later.

Question 624

A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?

Options:

A.

Increase project team resources to maintain the timeline

B.

Conduct simulations to determine the best way forward to ensure timely delivery

C.

Reduce scope to deliver on time

D.

Work with the team to ensure the project is delivered on time

Question 625

A project manager presents the project schedule to the customer, including the detailed phases for the whole project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?

Options:

A.

Adjust the project schedule to include additional resources for all project tasks.

B.

Submit a change request to extend the project timeline.

C.

Evaluate the impact of changing the project framework to an incremental approach.

D.

Apply crashing techniques to all activities in the project schedule.

Question 626

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

Options:

A.

Execute a qualitative analysis to provide identified risks prioritization.

B.

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.

Inform that a qualitative analysis has already been completed.

D.

Perform a quantitative analysis to provide identified risks prioritization.

Question 627

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

Options:

A.

Review the list of stakeholders that will be affected by starting this business initiative.

B.

Continue with the project the way it was planned and validated by the sponsor.

C.

Describe the outcome of the project and business value to all company stakeholders.

D.

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.

Modify the project management plan and scope of work to avoid future difficulties.

Question 628

It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?

Options:

A.

Address the required changes in the next release

B.

Review and update the acceptance criteria

C.

Put more emphasis on the definition of done (DoD)

D.

Extend the iterations to complete the items

Question 629

During project implementation, a critical performance issue is identified by team members. What should the project manager do?

Options:

A.

Submit a change request to handle the performance issue

B.

Review the tender requirements related to the performance issue

C.

Pass the performance issue to subject matter experts (SMEs) to handle

D.

Work with the project stakeholders to address the performance issue

Question 630

An organization is about to start a time-critical project and has decided to use an agile approach for the first time. However, stakeholders are worried they will not be able to verify project status because they believe their usual governance model will not work for an agile project. What should the project manager do?

Options:

A.

Discuss using a hybrid governance structure with stakeholders

B.

Meet with stakeholders to discuss and review the governance structure

C.

Recommend following the existing governance structure with the project team

D.

Review the governance structure to reflect scope changes

Question 631

A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?

Options:

A.

Remove the current backlog item from the sprint and replace it with defect fixing

B.

Remove the current backlog item from the sprint and replace it with a similar item

C.

Update the backlog and advise the team to add this to the acceptance criteria

D.

Update the product backlog and include the change as a high priority for the next iteration

Question 632

A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?

Options:

A.

Add more resources to complete the remaining deliverables early.

B.

Review and analyze the risks associated with compressing the schedule.

C.

Prioritize critical activities and skip noncritical activities.

D.

Perform several activities in parallel to compress the schedule.

Question 633

A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization requested their assignment. What should the project manager do?

Options:

A.

Emphasize to the executives that the project manager was specifically requested for this project

B.

Schedule deliverables solely based on priorities and must-have-by dates, and gauge responses

C.

Hold a team meeting emphasizing existing governance policies and procedures

D.

Adopt a project framework aligned to the executives’ availabilities and then evaluate the risks

Question 634

A project manager is presented with a roadmap that excludes most of their recommendations. The content source of the roadmap is an influential stakeholder who disagrees with the use of specific procedures and practices. The project sponsor deems the roadmap acceptable. Which two actions should the project manager take first? (Choose 2)

Options:

A.

Align the roadmap within the project framework and perform a risk analysis.

B.

Align deliverables based on the roadmap and documented results.

C.

Request to have the roadmap reviewed by the project management office (PMO).

D.

Request reassignment to another project to avoid conflict with the stakeholder.

E.

Discuss the reasoning behind the roadmap with the stakeholder.

Question 635

Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?

Options:

A.

Begin daily check-ins with the two vendors to recover time at their own expense

B.

Extend the project schedule and inform the vendors it was due to their poor performance

C.

Find replacements for the two vendors to complete the project in a timely manner

D.

Reduce the two vendors’ pay due to poor performance and lack of communication

Question 636

A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?

Options:

A.

Asked the customer to participate in project status meetings to better understand the progress

B.

Informed the project team to closely monitor the deliverables and keep the customer informed

C.

Reviewed benefits realization with the customer regularly and constantly aligned expectations

D.

Explained to the customer that the project is in good shape as the system is operational

Question 637

A project to develop a new service is initiated by a telecommunications operator. The project management plan was developed, approved, and shared with respective stakeholders. What should the project manager do next?

Options:

A.

Define deliverables, activities, and scheduling information.

B.

Estimate activity durations and list resource requirements.

C.

Incorporate the project's scope baseline in the scope statement.

D.

Start execution of the work packages according to the plan.

Question 638

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

Options:

A.

Remove those stakeholders from the project since they may negatively affect project goals

B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.

Schedule a meeting with relevant stakeholders to review the project communications plan

D.

Explain to the stakeholders that they must request project updates from the project sponsor

Question 639

A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved and developers have started work on the final application. What should the project manager do next?

Options:

A.

Be firm with the stakeholder, since they would push through any unreasonable requirement

B.

Document the stakeholder's requirements and validate those requirements by engaging stakeholders more often

C.

Inform the stakeholder that little can be done at this time, since core development has begun and the project must be delivered on time

D.

Inform the stakeholder that the requirement will be included in the next deliverable cycle

Question 640

A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?

Options:

A.

Evaluate the new proposal with the project team to determine if it is a more beneficial alternative

B.

Adhere to the issue response in the risk management plan as it is the agreed-on solution

C.

Implement the new proposal as soon as possible since it is cheaper and equally effective

D.

Ask the team member to write a formal email explaining the proposal and send it to the change control board (CCB)

Page: 1 / 219
Total 2191 questions