Question 1

Which is the BEST method of communication to gather feedback?

Options:

A.

Receiving emailed diagrams to encourage discussion

B.

Conducting online surveys to obtain a range of opinions

C.

Meeting face-to-face to encourage an exchange of views

D.

Discussing over the telephone to gather feedback quickly from stakeholders

Question 2

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

Options:

A.

To use empiricism, based on knowledge that comes from experience

B.

To build, measure, learn from your experiences

C.

To create a minimum viable product to manage uncertainty

D.

To fail fast, if you are going to fail

Question 3

What information is NOT typically displayed on a burn chart?

Options:

A.

Effort remaining

B.

Team working agreements

C.

Actual amount of work done

D.

Amount of time elapsed

Question 4

Which statement about quality tolerances for a product is CORRECT in an agile context?

Options:

A.

All quality criteria tolerance must be fixed

B.

Quality tolerances should be the same for all quality criteria

C.

Setting quality tolerance relies on prioritising quality criteria

D.

All quality criteria should have zero tolerance

Question 5

Which is an advantage of frequent releases?

Options:

A.

Releases can be used to replace management stages

B.

A ‘one-team’ culture in the project team is encouraged

C.

Configuration management becomes less important

D.

The delivery team becomes more experienced at product handover

Question 6

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It re-establishes team dynamics when a new member joins the team

B.

It trades user stories for those of a similar size

C.

It results in the late delivery of the minimum viable product

D.

It degrades the performance of the features that are delivered

Question 7

What is the MOST LIKELY benefit from frequent releases into operational use?

Options:

A.

Feedback is obtained from real customers

B.

The need for customer involvement is increased

C.

The risks associated with agile ways of working are assessed

D.

The need for configuration management is reduced

Question 8

Which is a benefit of the Lean Startup approach to releasing a product?

Options:

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

Question 9

How does the change theme regard change in PRINCE2 Agile?

Options:

A.

As disruptive

B.

As something to be avoided

C.

As a necessity

D.

As inevitable

Question 10

Which is a purpose of the plans theme?

Options:

A.

To identify any deviations from the project’s objectives

B.

To control any approved changes to the baseline

C.

To monitor actual achievements against those planned

D.

To communicate the approach for delivering products

Question 11

Which statement about an epic is CORRECT?

Options:

A.

It can be broken down into user stories

B.

Its purpose is to document technical requirements

C.

It should appear at the top of a product backlog

D.

It contains sufficient granularity to allow work to start

Question 12

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.

2. They are partially assigned to the delivery team.

3. They create the project's specialist products.

4. They prioritize requirements.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 13

How is the ‘tailor to suit the project’ principle applied in an agile context?

Options:

A.

By flexing what is produced to stay in control and deliver value

B.

By emphasizing tolerances on what is being delivered

C.

By using the Agilometer to assess the project environment

D.

By fitting releases into planned management stages

Page: 1 / 9
Total 92 questions