Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dumps65

SAP C_S4PPM_2021 Dumps

SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Questions and Answers

Question 1

When you create an item from an initiative, which of the following objects are authorizations inherited from?

NOTE: There are 3 correct answers to this question

Options:

A.

Portfolio

B.

Parent bucket

C.

Project management project

D.

Project system project

E.

initiative

Question 2

What must you do before you can use multiple currencies in financial planning in portfolio management?

Options:

A.

Select multiple currencies in the portfolio definition

B.

Define a subnet of currencies in portfolio and project management

C.

Select multiple currencies in the portfolio item

D.

Define a subnet of currencies in project system

Question 3

In a existing project management project, all objects have been released and all subordinate tasks for the checklist items have been completed.

Why does the status change fail when you try to set the status of the checklist to Finish?

How can you trigger a workflow for a portfolio item?

Options:

A.

A checklist item is still open

B.

You are missing the authorization for changing the project

C.

At least of the tasks has been configured

D.

The checklist item result is set to not ok

Question 4

How do you make a decision point field a required field for a specific portfolio item?

Options:

A.

Make the filed a required field for the decision point and assign the item type to the portfolio In customizing

B.

Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type

C.

Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type

D.

Make the field a require field for the combination of decision point and portfolio type in customizing for the item type

Question 5

How are groups linked to categories in capacity planning?

Options:

A.

A group is directly linked to one category

B.

A group is directly linked to multiple category

C.

A group is linked to multiple categories via view

D.

A group is linked to one category via view

Question 6

What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?

NOTE: There are 3 correct answers to this question.

Options:

A.

Accounting integration for this project is active

B.

The project type must allow time recording with the CATS

C.

The role type must allow time recording with CATS

D.

The planned efforts is on the task

Question 7

Which system behavior are enabled when a create a project with multiple phase?

NOTE: There are 2 correct answers to this question.

Options:

A.

Determination of the start-dates of subsequent phases

B.

Rollup of activity cost allocations to phases

C.

Rollup of resource requirements of tasks to phases

D.

Determination of the start- and end-dates of tasks

Question 8

Decision Flow management is delivered with standard scenarios.

For which combination of object types can you define a standard attitude synchronization?

Options:

A.

Decision point and PS project definition

B.

Portfolio item and WBS element

C.

Decision point and activity milestone

D.

Decision point and WBS element

Question 9

What is a prerequisite for using role charts in project management?

Options:

A.

The demand of a role must have been updated according to tasks

B.

A graphic profile is assigned to the role type

C.

A graphic profile is assigned to the project type

D.

The demand of a role must be distributed over a number of periods

Question 10

When you confirm a task, you wants the system to calculate the difference between planned work and actual work.

What must you do?

Options:

A.

Set the task status to in process

B.

Confirm the task using a completion percentage of less than 100

C.

Ensure that the Rem. Work manually indicator is inactive

D.

Enter an actual finish date of the task in the future

Question 11

You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.

How do you make this selection available?

Options:

A.

Run a report to enable the consultant role type

B.

Assign the consultant role type to the appropriate project type

C.

Activate the consultant role type

D.

Assign the consultant role type to the appropriate item type

Question 12

How can you trigger a workflow for a portfolio item?

NOTE: There are 2 correct answers to this question.

Options:

A.

Exceed the budget of the item

B.

Choose the start workflow button

C.

Change the master data of the item

D.

Change the item status

Page: 1 / 8
Total 82 questions