Black Friday Biggest Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

SAP C_TS422_2022 Dumps

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?

Options:

A.

The new operation is inserted at the desired time; the previous dispatched operation is moved forward.

B.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward

C.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

D.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

Question 2

What is the purpose of a reporting point confirmation in repetitive manufacturing?

Note: There are 2 Correct answers to this question?

Options:

A.

To determine the work in progress along the production line

B.

To provide timely updates of inventory management for the staged components

C.

To reduce the total production lead time for a long production line

D.

To stage different components for a production line simultaneously

Question 3

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

Note: There are 2 correct answers to this question.

Options:

A.

Use the Batch Information Cockpit.

B.

Use batch derivation.

C.

Use batch determination

D.

Use the batch where-used list.

Question 4

You are trying to create a production order and NO valid production version can be selected. What could be the reasons?

Note: There are 2 correct answers to this question.

Options:

A.

NO bills of material (BOMs) are assigned to the production versions.

B.

All production versions for the material are locked.

C.

The order lot size is NOT within the validity range of a production version.

D.

NO production lines are assigned to the production versions..

Question 5

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Question 6

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

Options:

A.

Planning with final assembly (40)

B.

Production by lot size (30)

C.

Planning at assembly level (70)

D.

Make-to-order production (20)

Question 7

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

Options:

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Question 8

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Move Time

B.

Pick/pack time

C.

Setup time

D.

Float before production

E.

Queue time

Question 9

How can you set up the supply source for the Kanban process in SAP S/4HANA?

Note: There are 3 correct answers to this question.

Options:

A.

Use stock transfer reservations for stock transfer.

B.

Use purchase orders for external procurement.

C.

Use quotations for internal and external procurement

D.

Use run schedule quantities for in-house production.

E.

Use purchasing costs for automated source prioritization.

Question 10

You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?

Options:

A.

Specify a negative planning horizon.

B.

Specify a positive planning horizon.

C.

Specify a positive offset time.

D.

Specify a negative offset time.

Question 11

Which master data object governs the relationship between supply source and demand source in the Kanban process?

Options:

A.

Replenishment strategy

B.

Production supply area

C.

Control cycle

D.

Rate routing

Question 12

What are the options if the Dispatched operation status is set for a production order operation?

Note: There are 2 correct answers to this question.

Options:

A.

You can reschedule the operation using finite scheduling in a planning table.

B.

You can reschedule the operation in the Manage Production Operations app.

C.

You can reschedule the operation using infinite scheduling in a planning table

D.

You can reschedule the operation using midpoint scheduling in a planning table.

Question 13

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?

Note: There are 2 correct answers to this question.

Options:

A.

Work Center

B.

Production Version

C.

Material

D.

plant

Question 14

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

Options:

A.

Queue

B.

Teardown time

C.

Move time

D.

Setup Time

Question 15

You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?

Options:

A.

Insert operation

B.

Squeeze in

C.

Schedule in working time only

D.

Find Slot

Question 16

For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?

Note: There are 2 correct answers to this question.

Options:

A.

In pro duct-related COC, all costs are debited and credited to a product cost collector.

B.

Order-related COC is beneficial in a flexible production environment

C.

Product-related COC is used in manufacturing for co-products

D.

In order-related COC, individual production orders do NOT have cost segments.

Question 17

For a production version to be valid and consistent, what requirements must be fulfilled? Note:There are 3 correct answers to this question.

Options:

A.

The deletion flag must NOT be set for the bill of material (BOM) or the routing

B.

The lot size range must be within the lot size range of the assigned routing.

C.

The assigned routing and bill of material (BOM) must be valid in the entirevalidity period.

D.

The assigned routing must be a rate routing.

E.

The assigned routing must NOT have alternative sequences

Question 18

What does forecasting in the demand planning cycle include?

Note: There are 3 correct answers to this question

Options:

A.

One-off events

B.

Past quotation quantities

C.

Past sales order quantities

D.

Market intelligence

E.

Past production planning quantities

Question 19

which SAP application can be used for forecasting in Supply Chain Planning?

Note: there are 2 correct answers to this question.

Options:

A.

Integration Business Planning (IBP)

B.

Capacity Requirement Planning (CRP)

C.

Supply Chain Management (SCM)

D.

Material Requirement Planning (MRP)

Question 20

You want to set up a make-to-order planning scenario for a finished material. The bill of materialcontains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

Options:

A.

Choose planning strategy 50 (Planning without final assembly) and select the — corresponding Individual/Collective indicator.

B.

Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator.

C.

Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator.

D.

Choose planning strategy 20 (Make-to-Order) and select the corresponding ndividual/Collectiveindicator.

Question 21

How would you define pegging in the context of Advanced Planning?

Options:

A.

An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements

B.

An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements

C.

An evaluation to verify if there are material or capacity shortages in the ^ network after the production planning run

D.

An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run

Question 22

What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?

Note: There are 2 correct answers to this question.

Options:

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities

C.

The Change Planning Direction indicator is set in the strategy profile

D.

Alternative work centers are fully occupied.

Question 23

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

Options:

A.

To increase the number of planning levels

B.

To simplify the structure of bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To reduce the number of changes required in bills of material

Question 24

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA.

Note: there are 2 correct answers to this question.

Options:

A.

Manual maintenance

B.

100% check

C.

First in First out (FIFO).

D.

Simultaneous

Page: 1 / 8
Total 80 questions