SAP C_TS422_2023 Dumps

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Question 1

Where does the system check master data selection settings during the creation of planned orders production orders? Note: There are 3 correct answers to this question.

Options:

A.

In the production version

B.

In the work centers

C.

In the bill of material (BOM)

D.

In the MRP controller

E.

In the routing

Question 2

Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

In which storage location is the BOM required?

B.

Is the material type allowed in the BOM?

C.

Which base unit of measure does the material have?

D.

What status does the BOM have?

Question 3

Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.

Options:

A.

You can use trigger points to automatically create rework orders via confirmations.

B.

You can use mass processing to set production orders to technically complete.

C.

You can use the production scheduling profile to automatically set orders to technically complete.

D.

You can use mass processing to read PP master data for production orders.

Question 4

Your company manufactures materials whose characteristics differ for each manufacturing process.

Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?

Options:

A.

Process order management

B.

Engineering change management

C.

Quality management

D.

Batch management

Question 5

What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?

Options:

A.

MRP creates a dependent requirement.

B.

A sales order is delivered.

C.

MRP creates a planned order.

D.

A sales order is created.

Question 6

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.

Options:

A.

Queue time

B.

Teardown time

C.

Move time

D.

Setup time

Question 7

In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

Options:

A.

Use a specific MRP list.

B.

Use a specific material status.

C.

Use a specific material group.

D.

Use a specific MRP type.

Question 8

How would you define pegging in the context of Advanced Planning?

Options:

A.

An evaluation that is ordered according to the billofmaterial structure of all related products represents the relationship between the receipt the issue elements

B.

An evaluation to identify overstock situations in the balance between the receipt the issue elements after the production planning run

C.

An evaluation that is ordered according to the network structure of all related products represents the coverage of issue elements with receipt elements stock

D.

An evaluation to identify material or capacity shortages in the billofmaterial structure after the production planning run

Question 9

Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

Base unit of measure

B.

Industry sector

C.

Selection screen for views

D.

Product type

Question 10

Under what circumstances can you change the material type for a material if stocks reservations or purchasing documents exist? Note: There are 2 correct answers to this question.

Options:

A.

The quantity value updates are the same.

B.

The same batch management level is used.

C.

The same base unit of measure is used.

D.

The same account category is used.

Question 11

You are a consultant on an SAP S/4HANA Cloud brownfield project. In a meeting the customer decides to remodel an existing business process in accordance with clean core principles.

Which of the following SAP Signavio solutions can be used for the remodeling?

Options:

A.

SAP Signavio Process Insights

B.

SAP Signavio Process Intelligence

C.

SAP Signavio Process Governance

D.

SAP Signavio Process Manager

Question 12

Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Assign planned orders manually in the planning table.

B.

Run MRP with quota arrangement.

C.

Run MRP with automatic selection of production version.

D.

Run PP/DS heuristics for repetitive manufacturing.

Question 13

What does the material type influence?

Note: There are 2 correct answers to this question.

Options:

A.

Which document types class categories are allowed

B.

Which plantspecific plantindependent statuses are allowed

C.

Which material master screens appear in which sequence

D.

Whether the material is produced inhouse procured externally or both

Question 14

What determines whether the planned independent requirements in dem management are consumed by other requirements? Note: There are 2 correct answers to this question.

Options:

A.

Order type

B.

Requirements profile

C.

Requirements type

D.

Planning strategy

Question 15

Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.

Which planning strategy do you use?

Options:

A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

C.

Planning without final assembly (50)

D.

Maketostock production (10)

Question 16

How can you set up the supply source for the Kanban process in SAP S/4HANA Cloud Private Edition? Note: There are 3 correct answers to this question.

Options:

A.

Use run schedule quantities for inhouse production.

B.

Use stock transfer reservations for stock transfer.

C.

Use purchase orders for external procurement.

D.

Use quotations for internal external procurement.

E.

Use purchasing costs for automated source prioritization.

Question 17

How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.

Options:

A.

Select a special procurement type inside the material master.

B.

Use a special item category in your material BOM (bill of material).

C.

Select a special MRP type inside the material master.

D.

Define the special procurement type inside the material BOM (bill of material).

Question 18

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with an alternative sequence in the routing

C.

A production line with a parallel sequence in the routing

D.

A production line with prioritized alternative work centers

Question 19

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?

Note: There are 2 correct answers to this question.

Options:

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Orders (dispatched) chart

D.

Work center capacities chart

Question 20

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

Options:

A.

Execute an infinite production planning run for the critical resources.

B.

Reduce the planning time interval.

C.

Determine a time period with available capacity on the planning board.

D.

Increase the capacity supply in a timephased interval.

E.

Form optimum sequences to reduce setup times.

Question 21

Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?

Note: There are 2 correct answers to this question.

Options:

A.

Use batch determination.

B.

Use the Batch Information Cockpit.

C.

Use the batch whereused list.

D.

Use batch derivation.

Question 22

Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

Options:

A.

Net requirements calculation is carried out for every sales order individually.

B.

Production orders are created with sales order reference.

C.

Storage location MRP areas are required for salesorderspecific stock.

D.

Both the reduction of maketoorder stock requirements occur on delivery.

E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

Question 23

You want to reduce planning efforts for B C classified materials. Which planning procedure do you recommend?

Options:

A.

Consumption Based Planning

B.

Subassembly Planning

C.

Advanced Planning

D.

Material Requirements Planning

Question 24

For production orders cost object controlling (COC) can be carried out on an order related or product related basis. Which of the following do you have to consider?

Note: There are 2 correct answers to this question.

Options:

A.

Productrelated COC is used in manufacturing for coproducts.

B.

In productrelated COC all costs are debited credited to a product cost collector.

C.

In orderrelated COC individual production orders do NOT have cost segments.

D.

Orderrelated COC is beneficial in a flexible production environment.

Page: 1 / 8
Total 80 questions