SAP Certified Specialist - Project Manager - SAP Activate for Agile Implementation Management Questions and Answers

Question 1

What is the result of fit-to-standard workshops?

Options:

A.

Detailed assessment of customer's current business processes

B.

Preparation of standard test cases and test scripts for end users

C.

Prioritization of the requirements backlog by the team

D.

Confirmation solution fit and identification of delta requirements

Question 2

Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?

Options:

A.

Scope and duration of testing is finalized.

B.

Durations of all sprints for the full release defined based on planned complexity.

C.

User Stories are in Ready state for only the first 2 to 3 sprints.

D.

Project scope and planning are completed and final.

Question 3

Which techniques should the SAP Activate practitioner follow? Note: There are 3 correct ans-wers to this que-stion.

Options:

A.

Optimize testing by running it only at the end of Realize phase

B.

Apply the fit-to-standard first mindset

C.

Reduce business user involvement for efficiency

D.

Leverage dynamic extensibility and integrations

E.

Use agile approach throughout the project

Question 4

Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?

Options:

A.

Leveraging effort estimates for similar User Stories from another Scrum team

B.

Detailed bottom-up estimates that break each User Story into shorter tasks

C.

Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team

D.

Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days

Question 5

Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct ans-wers to this que-stion.

Options:

A.

Backlog Template

B.

Test Strategy

C.

Quality Gate Checklist

D.

Business Process Design Template

Question 6

In which phase do you create "an ordered list of everything that is known to be needed in the product"?

Options:

A.

Prepare

B.

Discover

C.

Realize

D.

Explore

Question 7

What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct ans-wers to this que-stion.

Options:

A.

Sprint duration between 1 week to 4 weeks.

B.

Adjust sprint duration based on team availability.

C.

Set variable sprint duration based on work.

D.

Establish fixed duration of each sprint.

Question 8

Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct ans-wers to this que-stion.

Options:

A.

Detailed Design - Business Process

B.

End User Learning Needs Analysis

C.

Learning Content

D.

Change Management Roadmap

E.

Project Plan

Question 9

What are the capabilities of Task Management application in SAP Cloud ALM with SAP Activate methodology tasks? Note: There are 3 correct ans-wers to this que-stion.

Options:

A.

Change description of SAP Activate task

B.

Launch SAP Cloud ALM apps to perform SAP Activate task

C.

Create sub-tasks to break down the SAP Activate task

D.

Delete SAP delivered SAP Activate tasks

E.

Assign SAP Activate task to a team member

Question 10

What is the objective of a Sprint Retrospective meeting?

Options:

A.

Prioritize the remaining backlog items.

B.

Provide feedback to the project sponsor.

C.

Prepare for Quality Gate.

D.

Improve the team's process.

Question 11

Which artifacts in the Testing workstream are created within the Realize phase? Note: There are 2 correct ans-wers to this que-stion.

Options:

A.

User Acceptance Test - Plan

B.

Test Strategy

C.

Functional Specifications

D.

Functional Test Scenarios

Question 12

When does the product owner accept or reject the user stories included in the Sprint?

Options:

A.

During the Sprint Review

B.

During the Quality Gate

C.

During the daily Scrum meeting

D.

During the user acceptance test

Page: 1 / 4
Total 40 questions