Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dumps65

Scrum PSK-I Dumps

Page: 1 / 7
Total 73 questions

Professional Scrum with Kanban (PSK 1) Exam Questions and Answers

Question 1

What is the potential benefit of limiting Work in Progress (WIP)?

(choose the best answer)

Options:

A.

Shorter feedback cycles.

B.

More sustainable pace of work.

C.

Faster realization of value.

D.

Improved collaboration.

E.

All of the answers.

Question 2

When is the most appropriate time for Scrum Teams practicing professional Scrum with

Kanban to inspect and adapt their Work in Progress (WIP) Limits?

(choose the best answer)

Options:

A.

Anytime the Developers see fit.

B.

Never. Once set, WIP Limits cannot be modified.

C.

Every day during Daily Scrum.

D.

During the Sprint Retrospective.

Question 3

True or False: The Definition of Done still applies even if policies are explicitly stated at each

column of your Workflow.

Options:

A.

True

B.

False

Question 4

Which of the following is NOT an essential component to initially achieving flow?

(choose the best answer)

Options:

A.

Ensuring the Product Backlog is refined frequently.

B.

Limiting Work in Progress (WIP).

C.

Visualizing your Workflow.

D.

Actively managing WIP.

E.

Inspecting & adapting your Workflow.

Question 5

Which of these statements about Sprints and Kanban is NOT correct?

(choose the best answer)

Options:

A.

The Sprint is an example of a cadence.

B.

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

C.

The Sprint is an example of limiting Work in Progress (WIP).

D.

The Sprint is an example of an explicit policy for how a team is working.

Question 6

A service level expectation (SLE) consists of which two items?

(choose the best two answers)

Options:

A.

A cost of delay.

B.

A probability.

C.

A forecasted date.

D.

A period of elapsed days.

Question 7

True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull

system.

Options:

A.

True

B.

False

Question 8

When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?

Options:

A.

Definition of Done.

B.

Definition of Ready.

C.

Product Backlog refinement.

D.

All of the above.

Question 9

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to observe?

(Choose the best three answers)

Options:

A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Increased collaboration/swarming between the Developers.

D.

Self-management would be strengthened as a result of increased transparency.

Question 10

What might be considered during the Sprint Retrospective once a team decides to supplement

their Scrum with Kanban?

(choose the best answer)

Options:

A.

Workflow.

B.

Current policies.

C.

WIP Limit.

D.

Metrics and charts such as Cumulative Flow Diagram, Cycle Time Scatterplot, and

Work Item Aging.

E.

All of the answers.

Question 11

Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?

(choose the best two answers)

Options:

A.

Work Item Age.

B.

Work in Progress (WIP).

C.

Process control chart and Scrum Team's 85th percentile.

D.

Lead Time.

E.

Throughput.

F.

Cycle Time.

G.

Velocity.

Question 12

Which of the following statements about supplementing Scrum with Kanban practices is true?

(choose the best answer)

Options:

A.

Scrum Teams may choose to skip the Sprint Planning event.

B.

It encourages team collaboration/swarming.

C.

It applies primarily to maintenance type of work.

D.

It implies that the Scrum Team must have a sequential approach to work.

Question 13

In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?

Options:

A.

When they want to improve their Cycle Time, flow, and focus.

B.

When there is unplanned urgent work that emerges during the Sprint.

C.

When they see that the average story size they are working on is growing.

D.

When they have extra capacity during the Sprint and want to start some new work items from the Sprint Backlog.

Question 14

Which of the following are lagging indicator metrics?

(choose the best three answers)

Options:

A.

Velocity.

B.

Cycle Time.

C.

Work in Progress.

D.

Throughput.

E.

Work Item Aging.

Question 15

True or False: If you reduce your batch size, your overall efficiency will always increase.

Options:

A.

True

B.

False

Question 16

A Service Level Expectation (SLE) consists of which two items?

(Choose the best two answers)

Options:

A.

A period of elapsed days.

B.

A cost of delay.

C.

A probability.

D.

A forecasted date.

Question 17

True or False: The Scrum framework already contains elements that create a pull system.

Options:

A.

True

B.

False

Question 18

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)

Options:

A.

Cycle Time scatterplot.

B.

Cumulative Flow diagram (CFD).

C.

Throughput run chart.

D.

WIP Aging chart.

Question 19

True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. They can instead create one “on-demand” as new work flows into the Sprint Backlog.

Options:

A.

True

B.

False

Question 20

What should the Developers do if, during the Sprint, the Product Owner asks them to add an

urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work

in Progress (WIP) Limits?

(choose the two best answers)

Options:

A.

Add the urgent item to their Sprint Backlog but only start working on it when their

WIP Limits allow it.

B.

Adjust the WIP Limits to allow for taking on the extra item and record it as part of

their Definition of Workflow.

C.

Take on the urgent item as an exception to the WIP Limits and visualize that

they are above their WIP Limit.

D.

Reject the urgent item since the WIP Limits do not allow it. Tell the Product

Owner to wait until the next Sprint.

Question 21

What might a Scrum Team visualize with Kanban?

(choose the best three answers)

Options:

A.

The Product Backlog.

B.

The Sprint Retrospective.

C.

The Sprint Backlog.

D.

The Definition of Done.

Page: 1 / 7
Total 73 questions