Black Friday Biggest Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

Scrum PSPO-I Dumps

Page: 1 / 18
Total 177 questions

Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Question 1

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder

just started using the product. The stakeholder is unhappy with the quality of the product. What

are two good options for the Scrum Master?

(choose the best two answers)

Options:

A.

Coach the Product Owner on how to talk with the Developers about this

concern.

B.

Wait to bring this up until the Sprint Retrospective.

C.

Explain to the Product Owner that it is up to the Developers to decide on

acceptable quality standards.

D.

Encourage the Product Owner to put quality specifications on the Product

Backlog and express the stakeholder's concern to the Developers.

E.

Bring the concern to the testers to improve how the Product is verified.

Question 2

What are the two responsibilities of testers in a Scrum Team?

(choose the best two answers)

Options:

A.

Tracking quality metrics.

B.

Scrum has no "tester" role.

C.

Verifying the work of programmers.

D.

The Developers are responsible for quality.

E.

Finding bugs.

Question 3

When must the Product Owner participate in the Daily Scrum?

(choose the best answer)

Options:

A.

When the Scrum Master asks the Product Owner to attend.

B.

When the Product Owner is actively working on items on the Sprint Backlog;

however, they participate as a Developer.

C.

When there are impediments to discuss.

D.

When the Product Owner needs to represent the stakeholders' point of view to the

Developers.

Question 4

True or False: The purpose of a Sprint is to produce a valuable, useful Increment.

Options:

A.

True

B.

False

Question 5

The Daily Scrum is an event that happens every day. What would be three key concerns if the

frequency were to be lowered to every two or three days?

(choose the best three answers)

Options:

A.

The Sprint Backlog may become inaccurate.

B.

Too much work is spent updating the Scrum board before the meeting.

C.

The Scrum Master loses the ability to update the Gantt chart properly.

D.

The Product Owner cannot accurately report progress to the stakeholders.

E.

Opportunities to inspect and adapt the Sprint Backlog are lost.

F.

Impediments are raised and resolved more slowly.

Question 6

Which of the following are criteria to order Product Backlog items?

(choose the best three answers)

Options:

A.

The value of the Product Backlog items.

B.

The availability of the Scrum Master.

C.

Dependencies between Product Backlog items.

D.

Their relevance to achieving the Product Goal.

E.

The number of stakeholders who approve of the item.

Question 7

What is the purpose of a Sprint Review?

(choose the best answer)

Options:

A.

To build team spirit.

B.

To take time to judge the validity of the project.

C.

To inspect the product Increment with the stakeholders and collect feedback on next steps.

D.

To review the Scrum Team's activities and processes during the Sprint.

Question 8

What is the timebox for the Sprint Review?

(choose the best answer)

Options:

A.

2 hours for a one-month Sprint.

B.

1 day.

C.

4 hours for a one-month Sprint.

D.

As long as needed.

Question 9

When might a Sprint be cancelled?

(choose the best answer)

Options:

A.

When the Developers determine the product plan is infeasible.

B.

When it becomes clear that not everything will be finished by the end of the Sprint.

C.

When the sales department has an important new opportunity.

D.

When the Sprint Goal becomes obsolete.

Question 10

In order to maximize the value of the product, a Product Owner needs awareness of the following: (choose the best answer)

Options:

A.

Competitive research.

B.

Customer feedback.

C.

Product vision.

D.

Forecasting & feasibility.

E.

All of the above.

F.

None of the above.

Question 11

What three things might a Scrum Product Owner focus on to ensure the product delivers value?

(choose the best three answers)

Options:

A.

How much of the functionality of the product is being used.

B.

Direct customer feedback.

C.

How quickly or easily the product can be absorbed and used by its customers.

D.

Velocity is increasing over time.

E.

Minimizing changes to project scope.

Question 12

The length of a Sprint should be:

(choose the best answer)

Options:

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of the above.

Question 13

Why is the Daily Scrum held at the same time and same place?

(choose the best answer)

Options:

A.

The Product Owner demands it.

B.

Rooms are hard to book and must be booked in advance.

C.

The place can be named.

D.

The consistency reduces complexity.

Question 14

Which outcome is expected as a Scrum Team matures?

(choose the best answer)

Options:

A.

The Sprint Retrospectives will grow to be longer than 4 hours.

B.

They will improve their Definition of Done to include more stringent criteria.

C.

A Scrum Master is no longer needed since they are a mature team now.

D.

There will be no need for a timeboxed Sprint.

E.

Sprint Reviews will no longer be needed.

Question 15

A Scrum Team is a cohesive unit of professionals that consists of which of the following?

(choose the best three answers)

Options:

A.

One Product Owner.

B.

Developers.

C.

Customers.

D.

One Scrum Master.

E.

Users.

Question 16

A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?

(choose the best two answers)

Options:

A.

Promote transparency by sharing the Product Backlog and ensuring the Project

Manager has access.

B.

Have a discussion with the Project Manager; share the current impediments and

forecast for the Sprint.

C.

Show the Earned Value Analysis (EVA) report.

D.

Scrum does not have Project Managers so disregard their concerns.

E.

Share the last stakeholder briefing document prepared by the Product Owner.

Question 17

Why is it important that there is only one Product Owner per product?

(choose the best three answers)

Options:

A.

The Scrum Master knows who acts as their backup while on vacation.

B.

It would confuse the stakeholders if they had to work with more than one person.

C.

It is clear who is accountable for the ultimate value of the product.

D.

It helps avoid barriers to effective communication and rapid decision-making.

E.

The Scrum Team always knows who determines the order of the Product

Backlog.

Question 18

Which of the following are true about the length of the Sprint?

(choose the best answer)

Options:

A.

The length of the Sprint should be proportional to the work that is done in between

Sprints.

B.

All Sprints must be one month or less.

C.

Sprint length is determined during Sprint Planning, and should hold the time it will

take to build the planned features in the upcoming Sprint, but does not include time

for any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough to

make sure the Scrum Team can deliver what is to be accomplished in the upcoming

Sprint

Question 19

Who is on the Scrum Team?

(choose all that apply)

Options:

A.

Scrum Master.

B.

Product Owner.

C.

Developers.

D.

Project Manager.

E.

None of the above.

Question 20

Which best describes the Product Backlog?

(choose the best answer)

Options:

A.

It is allowed to grow and change as more is learned about the product and its

customers.

B.

It contains all foreseeable tasks and requirements from which the Scrum Team can

develop and maintain a complete project plan.

C.

It provides just enough information to enable a Scrum Team to start the design phase

of a product.

D.

It is baselined to follow change management processes.

Question 21

True or False: Multiple Scrum Teams working on the same product or system all select work

from the same Product Backlog.

Options:

A.

True

B.

False

Question 22

Who is accountable for tracking the remaining work toward the Sprint Goal?

(choose the best answer)

Options:

A.

The Developers.

B.

The Project Manager.

C.

The Product Owner.

D.

The Scrum Master.

Question 23

When is the Sprint Backlog created?

(choose the best answer)

Options:

A.

Prior to Sprint Planning.

B.

During refinement.

C.

During the Sprint Retrospective.

D.

During Sprint Planning.

Question 24

The Developers find out during the Sprint that they are not likely to build everything they forecast. What would you expect a Product Owner to do?

(choose the best answer)

Options:

A.

Skip Product Backlog refinement activities.

B.

Inform management that more Developers are needed.

C.

Change the Sprint Goal.

D.

Re-work the selected Product Backlog items with the Developers to meet the Sprint Goal.

E.

Cancel the Sprint.

Question 25

When does the second Sprint start?

(choose the best answer)

Options:

A.

After the customer completes acceptance testing of the first Sprint.

B.

Once the architectural changes for the second Sprint are approved by the senior

architect.

C.

Immediately after the first Sprint.

D.

After the Product Backlog items for the second Sprint have been selected.

Question 26

How often should Scrum Team membership change?

(choose the best answer)

Options:

A.

Every Sprint to promote shared learning.

B.

As needed, with no special allowance for changes in productivity.

C.

Never, it reduces productivity.

D.

As needed, while taking into account a short-term reduction in productivity.

Question 27

True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.

Options:

A.

True

B.

False

Question 28

What is the Product Owner responsible for during the Sprint Retrospective?

(choose the best answer)

Options:

A.

Summarizing and reporting the discussions to the stakeholders that they represent in

the Scrum Team.

B.

The Product Owner should not take part in Sprint Retrospective.

C.

Participating as a Scrum Team member.

D.

Capturing requirements for the Product Backlog.

Question 29

True or False: A Product Owner is essentially the same thing as a traditional Project Manager.

Options:

A.

True

B.

False

Question 30

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.

The Product Owner with input from the Developers.

B.

The Scrum Master.

C.

The Developers, alone.

D.

The Developers after clarifying requirements with the Product Owner.

E.

The most senior people in the organization, including architects and subject matter

experts.

Question 31

True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.

Options:

A.

True

B.

False

Question 32

Which of the following are appropriate topics for discussion during a Sprint Retrospective?

(choose the best two answers)

Options:

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Question 33

Who owns the Sprint Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The Scrum Team.

C.

The Product Owner.

D.

The Developers.

Question 34

Who creates the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Master

B.

The Scrum Team

C.

The Product Owner

D.

The Developers

Question 35

True or False: Multiple Scrum Teams working on the same product must have the same Sprint

start date.

Options:

A.

True

B.

False

Question 36

True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.

Options:

A.

True

B.

False

Question 37

True or False: A Product Owner should measure product value by the increase in the team's velocity.

Options:

A.

True

B.

False

Question 38

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

Options:

A.

Remove or change selected Product Backlog items.

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

Recruit additional Developers before the work can begin.

D.

Cancel the Sprint.

E.

The Developers work overtime during this Sprint.

Question 39

True or False: To get started in terms of what to build, Scrum requires no more than a Product

Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum

Master to help guide the process.

Options:

A.

True

B.

False

Question 40

User documentation is part of your Definition of Done. However, there are not enough technical

writers for all teams. Your Scrum Team does not have a technical writer. What should the

Scrum Team do?

(choose the best answer)

Options:

A.

The Developers on the Scrum Team should write the user documentation.

B.

Wait until you have a technical writer on your Scrum Team to take care of this.

C.

Form a separate team of technical writers that will work on an on-demand basis for

the various Product Owners. Work order will be first in, first out.

D.

Let the user documentation remain undone and accumulate until after the last

development Sprint. It will then be done by any available technical writers.

Question 41

Which statement best describes the Sprint Backlog as the output of the Sprint Planning?

(choose the best answer)

Options:

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Developers plan for the Sprint.

E.

It is ordered by the Product Owner.

Question 42

Which statement best describes Scrum?

(choose the best answer)

Options:

A.

A defined and predictive process that conforms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A framework to generate value through adaptive solutions for complex problems.

D.

A cookbook that defines best practices for software development.

Question 43

True or False: The value delivered by a product can only be determined by revenue.

Options:

A.

True

B.

False

Question 44

How much of the Sprint Backlog must be defined during the Sprint Planning event?

(choose the best answer)

Options:

A.

Just enough to understand design and architectural implications.

B.

Enough so the Developers can create their forecast of what work they can do.

C.

The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.

D.

Just enough tasks for the Scrum Master to be confident in the Developers'

understanding of the Sprint.

Question 45

True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.

Options:

A.

True

B.

False

Question 46

When does a Sprint conclude?

(choose the best answer)

Options:

A.

When all the tasks are completed by the Developers.

B.

When the Sprint Retrospective is complete.

C.

When all Product Backlog items meet their Definition of Done.

D.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

Question 47

At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the

Definition of Done. What two things should happen with the undone Product Backlog item?

(choose the best two answers)

Options:

A.

Review the item, add the done part of the estimate to the velocity and create a

Story for the remaining work.

B.

If the stakeholders agree, the Product Owner can accept it and release it to the

users.

C.

Do not include the item in the Increment this Sprint.

D.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

Question 48

What may be included in the Sprint Backlog?

(choose the best answer)

Options:

A.

User Stories.

B.

Tasks.

C.

Use Cases.

D.

Tests.

E.

Any of the above (or others) which are a decomposition of the selected Product

Backlog items.

Question 49

During the Sprint Retrospective a Scrum Team has identified several high priority process

improvements. Which of the following statements is most accurate?

(choose the best answer)

Options:

A.

The Scrum Team may add the items to the Sprint Backlog for the next Sprint.

B.

The Scrum Team should decline to add a process improvement to the Sprint Backlog

when things are running smoothly.

C.

The Scrum Team should choose at least one high priority process improvement to

place in the Product Backlog.

D.

The Scrum Master selects the most important process improvement and places it in

the Sprint Backlog

Question 50

True or False: The Product Owner makes sure the correct stakeholders are invited to the Sprint Retrospective. They might have important instructions for team improvements.

Options:

A.

True

B.

False

Question 51

True or False: Every Scrum Team must have a Product Owner and Scrum Master.

Options:

A.

False. A Scrum Master is only required when asked for by the Scrum Team.

B.

True. Each must be 100% dedicated to the Scrum Team.

C.

False. A Product Owner can be replaced by a subject matter expert in the Scrum

Team.

D.

True. Outcomes are affected by their participation and availability.

Question 52

What is a Product Owner typically responsible for during a Sprint?

(choose the best two answers)

Options:

A.

Attending every Daily Scrum to answer questions about the Sprint Backlog

items.

B.

Creating financial reporting upon the spent hours reported by the Developers.

C.

Nothing.

D.

Updating the work plan for the Developers on a daily basis.

E.

Collaborating with stakeholders, users, and customers.

F.

Working with the Scrum Team on Product Backlog refinement.

Question 53

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?

(choose the best answer)

Options:

A.

Find another Scrum Team to give the excess work to.

B.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

C.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

D.

Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.

Page: 1 / 18
Total 177 questions