Black Friday Biggest Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

Scrum SPS Dumps

Page: 1 / 4
Total 40 questions

Scaled Professional Scrum (SPS) Exam Questions and Answers

Question 1

True or False: A Nexus Integration Team is accountable for ensuring that a Integrated

Increment is produced at least once a Sprint.

Options:

A.

True

B.

False

Question 2

What are three benefits of self-managing Scrum Teams?

(choose the best three answers)

Options:

A.

Increased rule compliance.

B.

Increased self-accountability.

C.

Increased creativity.

D.

Increased commitment.

E.

Increased accuracy of estimates.

Question 3

The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver

a valuable and useful Increment. What could they try to improve their ability to produce an

Increment for the next Sprint?

(choose the best answer)

Options:

A.

Reduce the amount of work that the teams pull into the Sprint.

B.

Ask the Nexus Integration Team to extend the Sprint to allow more time for

integration.

C.

Reduce the number of Scrum Teams to reduce complexity.

D.

Add another Scrum Team to the Nexus to increase capacity.

Question 4

The purpose of a Nexus Sprint Retrospective is to:

(choose the best two answers)

Options:

A.

Enable bottom-up intelligence to improve how the Scrum Teams in a Nexus are

working together.

B.

Provide a forum for management to see how the Nexus is performing.

C.

Allow for inspection and adaptation of both individual Scrum Teams and a

Nexus.

D.

Provide a single meeting to inspect and adapt how all Scrum Teams work

together.

Question 5

The purpose of the Nexus Integration Team is to:

(choose the best two answers)

Options:

A.

Raise transparency.

B.

Manage the Nexus.

C.

Be accountable that an Integrated Increment is produced.

D.

Integrate the work of the Scrum Teams.

Question 6

How should Product Backlog items be chosen when multiple Scrum Teams work from the same

Product Backlog?

(choose the best answer)

Options:

A.

The Scrum Teams choose the Weighted Shortest Job First.

B.

The Developers pull work in agreement with the Product Owner.

C.

Each Scrum Team takes an equal number of items.

D.

The Scrum Team with the highest velocity pulls Product Backlog items first.

E.

The Product Owner should provide each team with its own Product Backlog.

Question 7

If two Scrum Teams are added to a product that previously had only one Scrum Team, what will

be the immediate impact on the productivity of the original Scrum Team?

(choose the best answer)

Options:

A.

Its productivity is likely to stay the same.

B.

Its productivity is likely to decrease.

C.

Its productivity is likely to increase.

Question 8

A Nexus Daily Scrum:

(choose the best two answers)

Options:

A.

Provides a single meeting where all Scrum Teams can update the Sprint

Backlog.

B.

Is the same as a Scrum-of-Scrums.

C.

Provides input into each Scrum Team's individual Daily Scrums to help them

better plan their days work.

D.

Is only for the Nexus Integration Team to plan their work for the next 24-hours.

E.

Is an opportunity to make integration issues transparent.

Question 9

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Which of the following practices could this Nexus try in order to conduct Nexus Sprint Planning

more effectively?

(choose the best two answers)

Options:

A.

Ensure all Scrum Teams and outside experts are available during the Nexus

Sprint Planning event and have a way of quickly communicating with each other.

They should try to be together in the same room or use technology that makes it

seem as if they are in the same room.

B.

Plan one Scrum Team's Sprint at a time before moving on to the next team. This

way you can account for time zone differences and can communicate

dependencies across all teams.

C.

Have the Nexus Integration Team select the work for each of the individual

Scrum Teams. This allows the Nexus Integration Team to control the

dependencies.

D.

Visualize the known dependencies in the Product Backlog for all to see. As

Scrum Teams select work for the Sprint, they can easily check for any

dependent work and communicate with other teams.

Question 10

You have been assigned as the Scrum Master of six new Scrum Teams that will build one

product. What conditions should you strive for in this scenario?

(choose the best two answers)

Options:

A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, one of whom is chief Product Owner.

C.

The product has one Product Backlog.

D.

There should be only one Product Owner who is accountable for the success of

the product.

E.

Each Scrum Team should have a separate Product Backlog.

Question 11

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What would you recommend to the two teams that are continually dependent on each other to

help them manage their work?

(choose the best answer)

Options:

A.

The Nexus Integration Team should be responsible for integrating the work of these

two Scrum Teams.

B.

Reorganize these two Scrum Teams so that one is responsible for development and

one is responsible for integration.

C.

Merge the two Scrum Teams together.

D.

Ensure the appropriate representatives from both teams are present during Cross-

Team Refinement.

Question 12

During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so

the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on

Team Red completing PBI 1.

as

All else being equal, which PBI is most concerning?

(choose the best answer)

Options:

A.

PBI 2, because it has the most dependencies.

B.

PBI 1, because it is on the top of the Product Backlog.

C.

PBI 1, because it is the first piece of work with a dependency.

D.

PBI 2, because there is a dependency with a different team on work that occurs

within the same Sprint.

Page: 1 / 4
Total 40 questions