Black Friday Biggest Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

Scrum PSM-I Dumps

Page: 1 / 25
Total 250 questions

Professional Scrum Master I Questions and Answers

Question 1

Which of the following best describes an increment of working software?

Options:

A.

A decomposition of all Product Backlog items into tasks for future Sprint Backlog lists.

B.

Additional features in a usable state that complement those delivered in previous iterations.

C.

A new user interface design for functionality delivered in previous iterations.

D.

An automated test suite to verify functionality delivered in previous iterations.

E.

UML diagrams that describe how to deliver functionality in future iterations.

Question 2

What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)

Options:

A.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

B.

Add security concerns to the definition of “Done”.

C.

Add a Sprint to specifically resolve all security concerns.

D.

Delegate the work to the concerned department.

E.

Have the Scrum Team create Product Backlog items for each concern.

Question 3

What does it mean for a Development Team to be cross-functional?

Options:

A.

The Development Team includes not only developers but also business analysts, architects, and testers.

B.

The Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software.

C.

Developers on the Development Team work closely with business analysts, architects, developers and testers who are not on the team.

D.

The Development Team is a virtual team drawing from separate teams of business analysts, architects, developers and testers.

Question 4

Why does a Development Team need a Sprint Goal?

Options:

A.

A Sprint Goal only gives purpose to Sprint 0.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Development Team is more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

Question 5

Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply.)

Options:

A.

Definition of “Done”.

B.

How the team does its work.

C.

Team relations.

D.

The value of work currently represented in the Product Backlog.

E.

Arranging the Sprint Backlog for the next Sprint.

Question 6

How often should Development Team membership change?

Options:

A.

As needed, while taking into account a short term reduction in productivity.

B.

Never, because it reduces productivity.

C.

As needed, with no special allowance for changes in productivity.

D.

Every Sprint to promote shared learning.

Question 7

A Scrum Master is essentially the same thing as a traditional PM (Project Manager).

Options:

A.

True

B.

False

Question 8

A Scrum Team is experiencing a growing list of impediments. Which techniques would be most

helpful in this situation?

(choose the best two answers)

Options:

A.

As a Scrum Team, prioritize the list and work on them in order.

B.

The Scrum Master discusses the impediments with the Scrum Team.

C.

The Product Owner should add the open impediments to the Product Backlog.

D.

Arrange a triage meeting with management.

Question 9

A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint

Retrospective is unnecessary. What action should the Scrum Master take?

(choose the best answer)

Options:

A.

Comply with the decision of the self-managing team.

B.

Begin facilitating productive and useful Sprint Retrospectives.

C.

Call a meeting between the ScrumTeam and senior management

D.

Consult with the Product Owner to see how they feel about the situation.

Question 10

Who must attend the Daily Scrum?

Options:

A.

The Scrum Master and Product Owner.

B.

The Development Team.

C.

The Development Team and Product Owner.

D.

The Scrum Team.

E.

The Development Team and Scrum Master.

Question 11

For the purpose of transparency, when does Scrum say a new increment of working software must be available?

Options:

A.

After the acceptance testing phase.

B.

Before the release Sprint.

C.

Every 3 Sprints.

D.

At the end of every Sprint.

E.

When the Product Owner asks to create one.

Question 12

When can a Development Team cancel a Sprint?

Options:

A.

It can’t. Only Product Owners can cancel Sprints.

B.

When functional expectations are not well understood.

C.

When the Product Owner is absent too often.

D.

When the selected Product Backlog items for the Sprint become unachievable.

E.

When a technical dependency cannot be resolved.

Question 13

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)

Options:

A.

Consulting with the Development Team.

B.

Prioritizing the list and working on them in order.

C.

Arranging a triage meeting with all project managers.

D.

Alerting management to the impediments and their impact.

Question 14

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

Options:

A.

A proportional amount of time on analysis, design, programming, testing, and documentation.

B.

As much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.

C.

All development work and at least some testing.

D.

As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of “Done”.

Question 15

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

Options:

A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

Question 16

When does the next Sprint begin?

Options:

A.

When the Product Owner is ready.

B.

Immediately after the conclusion of the previous Sprint.

C.

The Monday following the Sprint Review.

D.

Immediately following the next Sprint Planning.

Question 17

Who is accountable for clearly expressing Product Backlog items? (Choose the best answer.)

Options:

A.

The business analyst who represents the Product Owner.

B.

The Product Owner.

C.

The Scrum Master, or the Scrum Master may have the Developers do it.

D.

The Scrum Master.

Question 18

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Analyze, design, and describe the complete architecture and infrastructure.

E.

Create an increment of potentially releasable software.

Question 19

Which two things should the Scrum Team do during the first Sprint?

(choose the best two answers)

Options:

A.

Define the major product features and a release plan architecture.

B.

Build at least one piece of valuable functionality.

C.

Create at least one valuable, useful Increment

D.

Make up a plan tor the rest of the project

E.

Analyze, describe, and document the requirements for the subsequent Sprints.

Question 20

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

Options:

A.

Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

B.

It depends.

C.

Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.

D.

All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.

Question 21

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Options:

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Question 22

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Question 23

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

Options:

A.

There should be six Product Owners, one tor each Scrum Team.

B.

There should be six Product Owners, reporting to a Chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Question 24

Which best describes the Product Backlog?

Options:

A.

It is allowed to grow and change as more is learned about the product and its customers.

B.

It provides just enough information to enable a Scrum team to start the design phase of a product.

C.

It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.

D.

It is baselined to follow change management processes.

Question 25

Which three of the following are true about Scrum? (Choose the best three answers.)

Options:

A.

Scrum implements self-management by replacing Project Managers with Scrum Masters.

B.

Each component of Scrum serves a specific purpose and is essential to Scrum’s success and your usage

of Scrum to develop complex products.

C.

Scrum is a methodology where you can pick and choose which parts of Scrum you think will work for your

environment.

D.

Scrum is a framework for developing and sustaining complex products.

E.

Scrum is based on empiricism and lean thinking.

Question 26

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

Options:

A.

True

B.

False

Question 27

When should a Sprint Goal be created?

Options:

A.

It should have been created in the previous Sprint during Product Backlog refinement.

B.

It must be established before Sprint Planning in order to begin planning.

C.

A Sprint Goal is not mandatory in Scrum.

D.

At any time during the Sprint.

E.

During Sprint Planning.

Question 28

Who is accountable for managing the progress ot work during a Sprint?

(choose the best answer)

Options:

A.

The Product Owner.

B.

The Developers.

C.

The Scrum Master.

D.

The most junior member ot the team.

Question 29

Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).

Options:

A.

True

B.

False

Question 30

Who creates the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Master

B.

The Product Owner

C.

The scrum Team

D.

The Developers

Question 31

When must a scrum Team release each increment? (choose the best answer)

Options:

A.

when the Scrum Team finishes their work

B.

Alter every Sprint. without exception

C.

Whenever the product s tree of detects

D.

When it makes sense to release It.

Question 32

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

Options:

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Question 33

During a Sprint Retrospective, for what is the Product Owner responsible?

Options:

A.

Participating as a Scrum Team member.

B.

Summarizing and reporting the discussions to the stakeholders that he/she represents in the Scrum Team.

C.

Capturing requirements for the Product Backlog.

D.

The Product Owner should not take part in Sprint Retrospectives.

Question 34

Which of the following is a Developer accountable for? (Choose the best two answers.)

Options:

A.

Selecting the Product Owner.

B.

Reporting productivity.

C.

Creating a plan for the Sprint, the Sprint Backlog.

D.

Organizing the work required to meet the Sprint Goal.

Question 35

Who is on the Scrum Team? (Choose all that apply.)

Options:

A.

Scrum Master

B.

Product Owner

C.

Development Team member

D.

Project Manager

E.

None of the above

Question 36

Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)

Options:

A.

Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of “Done” accordingly.

B.

Encourage the Product Owner to accept partially “Done” increments until the situation improves.

C.

Refocus the current Sprint on establishing the Development Team’s infrastructure instead of delivering an increment.

D.

Declare the Development Team not ready for Scrum.

E.

Have the Development Team establish a Definition of “Done” that is actually possible to achieve given current circumstances.

Question 37

Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?

Options:

A.

Lead the discussions of the Development Team.

B.

Make sure that all 3 questions have been answered by each member of the team.

C.

Keep track of whether each team member has a chance to speak.

D.

Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.

E.

All of the above.

Question 38

Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)

Options:

A.

How is the Sprint proceeding?

B.

What did I do yesterday that helped the Development Team meet the Sprint Goal?

C.

Why were you late?

D.

What will I do today to help the Development Team meet the Sprint Goal?

E.

How many hours did I spend on the project yesterday?

F.

What will I be working on tomorrow?

G.

Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?

Question 39

A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?

Options:

A.

Add security to the definition of “Done”.

B.

Tell the Product Owner to stop further development of features until the issues are fixed.

C.

Create a Product Backlog item for security.

D.

Go check with the testers.

E.

Ask the person to share the issue with the team as soon as possible.

Question 40

user documentation is part ot your Definition ot Done. However, there are not enough technical

writers for all teams. Your Scrum Team does not have a technical writer. What should the

Scrum Team do?

(choose the best answer)

Options:

A.

The Developers on the Scrum Team should write the user documentatiom

B.

Wait until you have a technical writer on your Scrum Team to take care of this.

C.

Form a separate team of technical writers that will work on an on-demand basis tor

the various Product Owners. Work order will be first in, first out.

D.

Let the user documentation remain undone and accumulate until after the last

development Sprint. It will then be done by any available technical writers.

Question 41

What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)

Options:

A.

Put them on a separate list on the Scrum board, available for all to see.

B.

Add them to the Product Backlog and keep the Product Owner posted on the expected effort.

C.

Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.

D.

Add them to the definition of “Done” so the work is taken care of every Sprint.

Question 42

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

Options:

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Question 43

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

Options:

A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Question 44

Which three of the following are time-boxed events in Scrum? (Choose three.)

Options:

A.

Release Testing.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Question 45

Scrum has a role called “Project Manager”.

Options:

A.

True

B.

False

Question 46

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

Options:

A.

The Scrum Team includes not only developers but also business analysts, architects, and testers.

B.

The Scrum Team includes skilled individuals who together have all the skills

necessary to create value each Sprint.

C.

Developers on the Scrum Team work closely with business analysts, architects,

developers, and testers who are not on the team.

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers.

Question 47

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

Options:

A.

True

B.

False

Question 48

Who should know the most about the progress toward a business objective or a release?

Options:

A.

The Project Manager.

B.

The Scrum Master.

C.

The Development Team.

D.

The Product Owner.

Question 49

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.

The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

Options:

A.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

B.

Tell the Development Team to figure it out themselves.

C.

Tell the Development Team to fit the report into the Sprint Backlog.

D.

Create and deliver the report to the manager herself.

E.

Ask the Product Owner to send the manager the report.

Question 50

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

Options:

A.

The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint

B.

Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team

C.

The Scrum Team includes not only developers but also business analysts, architects, and testers

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers

Question 51

Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)

Options:

A.

You cannot do Scrum without feature teams.

B.

Productivity may suffer when making this kind of move.

C.

Getting support from the business side first helps.

D.

Feature teams have less communication overhead.

E.

With feature teams, it is easier to calculate the productivity per team.

Question 52

What is the time-box for the Sprint Review?

Options:

A.

As long as needed.

B.

2 hours for a monthly Sprint.

C.

4 hours for a monthly Sprint.

D.

4 hours and longer as needed.

E.

1 day

Question 53

Which are properties of the Daily Scrum? (Choose two.)

Options:

A.

It is facilitated by the team lead.

B.

It is held first thing in the morning.

C.

It is fifteen minutes or less in duration.

D.

It is free from and designed to promote conversation.

E.

It consists of the Scrum Master asking the Team members the three questions.

F.

Its location and time remain constant.

Question 54

A product Increment must be released to production at the end of each Sprint.

Options:

A.

True

B.

False

Question 55

Which two ways of creating Development Teams are consistent with Scrum’s values? (Choose two.)

Options:

A.

Existing teams propose how they would like to go about organizing into the new structure.

B.

Managers personally re-assign current subordinates to new teams.

C.

Managers collaborate to assign individuals to specific teams.

D.

Bring all the developers together and let them self-organize into Development Teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Question 56

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Options:

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Question 57

What are two ways that regulatory compliance issues are dealt with in Scrum?

(choose the best two answers)

Options:

A.

They are addressed by a separate team who is responsible for compliance

issues.

B.

They are addressed along with functional development of the product.

C.

They are discussed, determined, and documented before the actual feature

development Sprints.

D.

They are added to the Product Backlog and addressed in early Sprints, while

always requiring at least some business functionality, no matter how small.

Question 58

Who creates a Product Backlog Item’s estimate?

Options:

A.

The Development Team after clarifying requirements with the Product Owner.

B.

The Product Owner with input from the Development Team.

C.

The most senior people in the organization, including architects and subject matter experts.

D.

The Scrum Master.

E.

The Development Team, alone.

Question 59

What is the best suited structure for Development Teams in order to produce integrated Increments?

Options:

A.

Each Development Team works only one technical layer of the system (e.g. GUI, database, middle tier, interfaces).

B.

Each Development Team develops functionality from beginning to end throughout all technical layers.

Question 60

Why does the Product Owner want the Development Team to adhere to its definition of “Done”?

Options:

A.

To have complete transparency into what has been done at the end of each Sprint.

B.

To be able to reprimand the team when they don’t meet their velocity goal for the Sprint.

C.

To know what the team will deliver over the next three Sprints.

D.

To predict the team’s productivity over time.

Question 61

Who determines how many Product Backlog items the Developers select tor a sprint? (choose the best answer)

Options:

A.

The Scrum Master

B.

The Scrum Team

C.

The Developers

D.

The stakeholders attending Sprint Planning

E.

The Product Owner

Question 62

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)

Options:

A.

A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.

C.

A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.

D.

An updated Scrum board to make Sprint progress transparent for the stakeholders.

E.

New impediments for the Scrum Master to take care of.

Question 63

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

Options:

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the Development Team.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Question 64

Select two ways in which technical debt impacts transparency. (Choose two.)

Options:

A.

When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.

B.

It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.

C.

As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.

D.

It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.

Question 65

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

Options:

A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Question 66

Who starts the Daily Scrum?

Options:

A.

The person coming in last. This encourages people to be on time and helps to stay within the time-box.

B.

Whoever the Development Team decides should start.

C.

The person who has the token.

D.

The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

E.

The person who last broke the build.

Question 67

How do you know that a Development Team is cross-functional?

Options:

A.

Development Team has all the skills to create a potentially releasable increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Development Team.

D.

Every member of the Development Team is able to perform every task.

Question 68

What is the key concern when multiple Development Teams are working from the same Product Backlog?

Options:

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

Question 69

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started

using the product. The stakeholder is unhappy with the quality of the product. What are two good options for the

Scrum Master? (Choose the best two answers.)

Options:

A.

Wait to bring this up until the Sprint Retrospective.

B.

Encourage the Product Owner to put quality specifications on the Product Backlog and express the

stakeholder’s concern to the Developers.

C.

Bring the concern to the testers to improve how the Product is verified.

D.

Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.

E.

Coach the Product Owner on how to talk with the Developers about this concern.

Question 70

When might a Sprint be abnormally cancelled?

Options:

A.

When the Development Team feels that the work is too hard.

B.

When the Sprint Goal becomes obsolete.

C.

When the sales department has an important new opportunity.

D.

When it becomes clear that not everything will be finished by the end of the Sprint.

Question 71

Who has the final say on the order of the Product Backlog?

Options:

A.

The Development Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Stakeholders.

E.

The CEO.

Question 72

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

Options:

A.

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Question 73

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Options:

A.

The Scrum Team.

B.

The Product Owner.

C.

The Developers.

D.

The Project Manager.

Question 74

A Scrum Team is only allowed to meet with stakeholders during Sprint Review.

Options:

A.

True

B.

False

Question 75

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

Options:

A.

By ensuring the meetings start and end at the proper time.

B.

By removing impediments that hinder the Development Team.

C.

By facilitating Development Team decisions.

D.

By keeping high value features high in the Product Backlog.

Page: 1 / 25
Total 250 questions